Professional Documents
Culture Documents
OF SUB TRANSMISSION,
DISTRIBUION LINES & SUBEr. K.V. Surya Prakasa Rao, Former
STATIONS
SE/APTRANSCO
is
Permissible Voltage
Variations:
Up to 650V supply
+ 6%
+ 6% ; - 9%
132 KV
+ 10.0%; - 12.5%
220KV
+ 5%
Pole
Line
(mts)
PSCC
9.1 meters
33KV
100
PSCC
8.0 meters
11KV
107
PSCC
8.0 meters
415/240V
67
Support Formation
Conductor:
The table below gives sizes and other details of conductors standardized
for use in subtransmission and distribution system for various types of
lines. These are:
ACSR Aluminium Conductors Steel Reinforced
AAC All Aluminium Conductors
AAAC Aluminium
Conductors
Voltage
No. andAlloy
Diameter
of Wire
Class
33 KV Lines
Type of
Conductor
Resistance /
KM
ACSR (AAAC)
ACSR (AAAC)
ACSR (AAAC)
0.5524 OHMS
0.3712 OHMS
0.2792 OHMS
11 KV Lines
ACSR (AAAC)
ACSR (AAAC)
ACSR (AAAC)
1.394 OHMS
0.9289 OHMS
0.5524 OHMS
LT Lines
1.
2.
3.
4.
5.
ACSR (AAAC)
ACSR (AAAC)
ACSR (AAAC)
AAC (AAAC)
AAC (AAAC)
1.394 OHMS
0.9289 OHMS
0.5524 OHMS
1.306 OHMS
0.5524 OHMS
7/2.11
7/2.59
7/3.35
7/2.21
7/3.10
mm
mm
mm
mm
mm
(20
(30
(50
(25
(50
mm2)
mm2)
mm2)
mm2)
mm2)
Stay Wire:
Stay Wires are used for anchoring of power line
poles at dead ends and at angular locations. The
individual wire used to form stranded stay
wire is to be of Tensile grade 4 having minimum
tensile strength of 700 N / mm2 as per IS2141.
Three sizes have been standardized and are
No. of
Wires & below:
Wire Dia
Minimum
Minimum
tabulated
Const.
(mm)
Breaking Load
of Single - Wire
Before
Stranding (KN)
Breaking Load
of Line
Stranded Wire
(KN)
7 (6/1)
2.5
3.44
22.86
7 (6/1)
3.15
5.45
36.26
7 (6/1)
4.0
8.79
58.45
Factor of Safety:
The factor of safety
adopted is 2 with the
following
loads:
Working
Load working
on Wind Pressure
Pole
Zone (where to be
used)
1.200 kg
2.300 kg
3.400 kg
50 kg / m2
75 kg / m2
100 kg / m2
Code
Size
Mm
Conduc
tor
W.R. 75 kg /
m2
W.R.100 kg /
m2
W.R.150 kg /
m2
Dog
6/4.72+
7/1.57
ASCR
0.472
0.757
0.943
1.415
Racoon
7/4.09
ASCR
0.409
0.613
0.818
1.227
Rabbit
7/3.35
ASCR
0.335
0.502
0.670
1.005
Weasel
7/2.59
ASCR
0.259
0.388
0.518
0.777
Squirrel
7/2.11
ASCR
0.211
0.316
0.422
0.633
Amt.
7/3.1
AAC
0.310
0.465
0.620
0.930
Gnat
7/2.21
AAC
0.221
0.331
0.442
0.663
Dog
(equivalent)
7/4.26
AAAC
0.426
0.639
0.852
1.278
Racoon
7/3.81
AAAC
0.381
0.572
0.762
1.143
Rabbit
7/3.15
AAAC
0.315
0.472
0.630
0.945
Weasel
7/2.5
AAAC
0.250
0.375
0.500
0.750
Squirrel
7/2.0
AAAC
0.200
0.300
0.400
0.600
Ground Clearance:
Clearance above ground of the lowest conductor (including
guard wires) is to meet the following conditions:
1. No conductor of an overhead line including service lines
erected across a street shall be at any part there of be at a
height less than:
a) For low & medium voltage line (i.e. up to 650 volts) 5.791
mts
b) For high voltage lines (up to 33 KV)
6.096 mts
2. Along a street:
a) For low& medium voltage lines
_5.486 mts
b) For high voltage lines(up to 33 KV)
_ 5.794
mts
3.Elsewhere other than 1,2 above
a) For high voltage up to 11KV
- 4.572 mts
b) For HV line above 11 KV but up to 33KV - 5.182 mts
Ground Clearance:
a.
b.
i)
ii)
Construction of
Lines
Construction Practice
Detailed Survey
(a) Preliminary Walk Over survey
(b) Detailed survey
Right of Way
(a) Once the route of the line is fixed approval has
to be obtained,
Pole Locations
Construction
The construction activity of H.T. lines may b& divided as follows
(1) Pit marking, pit digging.
(2) Erection of supports and concreting.
(3) Providing of guys to supports.
(4) Mounting cross-arms, phi and insulators, and pin binding.
(5) Paying and stringing of the conductor.
.
(6) Jointing of conductors.
(7) Sagging and tensioning of conductors.
(8) Crossings.
(9) Guardings.
(10) Earthings.
(11) Testing and commissioning
For low tension lines the activities could be followed, with
simplified procedure.
Pully
' --
"'
;ff y.|"V"J'.""'
Concreting
33 KV Line
(i)
llkVLine
The guys are made with 7/3.15 stay wire (5.5 kg)
turnbuckle rod is of 16 mm dia. 6 Guy-sets are
required at D.P. locations and 4 additional Guysets are required in a km for 8 tangent-locations.
The quantity of concrete for Guy-sets is provided
at the rate of 0.2 cum per Guy-set. D.P. locations
of P.C.C. poles require 0.3 cum concrete per
location. Boulder filling of tangent locations could
be adopted. If concreting is done for tangent
locations additional provision at the rate of 0.3
cum per location should be made. Base-pad is to
be used if not additional provision for base^pad
concreting should be made
LTLine
phase
in
There are two important factors which vary the sag and
tension : (i) Elasticity of the conductor and (ii) Temperature.
Sag is directly proportional to Wand inversely proportional to
T. If the length of the conductor increases due to temperature
increase then sag will increase. This may be the case in
summer, while it may be reverse in winter. The tension
accordingly decreases or increases.
In order that the sag and tension values under varied working
conditions may be kept according to the regulations, SagTension charts are prepared for different spans and
temperatures for ACSR, AAAC & AAC conductor.
Special Crossings
(A) In case the lines cross-over the other lines or buildings, safe
minimum clearances are to be maintained as per IE Regulations.
The clearances have been tabulated for this purpose under design
aspects. These clearances should be maintained. The crossings
could be for j
(i) Telephone/telegraph lines.
(ii) Buildings..
(w) Lines of other voltages.
(iv) Roads, streets, other than Roads/Streets.
(B) River Crossing: Data for the highest flood-level should be obtained
'for previous years. For medium voltage minimum clearance of 3 m
be kept over the highest floor level. Double pole or 4 pole structure
would be required to be specially designed, depending upon the
span and conductor size for the river crossing. The structures
should be located at such places that they could be approached
under flood condition, also. The foundation of structures should be
sound so that it may not get eroded or damaged due to rain water
Guarding
Earthing
1
2.
3
4
5
Anti-climbing Devices
Functional Responsibility
Sl.
No
Particular of Works
Sub Division
Division
Constn Gang
Head
AE (CSD)
EE ( O & M)
EE ST/RE (Const)
Supervision
Forest Clearance
PTCC Approval
Supervision
Identity of materials
Supervision
Material lifting
Supervision
Checking
10
Supervision
11
Supervision
Sample Check
12
Supervision
Sample Check
13
Fixing of insulators
Supervision
Sample Check
14
Supervision
Sample Check
15
Stringing of conductor
Supervision
Sample Check
16
Supervision
Sample Check
17
Guardining at crossing
Supervision
Sample Check
18
Supervision
Sample Check
19
Supervision
Sample Check
20
Supervision
Sample Check
21
Connecton of earth
Supervision
Sample Check
22
Supervision
Sample Check
23
Supervision
Sample Check
24
Supervision
Sample Check
Sl. No
Particular of Works
Sub Division
Division
AE (CSD)
EE ( O & M)
EE ST/RE (Const)
-
Supervision
Supervision
Identity of materials
Sample check
Lifting of material
Supervision
check
supervision
Supervision
Sample check
10
Supervision
Sample check
11
Supervision
Sample check
12
Stringing of conductor
Supervision
Sample check
13
Supervision
Sample check
14
Guardining at crossing
Supervision
Sample check
15
Supervision
Sample check
16
Supervision
Sample check
17
Earth connection
Supervision
Sample check
18
Sample check
19
Sample check
20
checking
Sample check
Sample check
REC has standardized the following sizes and types of supports for
11 KV and LT lines
Type
Length
Voltage
Max Spn
Type of
With or
without
earth wire
PCC
7.5 Mt
11 KV
107
Triangular
Without
earth wire
PCC
8.0 Mt
11 KV
107
Triangular
With
earthwire
PCC
7.5 Mt
415/240 V
107
Horizantal
With
earthwire
PCC
8.0 Mt
415/240 V
67
Vertical
With
earthwire
REC has standardized the following sizes of conductors for 33 KV, 11 KV and LT lines
Voltage Class
33 KV Lines
11 KV Lines
LT Lines
Type of conductor
ACSR
ACSR
ACSR
ACSR
ACSR
ACSR
i) 7/2.11 mm ( 20 mm2)
ACSR
ACSR
ACSR
AAC
AAC
COIL EARTHING
Earthing Spiral
Bentonite power
PIPE/ROD EARTHING
COIL EARTHING
Earthing Spiral
Bentonite power
PIPE/ROD EARTHING
Construction Standard
F-5
EARTHING ARRANGEMENT
Transformer Body /AB
Handle /Earth
Terminal of Pole
6500mm
J2
Neutral
Note:
11KV /433-250V
Substation
Location Of Earth Pits And
Connections
1.
1.Generation
2.Transmission
3.Sub transmission
4.Distribution
1.
2.
3.
4.
5.
6.
7.
8.
Classification of Distribution
System
1.Radial System
2.Looped System
3.Net work system
2.
Connecting loads.
Lighting loads
Power loads
Heating loads
Electronic loads
Consumer factors.
Maximum Demand
Demand factor
Load factor
Diversity factor
Utilization factor
Power factor
Safety
Providing quality service to the people
to lay down technical parameters and
specifications of materials to follow
standards in construction, installation
protection, operation & maintence.
to follow laid down principles &
procedures with accountability to people.
a)Ground clearances
Across Street
i) up to 650V
5.791 mt
5.486 mt
4.572 mt
ii) 650 V to 33 KV
6.096 mt
5.791 mts
5.182 mt
Horizontal clearances
i) up to 650V
2.439 mt ( 8ft)
ii) 650 V to 33 KV
3.64 mt (12ft)
1.82 mt ( 6ft)
Temperatures
Voltage Regulation
Frequency Variation
Maximum clearance between supports
Earthing
Lightning Protection
Insulator & Insulator fittings
Protection.
12.Earthing
arrangement
13.Station Transformer
14.Control room
15.Communication Equipment
16.Fencing, Retaining wall
17.Illumination, firefighting equipment, quarter
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
1.
2.
3.
4.
5.
6.
2.
3.
4.
5.
11 KV FEEDER
Examine the switch yard for any visible fault, If no fault is noticed,
open line isolator.
00.04. Charge lne OCB if OK, Trip the OCB,
officers concerned.
CASE II
33 KV feeder breaker (p) Trips at 132 KV sub station 'M'
00.01 Note the relay indications, reset, charge the feeder, If OK supply is
restored.
If trips note relay indications, reset
00.03 Charge the feeder If OK supply is restored If Trips note relay
indication, open line isolator.
00.08 Charge the OCB, If trips, inform maintenance personnel for
rectification If OK, hand trip the OCB close line isolator charge the
feeder. If OK supply is restored, if trips proceed as
follows:
Ask the operator to open incoming isolator and 33 KV out going line
isolator Ask him to examine the switch yard and report.
If OK ask operator at 'A' to restore supply to the station 'A' and inform,
If at the time of charging any 11 KV feeder at station 'A' of the 33 KV
If OK supply is restored
CASE III
Power Transformer Trips on
A WINDING TEMPARATURE :
Note the winding temperature is more than the set temperature?
If so, is the transformer overloaded? If sot
reduce the load on the transformer.
.Are the cooler fans, oil pumps functioning satisfactorily?
Is fuse blown out in Fan/Pump? If so, rectify.
Ts there any shortive between the contacts of
winding temperature relay due to vermin or ingress 'of moisture, if
so take remedial action.
B Bucholtz Relay:
Isolate the power transformer check bucholtz relay, is there any gas
collected, if so arrange for testing. If not check any shorting of the
contacts Megger the power transformer close HV/LV breakers. If OK
hand trip, inform maintenance personnel for check up
C Differential Relay
Isolate the power transformer inform maintenance personnel for
detailed check
D O/L Relay.
Check if any feeder relays indication is received without the feeder
breaker tripping isolate the feeder. Check the yard. If ok check is
power transformer is overloaded.
GUIDELINES FOR
ERECTION OF
EQUIPMENT IN THE SUB
STATIONS
Unloading
of
Transformer
form
Tractor
Trailer/Lorry at the Sub Station.
Stacking aside wherever the Power Transformer
plinth etc are not ready.
Moving the transformer on to plinth
Assembly of all the mounting , accessories etc.,
Filling and topping up of transformer oil
Oil circulation through filter if required.
Earthing
Jumpering
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Keep two jacks under jack pads of transformers along the top sleeper ( Which is be
removed one jack each on either and of sleeper)
Operate the Jacks so that lifting pad of jacks are tightly positioned under transformer
jack pads
Now slowly pressurize jacks equally on both sides simultaneously so that one side of the
transformer tank is raised slightly to enable to draw out the sleeper.
Now Place the wooden packing pieces one over the other by the sides of Jacks up to
jack height
Now remove the sleeper slowly with out hitting the jacks
Slowly lower the transformer tank, by releasing pressure in jacks slowly (both
simultaneously) and removing the packing pieces one after another
Now remove the Jacks, when the side of transformer is securely resting on the next
bottom sleepers
Now place the jacks on the other side of the power transformer tank and carry pout
above operation and remove other side sleeper also.
After the transformer tank lowered to the height of one sleeper height, then sleepers
are to be placed along the rout to the plinth on which PTR is to be erected.
ON the sleepers rail poles are to be kept duly inserting under the tank and transformer
tank is to be dragged close to the plinth.
After dragging the transformer tank nearer to plinth the transformer tank is to be raised
to the level slightly above the plinth top level by using sleepers & Hydraulic jack
Then the Power Transformer tank is to be dragged on to the plinth slowly with the help
of rail poles and winch tirfor.
When the transformer tank is correctly positioned placed on the plinth further work is to
be taken up.
Erection of Breakers
Earthing Systems:
Electrical earthing is designed primarily to render electrical installation safe. The
purpose of earthing are :
1. Protection to the plant
2. Protection to the personnel and
3. Improvement in service reliability
Non- current carrying parts with conducting surface such as tanks of Power
Transformers, and frame work of circuits breakers, structural steel work in
switch yard instrument transformer cases, lightning arresters and armored
cables armoring should be effectively grounded for protection of equipments
and operating personnel. Earth connections of all equipments should be
made in duplicate.
Connecting lead should have sufficient current carrying capacity.
L A s should have independent earth electrode which should be inter connected
to the station grounding system.
All paints, enamel, seals should be removed from the point off contact of metal
surfaces before earth connections are made.
The resistances of earth system should not exceed 2 ohms for 33/11 KV Sub
Stations.
But in the sub stations of Distribution companies Earth resistance Maximum of 1
Ohm is maintained.
Suitable grounding mat should be provided in the sub station yard.
System Grounding:
It is a connection to the ground of a part of the
plant forming part of the operating circuits for
example the star point of the transformer or the
neutral conductor. The grounding of the lighting,
arrestors also comes under the head of system
grounding.
The provision of system ground
reduces to considerable extent the magnitude of
the transient over voltages and there by increases
the life of electrical equipment besides minimizing
the services interruptions.
Thus the fundamental purpose of system ground is
the protection of installation and improvement in
quality of service. The system ground also will
ensure the safety of the personnel to some extent,
as it helps to clear the fault speedily.
System Earthing
Types of System
Earthing:
Earthing
Earthing
Earthing
Earthing
through a resistance.
through a reactance.
through a Peterson coil
directly or solid earthing.
SubBecause
Station
Earthing
of the difficulties and disadvantages
involved in
marinating the system grounding and safety grounding separately
it is the common practice now to have a combined grounding
system at the sub stations. Provision of adequate earthing in a
sub station is extremely important for the safety of the operating
personnel as well as for proper system operation. The Primary
requirements of a good earthing system in a sub station are.
The impedance to ground should be as low as possible.
The
impedance of the earth system shall not exceed the following
limits in the sub stations
Power Stations
0.5 Ohms
1.0 Ohms
2.0 Ohms
5.0 Ohms
10.0 Ohms
Touch Potential :
Touch potential is the potential difference between the ground
surface potential where a person is standing and the potential of his
outstretched hand (s) which are in contact with an earthed
structure. It is normally assumed that a persons maximum reach is
1.0 meter.
Step Potential :
Step Potential is the potential difference between outstretched feet,
at a spacing of 1.0 meter without the person touching any earthed
structure
Mesh Potential
The maximum potential difference between the centre of a mesh in
an earth grid, and an earthed structure connected to the buried grid
conductors. It is worst case scenario of a touch potential.
Transferred potential
The transferred potential is a touch potential which is transferred
some distance by an earth referenced metallic conductor. For
example, consider a screened cable connecting two sub stations
which are some distance apart. If a person disconnects the earthed
termination at one end of a screened cable he may be subjected to
the full ground potential rise occurring due to an earth fault. This
can be a very high touch potential.
Duration of fault.
Magnitude of the fault current.
Resistivity of the underlying strata.
Resistivity of the surface material
Material of the earth electrode.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
100 X 16 mm and 75 X 8mm size MS steel flats are being ordered for forming
the earthing system for EHT Sub station and 33/11 KV Sub Stations respectively
Earth mat shall be formed with the steel flats buried in the ground at a depth of
500mm.
The earth mat shall extend over the entire switchgear yard and beyond the
security fencing of structural yard by at least one meter.
The outer most peripheral earthing conductor surrounding the earth mat shall
be of 100 x 16 mm size MS flat.
The intermediate earthing conductors forming the earth mat shall be of 75 x 8
mm size flat.
All the risers used for connecting the equipment steel structures etc., to earth
mat shall be of 50 x6 mm size excepting for earthing of L A s and transformer
neutrals for which 100 x 16 mm or 75 x 8 mm size shall be used.
All Junctions (crossing of the steel flats while forming the earth mat and taking
risers from the earthmat for giving earth connections to equipments, steel
structural conducts, cable shearths shall be propersly welded.
Proper earthing lugs shall be used for connecting the earth terminals of
equipments to the earthing steel flat.
Provisions shall be made for thermal expansion of the steel flats by giving
suitable bends.
The earth mat shall be formed by placing 75 x8mm MS flat at a distance 5
meters along the length & breadth of the sub station duly welding at crossing.
All the equipments, steel structural, conduits, cable sheaths shall be solidly
grounded by connecting to the earthing mat at least two places for each.
The ground mat of the switchyard shall be properly connected to the earth mat
of the control house at least at two points.
welding is done shall be given a coat of black asphalitic varnish and then
covered with hessain tape to avoid rusting.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
All paints, enamel and scale shall be removed from point of contact in metal
surfaces before applying ground connections.
The risers taken along the main switchyard structures and equipment
structures up to their top) shall be clamped to the structure at an interval of
not more than one meter with ground connectors.
75 X 8 mm ground conductor shall run in cable trenches and shall be
connected to the ground amt at an interval of 5 meters.
Grounding electrodes 2.75 Mtrs length 100 mm dia 9 mm thickness CI Pipes
shall be provided at all their peripheral corners of the earthiong mat and
also at Distance of 10 Mtrs along length & width of switch gearand in the
entire switch yard.
The grounding electrodes shall be drived into the ground and their tops shall
be welded to a clamp and the clamp together with the grounding shall be
welded to the ground conductor.
The switchyard surface area shall be covered by a layer of crushed rock of
size 25 x 40 mm to a depth of 100mm
Transformers and L A s and single phase potential transformer shall be
provided with earth pits near them for earthing and these earth pits in turn
shall be connected to the earth mat.
Power Transformers neutral shall be provided with double earthing. Neutral
earthing and body earthing of power transformers shall be connected to
separate earth electrode.
the entire earthing system shall be laid with constructional conveniences in
the filed, keeping in view the above points.
The joints and tap-offs where welding is done shall be given a coat of black
asphalitic varnish and then covered with hessain tape to avoid rusting.
0.2 Seconds
0.35 Seconds
0.7 Seconds
On soil
1050 V
600 V
195 V
On chippings 150mm)
1400 V
800 V
250 V
0.2 Seconds
0.35 Seconds
0.7 Seconds
On soil
3200 V
1800 V
535 V
On chippings 150mm)
4600 V
2600 V
815 V
S.
No
Item
Material to be used
Grounding Electrodes
Earth mat
75 X 8mm MS Flat
EARTH ELECTRODES
Earth electrodes shall be of CI pipe 100mm (inner dia)
2.75 meters long with a flange at the top and earth flat
already indicated and shall be connected to earth grid in
the Sub Station. All earth pits are to excavated and the
preferred backfill is a mixture of coke and salt in alternate
layers. A suitable size cement collar may be provided to
each earth electrode. All bolted earth mat connections
and strip connections to plant and equipment panel will
be subject to strict scrutiny. Transformer Neutrals shall be
connected directly to the earth electrode by two
independent MS strips of 75 X 8mm. The transformer
body earthing shall be done with 75 X 8mm flat. The
independent connections of MS strips with earth mat shall
be given on either side of the Transformer. All contact
surface must be filled or ground flat ensures good
electrical connection, and the contact surface shall be
protected with a contact lubricant. Following this all
connections shall be painted with heavy coats of
bituminous black paint so as to exclude moisture.
While selecting site for Sub Station the following points should be
kept in view.
1. The Sub Station should be as near the load centre as feasible.
2. The Sub Station should be far away from the obstructions to have
permit easy and safe approach of HV over heads transmission lines.
3. The Sub Station should be easily accessible to the road to facilitate
transport of equipment
4. As far as possible near a town and away from built up areas
5. Sufficiently away from the areas where military rifle practices are
held
6. The Site should have as far as possible good drinking water supply
7. The Sub Station should not be located within two miles of any
aerodrome
8. The
site selected should have sufficient area to properly
accommodate the Sub Station equipment, Structures, Buildings and
also future extensions.
9. SITE REQUIREMENTS OF SUBSTATIONS:10. 33KV SS -1Acer,132KV SS-2to5Acers,220KVSS-5to20Acers,
11. 400KVSS-50to75Acers,
Selection of Arrangement of
Switching of Functions
RAIL CROSSINGS
Clearance is to be obtained from the Railway Authorities for the
proposed power line crossing railway track. A sketch showing full
particulars such as Vertical Clearance of the lowest power conductor
over the railway track, angle of crossing and the shortest distance
from the railway track from the nearest tower shall accompany the
proposal for railway crossing. The prescribed questionnaire duly
answered and Factor of Safety Calculations shall also be sent along
with the proposals for railway crossing.
Clearance for the railway crossing will be accorded if the following
conditions are fulfilled. The power line shall cross the railway track
at an angle not less than 60o.
The crossing span shall not exceed 80% of the normal design span.
The minimum clearance of the lowest power conductor over the
railway track shall be as per the statement 2-1 on page II-4.
The minimum distance between footing of the nearest tower and the
railway track shall not be less than 1.5 times the height of the tower.
The Railway crossing span shall be strung with double tension
hardware fitted to the towers on either side of crossing span with
dead end towers.
The foundations, structures and power conductors and earth-wire
are all provided to have a minimum Factor of Safety of 2.00 under
normal conditions and 1.50 under Broken Wire Conditions.
The towers shall be earthed by providing two earth pits on either
side.
STRUCTURES
DESIGN LOADS:
FACTOR OF SAFETY:
FOR STEEL: 2.0 based on maximum loading
conditions (on elastic limit for tension
members and crippling load for compression
members).
FOR R.C.C. : 3.5 on ultimate breaking load
FOR SAFETY AGAINST OVER TURNING:
Steel2, R.C.C 2.0
Busbars:
The substation busbars can be broadly classified in to
the following three categories:
Out door rigid tubular busbars
Outdoor flexible ACSR or aluminum alloy busbars
Indoor busbars
Busbar of Outdoor Switchyard:
These are of following forms:
1.Tubular aluminum conductors are supported on post
insulators made of porcelain. These are bolted to get
extended lengths.
2. ACSR/AAC conductor is supported at each stringing
point on strain insulator .Such flexible busbars are
used for long spans with (beams and columns) support
structures at each end. In some cases the strain
insulators may be supported on the walls of power
house or valve house buildings.
220 kV
400 kV
42/35
60/52
88/78
101.6/90.1
101.6/85.4
114.3/97.2
114.3/102.3
114.3/97.2
114.3/102.3
Voltage Class
430 kV / 230 kV
Size
Outer diameter
114.30 mm
Inner diameter
97.20 mm
Thickness
8.51 mm
2825.61 sq.mm
Type of designation
Tensile strength
63401 WP as per
IS:5082
20.5 kg/sq.mm
Weight
7.7 kg /m
Current rating at 75 C
3000 Amps
Strung Busbar:
Commonly Used Sizes of Conductor:
System
Voltage
Equivalent
Aluminum
area
(Sq.mm.)
Current
Carrying
Capacity
at 75oC
420
737
200
487
180
445
420
737
200
487
420
737
520
836
520
836
Conductor Size
220 kV
400 kV
Rated
Equipment live
voltage terminal elevation in
(KV)
meters
11 & 33
66
132
220
2.8 to 4.0
4.0
3.7 to 5
4.9 to 5.5
Low
High
5.5 to 6.5
6.0 to 7.0
8.0 to 9.5
9.0 to 13.0
9.0
9.0 to 10.5
13.5 to 14.5
18.5
Take-off
elevation
in metres
6.5 to 8.5
9.5
12.0 to 12.5
15.0 to 18.5
STRINGING TENSIONS:
The insulators, bus bars and connections
should not be stressed to more than one
fourth of the breaking load or one third of
their elastic limit whichever is lower.
CLEARANCES:
The following are the
minimum
clearances
for
out-door
equipment and rigid conductors in air.
Rated
voltage
(KV)
BIL Basic
insulation
level (KV)
Minimum Clearance
between
Phase to
phase
(mm)
Phase to
earth
(mm)
Phase to phase
spacing in isolators
and switches
11
75
400
310
610
920
33
170
400
320
760
120
66
325
750
630
1530
2140
132
550
650
1350
1600
1150
1380
2140
3050
220
900
1050
2300
2700
1960
2300
3400
4000
400
1425
1550
4000
5200
3500
3640
a)
11
3700
2600
33
3700
2800
66
4600
3000
132
4600
3500
220
5500
4300
400
8000
7000