INFORMATION PHASE

Nama: Muhammad Khairuddin Bin Azwi


Stakeholder: Engineer
Project: Revitalization of UTM Library (PSZ) Foyer

ENGINEERING REQUIREMENT
Add switch socket outlets (SSO)
Add cable internet socket
Add fans
Change the paint and add mural on wall
Install awning

ELECTRICAL SYSTEM
3 Pin Socket Plug with USB Connection at Table
13A
Usb - 5V 2A
Fix to Table

ELECTRICAL SYSTEM
3 Pin Socket Plug
13A
Fix to wall and column

STRUCTURAL SYSTEM
a) Awning
) size overall 1000mm x 14,000mm
b)

Hacking wall or add duct for install wire for electrical system.

MECHANICAL SYSTEM
CEILING FAN
a) PANASONIC 60 Ceiling Fan F-M15A0 White60" Basic Ceiling Fan
) 5-speed Electronic Regulator
) Enhanced Safety Features
) Low Noise
) Durable Advanced Motor
) Thermal Safety Fuse

MECHANICAL SYSTEM
WALL MOUNTED FAN
b)

Panasonic Wall Fan 16" F-MU408

Blade Size 40cm (16)


Switch 3 Speed On/Off Pull Switch
Colour White

LAYOUT

PROJECT CONSTRAINTS
PROBLEM
Cant do noisy work in Office hours
The area is the main route of the door for student to come out and in
SOLUTION
Use method anti sound for renovation or doing job after office hour
Create a barrier between the entrance and the renovation