KBR STANDARD PROJECT

IPMS CHAINS
PROCESS
ENGINEERING

Process/STD

15 APR

Chain D-KDEL: Engineering Deliverable

100%

DD-STT

CPM
CHAIN

DD-ICM

Prepare & Issue Deliverable

DD-STT

DD-PRC

10%

IPMS
CHAIN

75%

DD-IST

DD-ICM

75%

100%

Prepare

Finalize & Issue

Duration_15d
15d_
MILESTONES:
DD-STT
DD-PRC
DD-IST
DD-ICM

Start Document
Complete Prep
Start Document Issue
Complete Issue

Duration_5d_

Work Package Sub Types: PR2, PR3, PR6


Document Sub Types: PR20, PR32, PR33, PR34, PR60

Process/STD

15 APR

Chain E-KAPA: Advanced Process Automation


DD-SFS
DD-SHS
DD-SDD
DD-SIM
DD-CFS
DD-CHS
DD-CDD
DD-CIM
10%
10%
20%
20%

CPM
CHAIN

Functional Hardware/
Spec.
Software
Systems

Detailed
Design
Develop.

Implement

DD-SFS
DD-SHS
DD-SDD
DD-SIM
DD-CFS
DD-CHS
DD-CDD
DD-CIM
0%

IPMS
CHAIN

10% 10%

20% 20%

Functional Hardware/
Spec.
Software
Systems

40% 40%

Detailed
Design
Develop.

DD-SCT
DD-SCM
DD-SPS
DD-CCT
DD-CCM
DD-CPS
10%
20%
10%

Client
Trng.

Post-Com.
Support

DD-SCT
DD-SCM
DD-SPS
DD-CCT
DD-CCM
DD-CPS

60% 60%

Implement

Commissioning

70% 70%

Client
Trng.

90% 90%

Commissioning

100%

Post-Com.
Support

Duration 60d Duration 20d Duration 90d Duration 110dDuration 10d Duration 100dDuration 30d
MILESTONES
DD-SFS
DD-CFS
DD-SHS
DD-CHS
DD-SDD
DD-CDD
DD-SIM
DD-CIM
DD-SCT
DD-CCT

Start Functional Specification


DD-SCM
Complete Functional Specification
DD-CCM
Start Hardware/Software Systems
DD-SPS
Complete Hardware/Software System DD-CPS
Start Detailed Design Development
Complete Detailed Design Development
Start Implementation
Complete Implementation
Start Client Training
Complete Client Training

Start Commissioning
Complete Commissioning
Start Post-Commissioning Support
Complete Post-Commissioning Support

Process/STD

Work Package Sub Types: PR8


Document Sub Types: PR82, PR83, PR84

15 APR

Chain P-BOS:
Procurement (Acquisition) Chain
Blanket Order Bulks or Subcontracts
DD-STT DD-RFQ
DD-RFQ
30%
Issue
Scope

0%

FQ-ISS

FQ-ISS

Evaluate Bids /
Make
Recommendation

Issue
Inquiry

CPM
CHAIN

IPMS
CHAIN

DD-STT
0% DD-RFQ
30%
Issue
ERW, RFS
or MTO

MILESTONES:
DD-STT
DD-RFQ
RF-ISS
FQ-ISS
FQ-BID
FQ-TEC
FQ-REC
PP-FCR
AW-ISS

FQ-REC

70%

30%
30%
FQ-ISS
30%
DD-RFQ 30%
RF-ISS
RF-ISS

FQ-ISS
30%
30%
FQ-BID

PREP &
ISSUE
RFQW
5d

SUPPLIER
PREPARE
BIDS
10d

PREP &
ISSUE
RFQ
2d

Start ERW, RFS or MTO Assembly


Issue ERW, RFS, or MTO
Issue RFQW
RFQ (Inquiry) Issued
Bids Return
Eng Tech Review Complete
Recommend Issue
Client Approval
Award Issue External

FQ-BID
30%

PP-FCR
100%
FQ-REC
100%

EVAL BIDS
& ISSUE
RECOMEN
2d

Technical
Evaluation
50d

AW-ISS
0%

Issue Award
(Blanket or Subcontract)

FQ-TEC
100%
FQ-TEC
100%

FQ-REC

100%
FQ-REC
CLIENT
APPROVE
10d

AW-ISS
100%
100%
PP-FCR
ISSUE
BLANKET
AWARD
2d

Work Package Sub Types: PR8


Document Sub Types: PR89

NOTES:
1. Percentages shown are for Engineering Progress Only.
2. Dotted boxes represent Procurement (non-Engineering) responsibilities only.

Process/STD

15 APR