Professional Documents
Culture Documents
CONTENTS
SAMPLE
CONSTRUCTION
Protective and Life
SAFETY
STANDARD
Saving Equipment
(partial
coverage)
PERSONAL PROTECTIVE
EQUIPMENT 1926
Subpart E
Head Hazard
Assessment
Falling objects
Exposed electrical
conductors
Low-hanging
obstructions
Respiratory Protection
Hazard Assessment
Assess for
Inhalation of
airborne
dusts or
particulates
Inhalation of
chemical
vapors or fumes
Lack of adequate
oxygen
Foot Hazard
Assessment
Falling or rolling
objects
Objects piercing the
sole
Exposure to electrical
hazards
Slippery walking
surfaces
Wet or muddy
conditions
Hand Hazard
Assessment
Skin absorption
of
harmful
substances
Severe cuts or
lacerations
Severe abrasions
Punctures
Chemical burns
Thermal burns
10
11
12
Employee Training
When PPE is
necessary
What PPE is
necessary
How to put on,
remove,
adjust, and wear PPE
Limitations of PPE
Care, maintenance,
useful life, and
disposal
of PPE
13
Hard Hats
Hard hats are required for:
Overhead hazards
Falling objects
Flying objects
Electrical hazards
Scaffold use
14
15
Hard Hats
Hard hats must not be modified
Must be inspected for damage
Should not have items stored
inside
Must be hard hats, not bump caps
16
Hard Hats
17
Hard Hats
18
Selecting Foot
Protection
Steel toes
Metatarsal
protection
Puncture or slipresistant soles
Chemical
resistance
Waterproof boots
Cold weather
foot wear
19
20
Hearing Protection
Wearing earplugs or earmuffs can
help prevent damage to hearing.
Exposure to high noise levels can
cause irreversible hearing loss or
impairment as well as physical and
psychological stress.
21
Selecting Hearing
Protection
Made from foam,
waxed cotton, or
fiberglass wool
Self-forming
Comfortable fit
Plain cotton is not
an acceptable
protective device.
22
23
Hearing Protection
24
Hearing Protection
25
Hearing Protection
26
29
30
31
Selecting Respiratory
Protection
Filtering facepiece
Air purifying respirator
Different types of
cartridges
Air-supplied respirator
Self Contained Breathing
Apparatus (SCBA)
NIOSH approved
32
Respiratory Protection
35
36
SAMPLE
CONSTRUCTION SAFETY
STANDARD
(partial coverage)
Annual Inspection
Annual inspection of the hoisting
machinery shall be made by a
competent person
The employer shall maintain a
record of the dates and results of
inspections for each hoisting
machine
and piece of
equipment
Daily Inspection
Operation of crane,
controls, movement
Inspect all lines for
leaks
Check limit switch
Check brakes for
coasting
Twisted, broken,
kinked wire rope
Deformed, stretched,
or cracked hooks
Correct spooling
Crane Warnings
Equipment operated by properly trained personnel
only.
Do not lift loads over people, warn personnel of
approaching loads
Do not make side pulls, lift all loads vertically
Do not use limit switches as normal stopping devices
Moving Parts
(a)(14)(i) An accessible
fire extinguisher of 5BC
rating, or higher, available
at all operator stations or
cabs of equipment.
5BC
OSHAs 10-Foot
Circle of Safety rule
Increase safe
Maintain a safe distance from the
distance near higher
Danger Zone
voltage power lines (10 foot radius from the power line)
0 to 50,000
10
Over 50,000
0 to 50,000
50,000 to 345,000
10
Over 345,000 to
750,000
16
Source: OSHA
Crawler
Hoisting Employees
personnel hoist,
ladder,
stairway,
aerial lift,
Leveling, Outriggers
The crane shall be uniformly level within one
percent of level grade and located on firm
footing
Cranes equipped with outriggers shall have
them all fully deployed following manufacturer's
specifications, insofar as applicable, when
hoisting employees
B30.5 - 5-1.2
Crane to be standing on firm supporting surface
level within 1% grade
Level within
1% of grade
Rigging
Hooks on overhaul ball assemblies, lower load blocks, or other attachment
assemblies shall be of a type that can be closed and locked, eliminating the
hook throat opening.
Alternatively, an alloy anchor type shackle with a bolt, nut and retaining pin
may be used.
All hardware capable of 5 times maximum intended load
Tag Lines
Tag lines shall be used unless their use creates an
unsafe condition
The crane or derrick operator shall remain at the
controls at all times when the crane engine is
running and the platform is occupied
Hoisting of employees shall be promptly
discontinued upon indication of any
dangerous weather conditions or
other impending danger
Prelift Meeting
Pre-lift meeting with operator, supervisor,
signaler if used, and employees to be lifted to
review procedures & requirements
This meeting shall be held prior to the trial lift
at each new work location, and be repeated
for any employees newly assigned to the
operation.
SAMPLE
CONSTRUCTION
SAFETY
STANDARD
Protective and Life
(partial
coverage)
Saving Equipment
STEEL ERECTION SAFETY
1926 Subpart R
Column anchorage
1926.752(a)-(b)
Site layout
Adequate access
roads
Safe delivery of
supplies
Movement of
equipment
Firm, properly
graded, and
drained area
1926.752(e)
Site Layout, Site-Specific Erection
Plan and Construction Sequence (contd)
1926.753(c)-(d)
1926.753(e)
1926.754
Structural stability
Walking/working surface
Plumbing up
Metal decking
Structural Stability
1926.754(a)
Structural Stability
1926.754(b)
Multi-story structures
1926.754(c)
Walking/Working Surfaces
Shear connectors
and other similar
devices
Field-installed rather
than shop installed
Shear Connectors
Plumbing-Up Equipment
1926.754(d)
Installed in conjunction with steel erection
process to ensure stability of structure
In place and properly installed before structure
is loaded with construction
material
Be removed only with
approval of competent
person
Metal Decking
1926.754(e)(1)
Column Anchorage
1926.755(a)
1926.756
1926.756(a)
Perimeter Columns
Column for
next tier
48 min. from
finished floor
to top of column
1926.756(e)(1)
Perimeter columns
1926.756(e)(2)
1926.757
1926.757(a)
Shop installed
Erection Bridging
1926.757(d)
1926.757(e)
Releasing cables
1926.759(a)-(b)
Fall Protection
Fall protection requirements
Connectors
Controlled decking zone (CDZ)
Criteria for fall protection
equipment
Custody of fall protection
1926.760
1926.760(a)
Connectors
1926.760(b)
Completed connector
training
1926.760(d)
Fall Protection Equipment
1926.760(e)
Training
1926.761(a)
1926.761(b)
Special Training
1926.761(c)(1)
1926.761(c)(2)
Special Training (contd)
Connector procedures
1926.761(c)(3)
Special Training (contd)
SAMPLE
CONSTRUCTION
SAFETY
STANDARD
Protective and Life
(partial
coverage)
Saving Equipment
CONCRETE AND MASONRY
SAFETY 1926 Subpart Q
Construction Loads
1926.701(a)
Post-Tensioning Operations
1926.701(c)
Post-Tensioning
Operations
1926.701(c)(1)-(2)
Jack
No riders
1926.701(e)(1)
1926.701(e)(2)
1926.701(f)
Personal Protective Equipment
Conical or tapered
bottoms
Mechanical or pneumatic
means to start flow of
material.
Concrete
Mixers
1926.702(b)(1)-(2)
Concrete Buggies
1926.702(d)
Concrete Pumping
System
1926.702(e)(1)-(2)
Concrete Buckets
1926.702(f)(1)-(2)
Tremies
Sections of tremie
and similar concrete
conveyances must
be secured with
wire rope (or
equivalent
materials) in
addition to the
regular couplings or
connections
1926.702(g)
Bull Floats
Bull float handles
must be
constructed of
nonconductive
material or
insulated
When used where
1926.702(h)
Masonry Saws
Masonry saws
must be guarded
with a semicircular
enclosure over the
blade
Method for
retaining blade
fragments must be
incorporated in the
design of the
1926.702(i)(1)-(2)
Lockout/Tagout Procedures
1926.702(j)(1)
General Requirements1926.703(a)(1)
Formwork must be
designed,
fabricated, erected,
supported, braced,
and maintained.
Must support
without failure all
vertical and lateral
loads applied to it
General
Requirements
1926.703(a)(2)
Shoring and
Reshoring
1926.703(b)(1)-(3)
Shoring and
Reshoring
1926.703(b)(4)-(5)
As the original
forms and shores
are removed.
Whenever the
concrete is required
to support loads in
excess of its
capacity
Vertical Slipforms
Form steel rods or
pipes on which
jacks climb must
be:
Provided with
scaffolds or work
platform where
1926.703(c)(1)-(3)
Vertical
Slipforms
1926.703(c)(5)
Removal of
Formwork
Forms and
shores must
not be
removed until
employer
determines
concrete has
gained
sufficient
strength.
1926.703(e)(1)
Precast Concrete
Wall units,
structural
framing, and
tilt-up wall
panels must be
adequately
supported to
prevent
overturning.
1926.704(a)
Precast Concrete
1926.704(b)
Precast Concrete
1926.704(c)
Precast Concrete
1926.704(d)
Precast Concrete
1926.704(e)
Except employees
required for the
erection of those
members.
Fall Protection
1926.501(b)(12)
Precast Concrete
Precast walls can be installed
quickly
Foundations can be backfilled as
soon as the slab is in placed,
enhancing jobsite safety
Lift-Slab Operations
Designed by a
registered professional
engineer
Plans and designs
implemented by
employer must
include
Detailed instructions
Sketches indicating
1926.705(a)
Jack/Lifting Unit
Marked to indicate rated
capacity
Not loaded beyond
capacity
Synchronized lifting to
ensure uniform lifting
Manual controls located
in central location
attended by competent
person (must be
Lift-Slab Operations
1926.705(k)(1)
personnel
LAmbiance Plaza,
Bridgeport, Conn.
Lift slab construction project
28 workers killed
Multiple failures in design system
and
construction practices
1926.706(a)(1)-(5)
1926.706(b)
SAMPLE
CONSTRUCTION
SAFETY
STANDARD
Protective and Life
(partial
coverage)
Saving Equipment
FALL PROTECTION 1926
Subpart M
L Scaffolds
R Steel erection
S Tunneling operations
V Power transmission
and distribution
Subpart X Stairways and ladders
Subpart N Cranes and derricks
Subpart M Fall
Protection
1926.500(a)(1)
Exception
15
Scaffolds
10
Construction Sites
6
General Industry
1926.501(b)(1)
1926.501(b)(2)
1926.501(b)(3)
1926.501(b)(8)
bricklaying
Fall Protection
Required
Low-slope roof
Steep roof
1926.501(b)(10) &(11)
Covers shall:
Secured to prevent
displacement
Marked hole or
cover or colorcoded
Falling Objects
1926.501(c)
1926.502(a)(1)
Methods of Fall Protection
Conventional methods
Safety nets
Guardrails
Personal fall
arrest systems (PFAS)
Guardrail System
1926.502(b)
Guardrail System
Top rail: 42 +3
Midrail: 21 +3
Note: Toe boards are not part of a
guardrail system for fall protection
1926.502(b)
Guardrails
Job well done
Anchorage
Harness
Connectors
Allows an employee to
be supported on an
elevated vertical
surface
No more than 2 freefall
Inspected before each
use
Safety belts okay for
use
Warning Lines
1926.501(b)(10)
1926.502(f),
Used in:
Overhand bricklaying
Pre-cast concrete
Training Requirements
1926.503
SAMPLE
CONSTRUCTION
Protective and Life
SAFETY
STANDARD
Saving Equipment
(partial
coverage)
EXCAVATION AND
TRENCHING SAFETY
1926 Subpart P
Trench Cave - In
Mechanics of a Cave-In
Stress cracks form back
Mechanics of a Cave-In
Excavation bottoms are the first to fail.
Support for the upper part of excavation
is left hanging only by shear and reduced
tension forces.
The uppermost portion of the vertical wall
collapses into the excavation.
Soil, like concrete, is normally strong in
compression but not strong in tension.
Figures 1 and 2 two detail the scenario.
Mechanics of a Cave-In
Fig.
1
Fig.
2
Competent Person
Responsibilities
Authority to stop work
Inspection of excavations
Daily
Pre-shift
As needed
After rain
Any increasing hazard occurrence
atmospheres
Inspection of material and
equipment
Monitoring of water removal
Visual Tests
Manual Tests
Soil Classification
Cohesive
Stronger +
Clay
Granular
Silt
- Weaker
Sand
are excavated.
If it stays in clumps it is
cohesive
Mechanical
(Device)
Plasticity
Pocket Penetrometer
Dry Strength
Shear Vane
Thumb Penetration
Thumb Penetration
Pocket Penetrometer
Probes the soil with
a small tube-like
plunger
Device is pressed
into soil to
calibration mark
Spring loaded
piston displaces the
scale ring
Produces a
compressive
strength reading
Shear Vane
Hand-held instrument used
Sloping
are encountered, and the
Slope Configurations
Soil or
Rock
Type
Maximum
Allowable Slopes
for Excavations
Less than 20
Unconfine
d
Compressi
ve
Strength
_______
Stable
Rock
Type A
Vertical
90
to 1
53
1.5
tons/sq ft
Type B
1 to 1
45
.5 - 1.5
tons/sq ft
Type C
1 to 1
34
.5 tons/sq
ft
maximum
allowable slope is
a special situation
for Type A soil.
An excavation in
Type A soil that is
open for less than
24 hours and 12
feet or less in
depth, can have a
maximum
allowable slope of
Benching
Foundation/Basement
Excavations
The depth of the
foundation/basement trench
cannot exceed 7 feet deep
unless you provide other
cave-in protection
Keep the horizontal width of
the foundation trench at least
2 feet wide. Mind surface
encumbrances
Plan the foundation trench
work to minimize workers in
the trench and the length of
time they spend there
Inspect the trench regularly
Stop work ifany potential for
cave-in develops and fix the
problem before work starts
again
Utilities Location
Excavators must observe a tolerance zone
Utilities Location
When estimated location of
underground installations are
approached, exact location shall be
determined by safe/acceptable
means (hand digging, soft dig, pot
hole, etc.)
While excavation is open,
underground installations shall be
protected, supported or removed
as necessary to safeguard
Protective
Systems
Reasons for Needing a Protecive
System
Existing utility lines, roadways, or
structural foundations intruding on the
maximum allowable slope.
No right-of-way permit for sloped
excavation.
The vertical face excavation is beyond the
safety slope.
The gravitational force will cause soil
raveling, cave-ins, or slope stability
failures from the vertical face.
Protective Systems
Timber Shoring
Struts
Waler
s
Hydraulic Shoring
Protective Systems
Protective Systems
Trench Boxes
Access/ Egress
Hazardous Atmospheres
All testing must be
Methane
Natural Gas
Petroleum
Carbon Monoxide
Hazardous Atmospheres
Excavation Checklist
Utilities
locations identified
and marked
Access/
Potentially
Water
Hazardous
Atmosphere tested before and
during shift
Emergency
and machinery
protected from traffic
Soil
Employees
Shoring
protected from
classification performed
by Competent Person
falling loads
systems inspected
before and during shift
Proper
Daily
20 in depth
have engineered protection
systems
Stability
of adjacent structures
secured and shored
inspection performed by
a competent person before and
during the shift
Inspection includes the trench,
the area around it, and
protective systems
1926.452 SCAFFOLDS
1926.552 HOISTS
1926.652 EXCAVATIONS
1926.703 SHORING
SAMPLE PROVISIONS
1.
2.
3.
4.
5.
Suggestion
Design prefab units that
can be built on the ground
and erected in place
Design underground
utilities to be placed using
trenchless technologies
Allow adequate clearance
between structures and
power lines.
Design 42 parapet walls
Design permanent
anchorage points
Purpose
6.
7.
8.
9.
10.
Design permanent
guardrails around skylights
DfCS Examples:
Prefabrication
Concrete
Wall Panels
Concrete Segmented Bridge
Steel stairs
DfCS Examples:
Roofs
Skylights
THANK YOU!
QUESTIONS?