Professional Documents
Culture Documents
Resource Planning
Operations
Operations Management
Management -- 66thth Edition
Edition
Beni Asllani
Copyright 2009 John Wiley & Sons, Inc. University of Tennessee at Chattanooga
ERPEnterprise Resource
Planning
Starts with slide 56
We will not be covering the material on
pages 647-667 of Chapter 15 until after
the second exam
100 x 1 =
100 tabletops
Continuous demand
400 Discrete demand
400
300
No. of tables
300
200 No. of tables
200
100
100
1 2 3 4 5
Week M T W Th F M T W Th F
Planning
Product Material Item
structure requirements master
file planning file
Planned
order
releases
Inputs Outputs
Master production Planned order
schedule releases
Product structure file Work orders
Purchase orders
Item master file
Rescheduling notices
Rivets (2)
Finished clipboard Pressboard (1)
(1)
Phantom bills
Transient subassemblies
Never stocked
Immediately consumed in next stage
K-bills
Group small, loose parts under pseudo-item
number
Reduces paperwork, processing time, and file
space
Modular bills
Product assembled from major subassemblies and
customer options
Modular bill kept for each major subassembly
Simplifies forecasting and planning
X10 automobile example
3 x 8 x 3 x 8 x 4 = 2,304 configurations
3 + 8 + 3 + 8 + 4 = 26 modular bills
4-Cylinder (.40) Bright red (.10) Leather (.20) Grey (.10) Sports coupe (.20)
6-Cylinder (.50) White linen (.10) Tweed (.40) Light blue (.10) Two-door (.20)
8-Cylinder (.10) Sulphur yellow (.10) Plush (.40) Rose (.10) Four-door (.30)
Neon orange (.10) Off-white (.20) Station wagon (.30)
Metallic blue (.10) Cool green (.10)
Emerald green (.10) Black (.20)
Jet black (.20) Brown (.10)
Champagne (.20) B/W checked (.10)
Clipboard Level 0
Lapdesk Level 0
20 units available
(20 - 120) = -100 100 additional Clipboards are required
Order must be placed in Period 2 to be received in Period 3
Gross Requirements 0 60 0 60 0
Scheduled Receipts
Projected on Hand 20
Net Requirements
Planned Order Receipts
Planned Order Releases
Gross Requirements 0 60 0 60 0
Scheduled Receipts
Projected on Hand 20 20 10 10 0 0
Net Requirements 0 40 50
Planned Order Receipts 50 50
Planned Order Releases 50 50
2(30)(60
EOQ 60 minimum order quantity
1
Capacity Open
Routing
requirements orders
file
planning file
Utilization
Percent of available time spent working
Efficiency
How well a machine or worker performs compared to a
standard output level
Load
Standard hours of work assigned to a facility
Load Percent
Ratio of load to capacity
load
Load Percent = x 100%
capacity
90
80
70
60
50
40 Normal
30 capacity
20
10
0
1 2 3 4 5 6
Time (weeks)
90
80
70 Work
60 an
extra Push back
50 Pull ahead
shift
40 Overtime Push back Normal
30 capacity
20
10
0
1 2 3 4 5 6
Time (weeks)
Load leveling
process of balancing underloads and overloads
Copyright 2009 John Wiley & Sons, Inc. 15-52
Determining Loads
and Capacities
2 copiers, 2 operators
5 days/wk, 8 hr/day
1/2 hr meals, 1/2 hr maintenance per day
Efficiency = 100%
Utilization = 7/8 = 87.5%
Daily capacity = 2 machines x 2 shifts
x 8 hours/shift x 100% efficiency
x 87.5% utilization
= 28 hours or 1,680 minutes
Example 12.2
Copyright 2006 John Wiley & Sons, Inc. 14-53
Determining Loads
and Capacities
JOB NO. OF SETUP RUN TIME
NO. COPIES TIME (MIN) (MIN/UNIT) TOTAL TIME
10 500 5.2 0.08 5.2 + (500 x 0.08) = 45.2
20 1,000 10.6 0.10 10.6 + (1,000 x 0.10) = 110.6
30 5,000 3.4 0.12 3.4 + (5,000 x 0.12) = 603.4
40 10,000 11.2 0.14 11.2 + (10,000 x 0.14) = 1,411.2
50 2,000 15.3 0.10 15.3 + (2,000 x 0.10) = 215.3
2385.7 min
Load percent = 2,385.7 / 1,680 = 1.42 x 100% = 142%
Add another shift:
Daily capacity = 2 machines x 3 shifts x 8 hours/shift
x 100% efficiency x 87.5% utilization
= 42 hours or 2,520 minutes
Revised load percent = 2,385.7 / 2,520 = 0.9467 x 100% = 94.67%
Example 12.2
Copyright 2006 John Wiley & Sons, Inc. 14-54
Relaxing MRP Assumptions
Material is not always the most constraining
resource
Lead times can vary
Not every transaction needs to be recorded
Shop floor may require a more sophisticated
scheduling system
Scheduling in advance may not be appropriate
for on-demand production.
Independent data
pools are created that
cannot be integrated
Source: Adapted from Joseph Brady, Ellen Monk, and Bret Wagner, Concepts in
Enterprise Resource Planning (Boston: Course Technology, 2001), pp. 712