You are on page 1of 40

Cost Estimation Models

Estimating Relationships and


Problems
Engineering Economic
Analysis - Seven Steps
1. Recognition and formulation of the problem.
2. Development of the feasible alternatives.
3. Development of the net cash flows (and
other prospective outcomes) for each
alternative.
4. Selection of a criterion (or criteria) for
determining the preferred alternative.
5. Analysis and comparison of the alternatives.
6. Selection of the preferred alternative.
7. Performance monitoring and post-evaluation.
Developing Net Cash Flows
for Each Alternative
Because engineering economy
studies deal with outcomes that
extend into the future, estimating
the future cash flows for feasible
alternatives is a critical step in the
analysis procedure. $ value

0 time
0 1 2 3 4
LEARNING OUTCOMES
1. Approaches to estimation
2. Unit method
3. Cost indexes
4. Cost-capacity equations
5. Factor method
6. Indirect cost rates and allocation
7. ABC allocation
8. Ethical considerations

15-2 2012 by McGraw-Hill All Rights Reserved


Estimating Techniques
Indexes
Unit Technique
Factor Technique
Estimating Relationships
Power-Sizing Technique
Learning Curve
Analysis of product price and cost
Establishing product price as a
markup to cost
Establishing price in relation to
competition
What Direct Cost Estimation
Includes
Direct costs are more commonly estimated than revenue in an
engineering environment. Preliminary decisions required are:
What cost components should be
estimated?
What approach to estimation is best to
apply?
How accurate should the estimates be?
What technique(s) will be applied to
estimate costs?
Sample direct cost components: first costs
and its elements (P); annual costs (AOC or M&O);
salvage/market value (S)
Approaches: bottom-up; design-to-cost (top
down)
Accuracy: feasibility stage through detailed design
estimates require more exacting estimates
15-4
Some techniques: unit; 2012 by McGraw-Hill All Rights Reserved
factor; cost estimating
Different Approaches to Cost
Estimation

15-5 2012 by McGraw-Hill All Rights Reserved


Accuracy
Generalof Cost Estimates
guidelines for
accuracy
Conceptual/Feasibility stage
order-of-magnitude estimates are
in range of 20% of actual costs
Detailed design stage - Detailed
estimates are in range of 5% of
actualcurve
Characteristic costs of accuracy vs. time to make
estimates

15-6 2012 by McGraw-Hill All Rights Reserved


Unit Method
Commonly used technique for preliminary design stage estimates
Total cost estimate CT is per unit cost (u) times number of units
(N)
CT = u N
Example uses:
Cost to operate a car at 60/mile for 500 miles: CT = 0.60 500 = $300
Cost to build a 250 m2 house at $2250/m2: CT = 2250 250 = $562,500

Cost factors must be updated periodically to remain


timely

When several components are involved,


estimate cost of each component and add to
determine total cost estimate CT

15-7 2012 by McGraw-Hill All Rights Reserved


Unit Technique
Involves a per unit factor that can be
estimated effectively.
Examples:
Capital cost of a plant per kilowatt of
capacity
Revenue per customer served
Operating cost per mile
Construction cost per square foot
Maintenance cost per hour
Do problem 2
Example 2
We need a preliminary estimate of the
cost of a particular house. Use the
factor of, say, $55 per square foot
and assume that the house is
approximately 2,000 square feet.
Cost Indexes
Definition: Cost Index is ratio of cost today to
cost in the past
Indicates change in cost over time; therefore, they
account for the impact of inflation
Index is dimensionless
CPI (Consumer Price Index) is a good example

Formula for total


cost is
Formula for total cost is

15-8 2012 by McGraw-Hill All Rights Reserved


Example: Cost Index Method
Problem: Estimate the total cost of labor today in
US dollars for a
maritime construction project using data from a
similar project in
Europe completed in 1998.
Labor index, 1998: 789.6 Cost in 1998: 3.9
million
Labor index, current: 1165.8 Currently, 1 = 1.5
US$

Solution: Let t = today and 0 = 1998 base

Ct = 3.9 million (1165.8/789.6) = 5.76


million
= 5.76 1.5 = $8.64 million
15-9 2012 by McGraw-Hill All Rights Reserved
Finding Cost Indexes
Cost indexes are maintained in areas such as
construction, chemical and mechanical
industries
Updated monthly and annually; many include
regionalized and international project indexes
Indexes in these areas are often subdivided into
smaller components and can be used in
preliminary, as well as detailed design stages

Examples are:
Chemical Engineering Plant Cost Index (CEPCI)
www.che.com/pci
McGraw-Hill Construction Index
www.construction.com
US Department of Labor, Bureau of Labor
Statistics
15-10 2012 by McGraw-Hill All Rights Reserved
www.bls.gov
2012 by McGraw-Hill All
15
Rights Reserved
2012 by McGraw-Hill All
16
Rights Reserved
17
Indexes
An index is a dimensionless number that indicates
how a cost or a price has changed with time
(typically escalated) with respect to the base
year.
Cn = cost or selling price of an item in year n
Ck = cost or price of the item at an earlier point in
time (say year k)
In = index value in year n
Ik = index value in year k
Cn = Ck (In /Ik )
Do Problem 1
Example 1
A certain index for the cost of purchasing and installing utility
boilers is keyed to 1974, where its baseline value was set at
100. Company XYZ installed a 50,000 lb/hr in 1989 for
$350,000 when the index had value of 312. This same
company must install another boiler of the same size in
1996. The index in 1996 is 468.
Cost-Estimating Relationships
(CER)
CER equations are used in early
design stages to
estimate plant, equipment and
construction costs
CERs are generically different from index
relations,
because they estimate based on
design variables
(weight, thrust, force, pressure, speed,
etc.)
Two commonly used CERs
Cost-capacity equation (relates cost to
capacity)
Factor method (total plant cost estimator,
including indirect costs)
15-11 2012 by McGraw-Hill All Rights Reserved
Cost-Capacity Equation
Also called power law and sizing model

Exponent defines relation between capacities

x = 1, relationship is linear
x < 1, economies of scale (larger capacity is less costly than
linear)
x > 1, diseconomies of scale

15-12 2012 by McGraw-Hill All Rights Reserved


Power-Sizing Technique
Also sometimes referred to as the exponential
model
Often used to cost industrial plants and equipment
CA = cost for plant A
CB = cost for plant B
SA = size of plant A
SB = size of plant B
X = cost-capacity factor to reflect economies of
scale CA /CB = (SA /SB )X
or CA = CB (SA /SB )X
Example 4
Make a preliminary estimate of the cost of
building a 600-MW fossil fuel power plant. It is
known that a 200-MW plant cost $100 million 20
years ago when the appropriate cost index was
400. That cost index is now 1,200. The power-
sizing factor is 0.79.
Cost-Capacity Combined with Cost
Index
Multiply the cost-capacity equation by a cost index
(It/I0) to adjust for time differences and obtain
estimates of current cost (in constant-value dollars)

Example: A 100 hp air compressor costs $3000 five years ago when
the cost index was 130. Estimate the cost of a 300 hp compressor
today when the cost index is 255. The exponent for a 300 hp air
compressor is 0.9.

Solution: Let C300 represent the cost estimate today

C300 = 3000(300/100)0.9(255/130)
= $15,817
15-13 2012 by McGraw-Hill All Rights Reserved
Factor Method
Factor method is especially useful in estimating
total plant cost in processing industries
Both direct and indirect costs can be included

Total plant cost estimate CT is overall cost factor (h)


times total cost of major equipment items (CE)

CT = h C E

Overall cost factor h is determined using one of two


bases:
Delivered-equipment cost (purchase cost of major
equipment)
Installed-equipment cost
15-14 (equipment
2012cost plus
by McGraw-Hill All Rights all
Reserved

make-ready costs)
Cost Factor h
The cost factor is commonly the sum of a direct cost
component
and an indirect cost component, that is,

h = 1 + fi
for i = 1, 2, , n components, including indirect
costs

Example: Equipment is expected to cost $20 million


delivered to a new facility. A cost factor for direct
costs of 1.61 will make the plant ready to operate. An
indirect cost factor of 0.25 is used. What will the
plant cost?

Solution: h = 1 + 1.61 + 0.25 = 2.86


CT = 20 million (2.86) = $57.2 million
15-15 2012 by McGraw-Hill All Rights Reserved
Cost Factor h
If indirect costs are charged separately against all
direct costs,
the indirect cost component is added separately, that is,

h = 1 + fi (direct costs components)

and CT = hCE(1 + findirect)

Example: Conveyor delivered-equipment cost is $1.2 million. Factors for


installation costs (0.4) and training (0.2) are determined. An indirect cost
factor of 0.3 is applied to all direct costs. Estimate total cost.

Solution: h = 1 + 0.4 + 0.2 = 1.6


CT = hCE(1 + findirect)
= 1.6(1.2 million)(1 + 0.3) = $2.5 million

15-16 2012 by McGraw-Hill All Rights Reserved


Factor Technique
The factor technique is an extension of
the unit technique
C = cost being estimated
Cd = cost of the selected component d
that is estimated directly
fm = cost per unit of component m
Um = number of units of component m
C = Cd + fm Um
d m
Example 3
We need a refined estimate of the cost
of the house. Assume that the house
is approximately 2,000 square feet of
living space, has one porch and two
garages Use the factor of, say, $50
per square foot of living space,
$5,000 per porch and $8,000 per
garage.
Learning Curves
Mathematical model that explains the
phenomenon of increased worker
efficiency and improved performance
through repetitive production
Also called experience curves or
manufacturing progress functions
Was first reported in 1936 by T.P. Wright,
an aerospace engineer
He observed that, with each doubling of
cumulative production, the total man-
hours needed per plane were reduced to
80% of the former level.
Learning Curve Example
Cumulative 1 2 4 8 16
Production
Direct Labor (as % 1 0.8 0.64 0.512 0.410
of time required for
first item)
Mathematics of the Learning
u = the outputCurve
unit number
Zu = the number of input resources
needed to produce output unit
number u
K = the number of input resources
needed to produce the first output
unit
s = the learning curve slope
parameter
Zu = Ksa where a =
0,1,2,3,....
and u = 2a
Example 5
A student team is designing a formula
car for national competition. The
time required for the team to
assemble the first car is 100 hours.
Their learning rate is 0.8.
The time it will take to assemble the
10th car =
Z10 = 100 (10) log 0.8/log2

= 100 (10) -0.322


= 100 /
Example 6
A rare product is made in batches of 50
units. Within a batch, each unit take less
and less time to be produced because of
a learning process of 75%.
The time needed to assemble the first unit
= 2.3123 hrs
The time needed to assemble additional
units is
Zu = 2.3123 (u) log 0.75/log2
= 2.3123 (u) -0.415
The total time taken for all 50 units =
Determining the per unit
product cost estimate using
a bottom-up approach
Construct a table containing per unit
estimates, factor estimates, and direct
estimates
Start with labor costs
Compute indirect costs to get the total
manufacturing cost
Divide by the number of units for the
per unit cost
Account for margin of profit
This is referred to as the design to price
Target Costing
used by Japanese firms
top-down approach
focuses on what should the product cost
rather than what does the product cost
begins with market surveys to determine
competitors price
target cost(1 + Profit Margin) =
competitors price
target cost = competitors price/(1 + Profit
Margin)
Target cost is used as a goal for
engineering design, procurement, and
ABC Allocation
Activity-Based Costing Provides excellent allocation strategy and analysis of
costs for more advanced, high overhead, technologically-based systems
Cost Centers (cost pools) Final products/services that receive allocations
Activities Support departments that generate indirect costs for distribution to cost
centers (maintenance, engineering, management)
Cost drivers These are the volumes that drive consumption of shared resources (#
of POs, # of machine setups, # of safety violations, # of scrapped items)

Steps to implement ABC:


1. Identify each activity and its total cost (e.g., maintenance
at $5 million/year)
2. Identify cost drivers and expected volume (e.g., 3,500
requested repairs and 500
scheduled maintenances per year)
3. Calculate cost rate for each activity using the relation:
ABC rate = total activity cost/volume of cost driver

4. Use ABC rate to allocate IDC to cost centers for each activity
15-21 2012 by McGraw-Hill All Rights Reserved
Example: ABC Allocation
Use ABC to allocate safety program costs to plants in US and Europe
Cost centers: US and European plants
Activity and cost: Safety program costs $200,200 per year
Cost driver: # of accidents
Volume: 560 accidents; 425 in US plants and 135 in European plants

Solution:
ABC rate for accident basis = 200,200/560 =
$357.50/accident
US allocation: 357.50(425) = $151,938
Europe allocation: 357.50(135) = $48,262

15-22 2012 by McGraw-Hill All Rights Reserved


Summary
Developing cash flows for each
alternative in a study is a pivotal step
in the engineering economic analysis
procedure.
An integrated approach for
developing cash flows includes
determining the length of the analysis
period
fixing a perspective and determining a
baseline
a WBS definition of the project
Ethics and Cost Estimating
Unethical practices in estimation may be the result of:

Personal gain motivation

Bias

Deception

Favoritism toward an individual or organization

Intentional poor accuracy

Pre-arranged financial favors (bribes, kickbacks)

When making any type of estimates, always comply with the

Code of Ethics for Engineers

Avoid deceptive acts

15-25 2012 by McGraw-Hill All Rights Reserved

You might also like