Professional Documents
Culture Documents
DESPATCH COMPAN
COMPANY LIMITED (NTDCL)
2
PROJECT SCOPE
The Project
Package-1:
Lot-I : Jamshoro-Moro Section (202km)
Lot-II : Dadu-Moro-Goth Qazi Mahar Section (232km)
Lot-III : Goth Qazi Mahar- Rahim Yar Khan
Section (166km)
Package-2
500kV Switching Station at Moro
Extension works at existing 500kV Substation at
Jamshoro
Extension works at existing 500kV Substation at Dadu
Extension works at existing 500kV Substation at Rahim
Yar Khan
3
Financing
&
ADB Loan Proposed
Disbursement Schedule
4
Financing
Asian Development Bank (ADB) signed a
Loan Agreement with the Government
of Islamic Republic of Pakistan under
5
6
Progress Status of Package-1
7
Brief Summary
Lot-I: Jamshoro Moro (202 kM)
Contractor : M/S China National Electric Company, China -CNEEC
Acceptance of NOA: August 5, 2014
8
Construction and Material
Procurement Status
9
10
Construction Progress
LOT-I
Activity Newly Remainin
Total Foundatio Foundatio
No. of Completed g
Towers ns Already ns as per
Crews Foundation Foundati
(546) Completed New Scope
s ons
Convention
al 2 382 125 257 230 27
Foundation
Pile Cap/Tie
Beam 2 164 0 164 105 59
11
Status of Plants/Equipments and FATs (Lot-I)
Total Disbursement
Sr. Plants/ Quantity of Status/Material reached at 80% Amount in Million
Manufacturer Completed/Expected FATs
No. Equipments Plants / Store US $/RMB
Equipments
80kN=8000 80kN=8000
Porcelain 160kN=69000 160kN=69000 US$ 1.98M
Disc Reached at Site Store
80 kN =
Insulators Dalian, China
9,792
2. 80kN & Approved
160kN = NTD is issued RMB
160kN E&M Jan 22, 2015
133,650 80kN=8,635 15,353,615
Strength
(Fog Type) 160kN=88,627 will be shipped in August (To be Disbursed)
2016
Disbursement
Total Quantity of
Sr. Plants/ Status/Material 80% Amount in Million
Plants / Completed/Expected FATs
No. Equipments Manufacturer reached at Store US $/RMB
Equipments
13
Brief Summary
Lot-II: Dadu Moro Goth Qazi Mahar Section
(232 kM)
Contractor : M/S TBEA Co.Ltd,China
15
16
Construction Progress
LOT-II
Foundatio Foundati Newly
No. Remaini
Activity of Sectio
Total ns ons as Complet
ng
Towers Already per New ed
Cre n Foundati
(606) Complete Scope Foundati
ws ons
d ons
Conventi M-D 78 34
onal 37 28
2 88 83 5
Foundati M- 6 8
on 298 254
GQM
M-D 70 10
23
Piling 2 M- 0
78 152 148 4
160 68
GQM
Pile M-D 70 1
23
Cap/Tie 4 M- 0
54 176 159 17
Beam 160 53
GQM
M-D 148 0
60
Erection 1 M- 6
0 606 120 486
458 0
GQM
17
Status of Plants/Equipments and FATs
(Lot-II) Total Quantity of
Disbursement
Sr. Plants/ Completed/Expec Status/Material reached 80% Amount in
Plants /
No. Equipments Manufacturer ted FATs at Store Million US $/RMB
Equipments
US $ 2.63M
T = 535 T=209 Reached at store
Changshu, China
TR = 2
1. Steel Towers Approved
M = 55
Oct 02, 2014 T=260 Reached at store RMB 17,688,580
D = 15
ZTT, China
Conductor AAAC
3. Approved 2,784 km 960kM Reached at store RMB 21,315,072
Greeley
May 27, 2015
US$ 2.1932M
601.6kM NTD is issued (To be Disbursed)
18
Status of Plants/Equipments and FATs (Lot-II)
Disbursement
Total Quantity of
Sr. Plants/ Completed/Expected Status/Material 80% Amount in
Plants /
No. Equipments Manufacturer FATs reached at Store Million US $/RMB
Equipments
NTD is issued
ZTT, China
OPGW and Joint FATs carried out
4. Approved 232 km US $ 0.4237 Million
Box shipment will be start in
07-April-15
August, 2016
TBEA, China
RMB 489,646.08
5. EHS Shieldwire Approved 232 km FATs carried out NTD is issued
01-Sept-15
NTD is issued
Hardware For
Conductor Type Test and FATs (1st lot Shipped and
RMB 7,683,387.2
Mosdorfer, completed reached at Port
Austria Karachi and 2nd lot
6. shipment will be start in
Hardware For EHS Approved
Jun 08, 2015 August, 2016)
Shield Wire
&OPGW Additional Qty of Applied for the waiver
Hardware of FATs
Ground Rods =
Ground Rods = 460
Nanjing Shiyou, 460
Flat to Cable
China Flat to Cable FATs were carried out 0.02M
7. Grounding Material Connector = 550
Approved Connector = 550 for Total Material
Cable to Rod
April 07, 2015 Cable to Rod
Connector = 460
Connector = 460
19
Brief Summary
Lot-III: Goth Qazi Mahar Rahim Yar Khan Section
(166 kM)
Contractor : M/s Sinosteel Equipment & Engineering
Co. Ltd., China
21
22
Construction Progress
LOT-III
Foundatio Newly
Activity Total Foundatio
ns Completed Remaining
No. of Tower ns as per
Already Foundation
Crews s New
Complete Foundatio s
(442) Scope
d ns
Conventio
nal
Foundatio
2 309 229 80 65.75 14.25
n
23
Status of Plants/Equipments and FATs for Lot-III
Disbursement
80% Amount in
Sr. Total Quantity of Completed/Expected Status/Material
Plants/ Equipments Million US
No. Manufacturer Plants / Equipments FATs reached at Store
$/RMB
SGM =290,
RMB
TGM=2
SGM =102 9,819,751.20
AGM=10
SGM = 381 DGM=10 TGM=2 reached
Qingdao, China
AGM = 36 at Store and
1. Steel Towers Approved
DGM = 19 FATs carried out of 194 No. of Towers
Apr 10, 2015
TGM = 2 SGM = 94, reached at
Karachi Port US$ 0.7834M
AGM = 40 and
DGM = 9
NTD is issued
Porcelain Disc
Dalian, China 80kN=1000 Reached at US$ 0.12M
Insulators 80kN & 80 kN = 1,000
2. Approved 160kN=5000 store
160kN E&M Strength 160 kN = 5,000
Feb 09, 2015
(Fog Type)
Reached at
1001kM store US$ 4.02M
ZTT, China RMB
ACSR "Drake
3. Approved 1,992 km 991kM Conductor (553.6 km 24,235,896
Conductor
Mar 30, 2015 NTD is issued reached at
Store)
ZTT, China
OPGW and
4. Approved 166 km Reached at RMB
Joint Box
04-Jun-15 NTD is issued Store 2,383,800
24
Status of Plants/Equipments and FATs
for Lot-III
Disbursement
80% Amount in
Sr. Total Quantity of Completed/Expected Status/Material
Plants/ Equipments Million US
No. Manufacturer Plants / Equipments FATs reached at Store
$/RMB
25
Present Status of
Package-2
26
Brief Summary
Package-2
Contractor : M/s NEPCC-CHINT (J/V), China
28
29
30
31
32
Status of Plants/Equipment for Package-2
M/s NEPCC-CHINT (JV) have yet submitted Specific Plant Data for the
following Plants/Equipment
Disbursement
Total Quantity of
Sr. Plants/ Completed/Expected Status/Material 80% Amount in
Manufacturer Plants /
No. Equipments FATs reached at Store Million US $/RMB
Equipments
Disconnectors 5 Nos.
ABB, Beijing China US$ 1.4359 Million
with and without FATs carried out
3. Approved NTD is issued (To be Disbursed)
Earthing
Oct. 08, 2015
Switches 24 Nos.
Dalian, China
Material reached at
5. Disc Insulators Approved NTD is issued RMB 1,747,018.53
Site Stores
Aug. 20, 2015
33
Status of Plants/Equipments for Package-2
M/s NEPCC-CHINT (JV) have yet submitted Specific Plant Data for the
following Plants/Equipments
Disbursement
Total Quantity
Sr. Plants/ Completed/Expected Status/Material 80% Amount in
Manufacturer of Plants /
No. Equipments FATs reached at Store Million US $/RMB
Equipments
Substation
13. Automation NR Electric, China
System (SAS)
SCADA
System The Case of FATs are expected
Change of from September 15,
Manufacturer of 2016
(a) Gateway NR Electric is
Shanghai Schneider,
Communication approved by ADB Inspectors
14. China
Controller on May 18, 2016 Nominated
(b) Data
Highway Kyland, China
Interface
(C) Transducers Sfere, China
Asked for the
Nitrogen
Xuming Fire-Fighting Submission of FATs are expected
Injection and
15. (Shenzhen) and XIHARI from September 10,
Fire Protection
SERGI France accreditation 2016
System
Certificate
Revised Schedule is
Power Link
AC. Emergency Jiangsu Godlike, awaited
(Approved)
16. Diesel Weichai and Sitanfu,
Dated: April 20,
Generator Set China Inspectors
2016
Nominated
Submitted Revised
Drawings on July FATs are expected
Telecommunication
20. 21, 2016. from September 10,
System
The same are under 2016
review
Case of Change of
Chongqi, China to Manufacturer
Oil Purification Chonqing Ahonneng forwarded to Revised Schedule is
21.
Plant Oil purifier, China NTDCL for awaited
Approval dated July
27, 2016
Inspectors
Nanjing Daji,
Supporting Steel Nominated
22. China
Structure Revised Schedule is
(Approved)
awaited
Shanghai Besca
Revised Schedule is
23. Cable Tray Industrial Co., Ltd.,
awaited
China
36
Status of Plants/Equipments for Package-2
M/s NEPCC-CHINT (JV) have yet submitted Specific Plant Data for the
following Plants/Equipments
Disbursement
Total Quantity of
Sr. Plants/ Completed/Expected Status/Material 80% Amount in
Manufacturer Plants /
No. Equipments FATs reached at Store Million US $/RMB
Equipments
Switchyard
Submitted data on RFC
24. Connectors and Ribe, Austria
June 16, 2016 June 23, 2016
Hardware
37
Thanks
38