You are on page 1of 30

Department of Civil Engineering

University of Asia Pacific

Welcome to
Our
Presentation
Design of 6 Storied
Steel Building
Presented By
S. M. Tahmidur Rahman (ID 16215002)
Md. Mosaddaque Hossen (ID 16115005)
Md. Sadiqul Islam (ID 16115004)
Ibrahim Mohomed Omer (ID 15215001)
Afsana Sharmin Keya (ID 14205901)
Shuvo Basak (ID 13205084)
Dead & Live Load

Live Load: 6 KN/m2 (125 psf) (BNBC 15 T6.2.3)


Floor Finish: 25 psf
Brick Wall: Typical 5 Brick Work: (5/12)*120*12 = 600 lb/ft
Earthquake Load (BNBC 2015)
Co-efficient to estimate approximate period, Ct = .028, m =.8
(T 6.2.20)
Response Reduction Factor & other parameter (T 6.2.19)
R= 3.5 (OMRF), System Over strength Factor, 0 = 3,
Deflection Amplification Factor, Cd = 3
Occupancy Category III (T 6.1.1)
Importance Factor, I = 1.25 (T 6.2.17)
Seismic Zone 2 (T 6.2.14)
Spectral Accelerations (Appendix C T 6.c.1) : Ss = 0.5, S1 =
0.2
Site Class SB (T 6.2.13)
Long Period Transition Period = 2 s
Wind Load

Wind Speed for Dhaka: 65.7 m/s (147 mph) (T 6.2.8)


Exposure Category A (Art. 2.4.6)
Occupancy Category III (T 6.1.1)
Importance Factor, I = 1.15 (T6.2.17)
Topographic Factor, Kzt = 1 (Art 2.4.7)
Gust Effect Factor, G = .85 (Art 2.4.7)
Wind Directionality Factor, Kd = .85 (T 6.2.12)
Serviceability Check
Lateral Displacement & Inter Storey Drifts
Due to Seismic Forces
EQX
x = = x - Allowable Comment
Storey xe Cd I
Cd*xe/I xe (T 6.2.46) s

6 1.261659 3 1.25 3.027982 0.449498 2.16 OK


5 1.074368 3 1.25 2.578483 0.518635 2.16 OK
4 0.85827 3 1.25 2.059848 0.53569 2.16 OK
3 0.635066 3 1.25 1.524158 0.50094 2.16 OK
2 0.426341 3 1.25 1.023218 0.381324 2.16 OK
1 0.267456 3 1.25 0.641894 0.641894 2.9304 OK
Serviceability Check
Lateral Displacement & Inter Storey
Drifts Due to Seismic Forces
EQY
x = = x - Allowable Comment
Storey xe Cd I
Cd*xe/I xe (T 6.2.46) s
1.08724 2.60937 0.35198
6 3 1.25 2.16 OK
1 8 6
2.25739 0.42744
5 0.94058 3 1.25 2.16 OK
2 5
0.76247 1.82994 0.45746
4 3 1.25 2.16 OK
8 7 2
0.57186 1.37248 0.44482
3 3 1.25 2.16 OK
9 6 6
0.38652 0.39498
2 3 1.25 0.92766 2.16 OK
5 2
0.22194 0.53267 0.53267
1 3 1.25 2.9304 OK
P- Effect
EQX
=
Px*/V (allowable
x*hx*C ) = .5/ Comm
Storey Px Cd Vx hx d (*Cd) ent
0.4494 0.0070 0.166666
153.38
6 86.88 3 12 98 1 73 667 Ok
160.13 0.5186 0.0121 0.166666
5 134.88 3 7 12 35 1 34 667 Ok
119.81 0.5356 0.0162 0.166666
4 131.21 3 8 12 9 1 95 667 Ok
0.5009 0.0216 0.166666
83.614
3 129.95 3 12 4 1 26 667 Ok
0.3813 0.0276 0.166666
50.485
2 131.84 3 12 24 1 62 667 Ok
0.6418 0.1661 0.166666
20.311
1 256.73 3 16.28 94 1 24 667 Ok
P- Effect
EQY
=
Px*/V (allowable
x*hx*C ) = .5/ Comm
Storey Px Cd Vx hx d (*Cd) ent
0.4494 0.0070 0.166666
153.38
6 86.88 3 12 98 1 73 667 Ok
160.13 0.5186 0.0121 0.166666
5 134.88 3 7 12 35 1 34 667 Ok
119.81 0.5356 0.0162 0.166666
4 131.21 3 8 12 9 1 95 667 Ok
0.5009 0.0216 0.166666
83.614
3 129.95 3 12 4 1 26 667 Ok
0.3813 0.0276 0.166666
50.485
2 131.84 3 12 24 1 62 667 Ok
0.6418 0.1661 0.166666
20.311
1 256.73 3 16.28 94 1 24 667 Ok
Demand/Capacity Ratios (Grid 1)
Demand/Capacity Ratios (Grid 2)
Demand/Capacity Ratios (Grid 3)
Demand/Capacity Ratios (Grid 4)
Demand/Capacity Ratios (Grid 5)
Demand/Capacity Ratios (Grid 6)
Demand/Capacity Ratios (Grid 7)
Demand/Capacity Ratios (Grid 8)
DCR (Hand Calculation)
DCR (Hand Calculation)
DCR (Hand Calculation)
Beam
Connection & Base Plate
New Analysis (Grid 1)
New Analysis (Grid 2)
New Analysis (Grid 3)
New Analysis (Grid 4)
New Analysis (Grid 5)
New Analysis (Grid 6)
New Analysis (Grid 7)
New Analysis (Grid 8)