PROJECTS
PROGRESS (Up to 30/11/2016)
Project Name: Rehabilitation & Upgrading Of Naula-Elahara- Laggala-
Pallegama-Hettipola (B-312) Road , From Ch: 33+500km To
44+000km, 57+000km To 59+000km And Hasalaka-
Handungamuwa (B-484) Road -, From Ch: 20+000km to
45+000km
B312 B484
Total complete
33+500 - 44+000 57+000 - 59+000 20+000 - 45+000
Task Description % complete
Up to During Up to end of Up to During Up to end of Up to During Up to end of Up to During Up to end of
September October October September October October September October October September October October
Planned
Clearing &
Completed 20.80 - 20.80 3.30 - 3.30 47.45 - 47.45 71.55 - 71.55 99.9%
Grubbing
In progress - - - - - - - - - -
Planned
Roadway
Completed 20.80 - 20.80 3.30 - 3.30 47.45 - 47.45 71.55 - 71.55 99.9%
Excavation
In progress - - - - - - - - - -
Planned
Embankment
Completed 20.80 - 20.80 3.30 - 3.30 47.45 - 47.45 71.55 - 71.55 99.9%
Construction
In progress - - - - - - - - -
Planned
Sub Base
Completed 20.80 - 20.80 3.26 - 3.26 47.45 - 47.45 71.51 - 71.51 99.9%
Construction
In progress - - - - - - - - -
Planned
DGAB Construction Completed 20.80 - 20.80 3.26 - 3.26 46.71 0.74 47.45 70.77 0.74 71.51 99.9%
In progress - - - - - - - -
Planned
Shoulder
Completed 20.20 0.60 20.80 3.26 - 3.26 3.00 4.20 7.20 26.46 4.80 31.26 43.7%
Construction
In progress - - - - 22.40 - 22.40 22.40 - 22.40 -
Planned
Priming Completed 20.80 - 20.80 3.26 3.26 46.71 0.74 47.45 70.77 0.74 71.51 99.9%
In progress - - - - - - - - - -
Planned
Binder course
Completed 20.80 - 20.80 3.26 3.26 42.75 4.70 47.45 66.81 4.70 71.51 99.9%
In progress - - - - - - - - - - - - -
Planned
Wearing course Completed 20.80 - 20.80 3.26 - 3.26 40.13 7.32 47.45 64.19 7.32 71.51 99.9%
In progress - - - - - - - - - - - - -
Completed 18.60 - 18.60 0.50 0.50 11.60 3.50 15.10 30.70 3.50 34.20 48%
Slope protection
(Grassing) In progress - - - - - - - - - - - - -
Financial progress (According to Billing
Billin
g
Planned Cumula Value of Values)
Cumula Value of Planne Cumulati Rema
bill tive works tive Payment d ve rks
mont
h Value planned Certifie Value of Certified Cumul Progress
(Rs.) Bill d (Rs.) works after all ative of works
value Certifie add. and Progre certified(
(Rs) d (Rs.) ded. ss (%) %)
(Rs.)
May- IPC is not
17,993,303.37 17,993,303.37 - 0.00 0.00 0.56% 0.00%
13 submitted
July- 130,780,362.5
32,021,755.80 73,676,929.29 73,676,929.29 63,252,016.41 4.06% 2.29%
13 5
IPC-1
Aug-
100,415,598.3 231,195,960.9 certified
13 6 0
2,819,020.87 76,495,950.16 0.00 7.17% 2.37%
value is
zero
Sep- 312,250,353.1 IPC is not
81,054,392.25 - 76,495,950.16 - 9.69% 2.37%
13 5 submitted
Augu 2,322,394,349
75,173,352.23 54,841,888.27 100.00% 72.05% IPC-34
st .48
80%
% of Cum. Billing Progress
70%
60%
50%
40%
30%
20%
10%
Duration
0%
Sep-13 Nov-13 Feb-14 May-14 Jul-14 Oct-14 Dec-14 Mar-15 Jun-15 Aug-15 Nov-15 Jan-16 Apr-16 Jul-16 Sep-16
Jul-13 Oct-13 Jan-14 Mar-14 Jun-14 Aug-14 Nov-14 Feb-15 Apr-15 Jul-15 Oct-15 Dec-15 Mar-16 May-16 Aug-16 Nov-16
Physical Progress- S Curve
Cumulative Planned up to end of October 2016
= 100.00%
100.00%
Cumulative Actual up to end of October 2016
= 95.15%
90.00%
80.00%
70.00%
60.00%
50.00%
Physical progress %
40.00%
30.00%
20.00%
10.00%
0.00%
Month
Financial & Physical
Progress
Program % Progress %
(Reference to the revised
programme for balance work-
HOV/PM/505 dated 2015-08-04)
Financial Progress up to
end of September 2016 (up 100.00% 75.64%
to IPC-35)
Physical Progress up to
end of October 2016 100.00%
96.35%
Project Photographs (B484)
Surface preparation for turfing at ch. Surface preparation for turfing at ch.
38+650 to 38+750 RHS 42+900 to 42+960 RHS
Project Photographs (B484)