You are on page 1of 6

SAIPEM GROUP

HSE MANAGEMENT and


REQUIREMENTS for
CONTRACTORS

People Behind
Safety
SAIPEM GROUP
Reference Documents are:
Saipem S.p.A. Company Management Manual (COMM-SPA-E)
Vendor pre-qualification and data base management (WI-SPA-PROC-001-E)
Requirement definition and Rda management (WI-SPA-PROC-002-E)
Purchasing management and order issuing (WI-SPA-PROC-003-E)
Inspection and testing (WI-SPA-PROC-005-E)
HSE Requirements for Contractors (WI-SPA-HSE-012-E) and relevant specifics:
HSE Requirements for Contractors (SPC-SPA-HSE-001-E)
HSE Requirements for Contractors (SPC-SPA-HSE-002-E)
SAIPEM GROUP
Scope
The scope is defining the guidelines, operating procedures and responsibilities for
the management of Health, Safety and Environmental (HSE) aspects during the
selection of contractors and the management of their activities within the Company
and Projects.
The main aim is defining, at the tender stage, the HSE requirements related to the
service to be contracted. This activity shall be approached in a methodical way by
classifying the various products and services by commodity code.

Warning!!!

WE ARE RESPONSIBLE FOR OUR CONTRACTORS!


SAIPEM GROUP
Flow chart
Position Action
Project Manager List of Contractors

Project HSE Engineer Identify Commodity Code - issuing Specification (A or B)

Project HSE Engineer & Project Engineer Agreement checked

Project Manager & Project HSE Engineer Agreement approved


Project Manager Issue of RdA and transmission to Procurement Manager

Once received from the Contractors the HSE Documentation!!

Procurement Manager Verify compliance and transmission to Project Manager


Project Manager Evaluation
Project HSE Engineer Assistance to the PM Evaluation

Once completed, transmission to Procurement Manager for the Contract


HSE REQUIREMENTS FOR Form n. WI-SPA-HSE-012-E-A
SUBCONTRACTORS
Pag.1 di 1

HSE REQUIREMENTS FOR SUBCONTRACTORS


Job N / Purchase Order N: /

Client: Project:
A
Contracted Activity:
M.R. (R.d.A.) N:
Saipem Commodity Code:
Attached Specification:

B

NONE SPC-SPA-HSE-001-E SPC-SPA-HSE-002-E

Documents to be submitted with quotation in addition to the selected Specification:

NONE

Documents to be submitted upon assignment of the Purchase Order in addition to the


selected Specification:

NONE
D

REMARKS:

Issued Name: Signature:_______________________ Date:

Checked Name: Signature:_______________________ Date:

Approved Name: Signature:_______________________ Date:

NOTE: This form shall become integral part of the relevant Material Requisition (R.d.A.)
SERVICES SECTION
CODE DESCRIPTION SPECIFICATION
S002 CONSTRUCTION OF COMPLETE PLANTS
S00205 CONSTRUCTION OF COMPLETE PLANTS SPC-SPA-HSE-002-E
S00210 CONSTRUCTION OF CIVIL COMPLEXES SPC-SPA-HSE-002-E
S004 CIVIL WORKS
S00405 EARTH MOVING WORKS AND DEMOLITIONS SPC-SPA-HSE-002-E
S00410 CIVIL WORKS AT SITE AREAS SPC-SPA-HSE-002-E
S00415 SEA WATER INTAKE SPC-SPA-HSE-001-E
OFFSHORE CONSTRUCTION OF STRUCTURAL WORKS FOR SPC-SPA-HSE-002-E
S00420
INSTALLATIONS
S006 ELECTRICAL AND MECHANICAL ERECTION
S00605 SUPPLY AND ASSEMBLY OF STRUCTURAL WORK SPC-SPA-HSE-002-E
S00610 INSTALLATION OF SYSTEMS AND MACHINES SPC-SPA-HSE-002-E
S008 PAINTING, COATINGS, INSULATIONS AND SOUND PROOFING
S00805 PAINTING SPC-SPA-HSE-001-E
S00810 PIPE COATING SPC-SPA-HSE-001-E
S00815 ANTI-ACID COATINGS SPC-SPA-HSE-001-E