SCHEDULING

AOA AND AON PROBLEMS


Exercise 1
Job Predecessors Normal Time (days)
A - 10
B - 5
C B 3
D A, C 4
E A, C 5
F D 6
G E 5
H F, G 5

Find the critical path by using Arrow Diagram (Activity on Arrow)


Answer 1
4
D F
4 6
1 A
10 3 H
6 7
5
B C G
5 E
3 5 5

2 5
Answer 1
14 14

4
0 0 D F
10 10 4 6
1 A 20 20 25 25
10 3 H
6 7
5
B C G
5 E
3 5 5

2 5

5 8 15 15
Answer 1
14 14

0 0 4 0 0
0 0 D F
0 0
10 10 4 6
1 A 20 20 25 25
10 3 H
6 7
5
0 0
B C G 0 0
5 E
0 3 3 5
2 2 5 0 0

2 5

5 8 15 15

FF TF
Answer 1
14 14

0 0 4 0 0
0 0 D F
0 0
10 10 4 6
1 A 20 20 25 25
10 3 H
6 7
5
0 0
B C G 0 0
5 E
0 3 3 5
2 2 5 0 0

2 5

5 8 15 15

FF TF
Exercise 2

Find the critical path by using Arrow Diagram (Activity on Arrow)


Answer 2
Exercise 3
Activity Predecessors Duration
a --- 5
b --- 4
c a 3
d a 4
e a 6
f b,c 4
g d 5
h d,e 6
i f 6
j g,h 4
Answer 3
HOMEWORK DUE 5 MAY 2017
Make a clear and neat sketch of the network diagram
specified below using:
a) Precedence notation (Activity on Node)
b) Arrow notation (Activity on Arrow)
On the precedence diagram, calculate and show the early
start (EST), early finish (EFT), late start (LST), late finish (LFT),
total float (TF), and free float (FF) in each activity.
Start calculations with day zero (0). Show the critical paths
with colored highlights.
HOMEWORK:
The activity logic and durations are as follows:

Label Duration (days) Must follow operations


A 2 -
B 4 A
C 7 A
D 3 A
E 5 A
F 7 B
G 6 B
H 7 F
I 5 G
J 3 G
K 8 C, G
L 9 H, I
M 4 F, J, K
N 7 D, K
O 8 E, K
P 6 M, N
Q 10 N, O
R 5 L, O, P
S 7 Q, R