2015SW07
Presented By:
Naresh Suwal
M2016012
College of Water Conservancy and Hydropower
Significance of BBDMP at National level
Project of National Pride.
Nepals first large Multipurpose IWBT project
First time mechanized tunneling using TBM in Nepal
Paradigm shift for Department of Irrigation from small\medium towards
large multipurpose projects
Investigate in Nature: Experience gained in BBDMP will be pave way for
other IBWT project in Pipeline.
1. Sunkoshi-Marin
2. Kali Gandaki-Tihau
6/13/17 2
Main Objective
How????
By diverting and transferring 40 m3/s water from a snow- fed water
surplus Bheri river to water deficit Babai river
6/13/17 3
4
6/13/17
Phases of Project:
First Phase : A 12-kilometer tunnel will be dug
Second Phase : A hydropower project with installed capacity of 48 MW
will be built.
Third Phase :Irrigation works will be completed
6/13/17 5
6/13/17 6
Environmental Considerations:
6/13/17
7
Benefit due to BBDMP
Irrigation Hydropower
22 million USD 21 million USD 43 million USD
EIRR = 13.42%
B\C ratio = 1.36 at 10 % discount rate
6/13/17 8
6/13/17 9
References:
6/13/17 10
Thank you for kind attention.