Contract Management in

International Construction

Delay, Disruption and


Acceleration

Michael J.R. Kremer

Beijing, April 28, 2009


1. Introduction
Time is of essence in basically every construction
project
Yet, delays of some sort are general rule, rather
than the exception
Consequence: claims for extension of time, issue of
acceleration
Therefore, closer look to:
What are the obligations as to time in general?
When and how does acceleration become relevant?

Delay, Disruption and Acceleration April 2009 1


2. Contractors obligations as to time
Modern construction contracts typically foresee three
separate, but inter-related express obligations:

First obligation: Contractor to complete works by


certain date or within specified period; possibly with
stage or sectional completion obligation
Second obligation: Contractor to progress the works
regularly and diligently
Third obligation: Contractor to prepare and work to an
accepted program (work schedule)

Delay, Disruption and Acceleration April 2009 2


2.1 First obligation: specific date/period
In case of period for completion, identification of
commencement date as well as periods crucial
e.g.: x months from the Commencement Date
clarification of days and weeks

If no date or period foreseen: obligation to complete


by a reasonable time
Standard form contracts regularly provide for
express obligation

Delay, Disruption and Acceleration April 2009 3


2.1 First obligation: specific date/period (contd)
Effect of specific date of completion
typically no qualification as of the essence
clauses for extension of time or liquidated damages

prevent such interpretation


Specific date of completion of little assistance in
management of the project
Employer wants to take action early to avoid late
completion
stage or sectional completion obligations and
liquidated damages give only limited recourse

Delay, Disruption and Acceleration April 2009 4


2.2 Second obligation: progress regularly
If specific date for completion agreed, no implied
second obligation
Contractor has right to plan, execute and progress
the works
severe evidential difficulties for Employer

Therefore: express obligation (regularly included


in standard form contracts)

Delay, Disruption and Acceleration April 2009 5


2.2 Second obligation: progress regularly (contd)
Effect of express obligation to proceed regularly
and diligently
Proceed continuously, industriously and efficiently with
appropriate resources so as to progress steadily towards
completion substantially in accordance with the contract.
Contractor may not slow down even if ahead in
time schedule
Employer may have remedy of damages, even if

completed in time, if Employer can show loss

Delay, Disruption and Acceleration April 2009 6


2.3 Third obligation: program
program/work schedule no legal term
Requires basic information of activities or operation
with a list of dates for commencement and completion
of respective activities
Types of programs:
Bar Chart Network Program Line of Balance

Delay, Disruption and Acceleration April 2009 7


2.3 Third obligation: program (contd)
Potential roles of the program:
Monitor role:
- milestone program
- progress program
- prediction program

Dynamic role
- management program
- compensation program

Delay, Disruption and Acceleration April 2009 8


3. Employers obligations as to time
Completion of obligations specified in the contract
e.g. supply information, provide material, execution
of certain pre-condition works, permits,
appointment of engineer etc.
- at times specified in program
- or reasonable times with regard to execution of works
Typically no obligation to comply with approved
program, rather obligation not to hinder Contractor
implied obligation not to hinder
implied obligation to cooperate

Delay, Disruption and Acceleration April 2009 9


4. Acceleration
What does the term mean? What is the benchmark?
Basically, tow situations relating to the overall
works:
Contractor is required to finish earlier than the
contractual date
- variation of the contract, i.e. constructive order/change order
- constructive acceleration
Contractor is likely to complete later than the
contractual completion date
- acceleration to reduce delays

Delay, Disruption and Acceleration April 2009 10


4.1 Constructive acceleration
typical example for constructive acceleration claim:

Equipment procured by Employer from a third-party is


delivered late. Contractors words are delayed.
Contractor applies for Extension of Time (EOT). Interim
assessment of the Engineer denies EOT; final review
still pending. Employer presses Contractor to increase
resources to make up for the delay.

Delay, Disruption and Acceleration April 2009 11


4.1 Constructive acceleration (contd)
Contractors stark (unambiguous) choice:
Continue in hope to prove EOT or accept to be in
default temporarily and take steps to mitigate
Nature of problem: contracts EOT procedures
and contractors temporary default
Conclusion: Constructive acceleration claim
presents significant legal difficulties; claim for
disruption may be possible with fewer legal
difficulties

Delay, Disruption and Acceleration April 2009 12


4.2 Acceleration to reduce delays
The issue of right or obligation to reduce the effect of
qualifying delays may arise in three ways:

- Contractors may have right to choose how to deal with a


qualifying delay and whether to accelerate or not and to
recovery on the basis of this right;

- Contractor may be entitled to EOT and any associated loss


only to the extent that he has mitigated the effect of the delays;

- Contractor may be under an obligation to progress the works


including an express obligation to mitigate delays and the
failure to do so prevents remedies of EOT/associated losses.

Delay, Disruption and Acceleration April 2009 13


4.2 Acceleration to reduce delays (contd)
Mitigation of delay by acceleration?
Contractor reacts to the qualifying delay
- most contracts provide for EOT provisions and express terms
for agreement for acceleration
- generally no right of contractor to accelerate and recover costs
(except if constructive order)
- reasonabless-argument
Contractor does not react to the qualifying delay
- Generally no obligation where EOT provisions apply
Mitigation by managing delay?
obligation to re-plan recourses and activities
obligation to progress regularly & diligently includes
managing of effects of delay

Delay, Disruption and Acceleration April 2009 14


4.3 Obligation to accelerate?
Differentiation by reason for delay:
Delay not caused by Contractor, i.e. entitled to EOT
- no obligation; only by means of separate agreement
Delay caused by Contractor:
- in principle no obligation (discretion of contractor in regard of
his own culpable delay)
- contract may provide power to order Contractor to adopt
acceleration measures
Indirect obligation
Contractor must weigh costs of acceleration, chance of
recovery against liquidated damages potentially levied
against him

Delay, Disruption and Acceleration April 2009 15


4.4 Entitlement to acceleration
Contractor may perceive commercial advantage
to accelerate; generally only bound by completion
date
Generally no obligation of the Employer to co-
operate
Exception: entitlement of acceleration provided in
the contract and bound to program

Delay, Disruption and Acceleration April 2009 16


5. Conclusion
Time is of the essence in construction projects
The effort of planning, negotiating and drafting
does not end at providing sophisticated terms for
the event of delays by
finding a realistic completion date,
incorporating EOT provisions and delay related
liquidated damages
Instead, the same though and sophistication
should be put in addressing delays in terms of
acceleration, rather than only dealing with them in
terms of EOT and liquidated damages.

Delay, Disruption and Acceleration April 2009 17


Contract Management in
International Construction
Beijing, April 28, 2009

Delay, Disruption and


Acceleration

www.cliffordchance.com
Clifford Chance, Knigsallee 59, 40215 Dsseldorf, Germany
Clifford Chance 2009