You are on page 1of 44

CANAL:-

A canal is an artificial channel generally


trapezoidal in shape constructed on the ground
to carry water to the field either from the river
of from a reservoir.
Classification of CANAL:-
CANALS

NATURE OF BOUNDRY DISCHARGE & ITS


SOURCE OF FINANCIAL CANAL
SUPPLY FUNCTION SURFACE RELATIVE
OUTPUT ALIGNMENT
OF CANAL IMPORTANCE

1. PERMANENT
2. INUNDATION 1. PRODUCTIVE CANAL
CANAL 2. PROTECTIVE CANAL 1. IRRIGATIONAL 1. ALLUVIAL
CANAL 2. CARRER CANAL 2. NON 1. MAIN 2. BRANCH
3. MAJOR DISTRICUTORY 1. CONTOUR
CANAL 3. FEEDER ALLUVIAL CANAL
3. RIGID 4.MINOR 2.WATERSHED
CANAL 4.
NAVIGATION BOUNDRY CANAL DISTRUBUTORY 3. SIDE SLOPE
5. WATER COURSE
CANAL 5. POWER
CANAL
Classification of CANAL:-
Classification based on the nature of source of
supply:-
1. Permanent Canal.
2. Inundation Canal.

Classification based on the financial output:-


1. Productive Canal
2. Protective Canal
Classification of CANAL:-
Classification based on function of the canal:-
1. Irrigation Canal
2.Carrier Canal
3. Feeder Canal
4. Navigation Canal
5. Power Canal
Classification based on boundary surface of canal:-
1. Alluvial Canal
2. Non- Alluvial Canal
3. Rigid Boundary Canal
Classification of CANAL:-
Classification based on discharge and its relative importance
in a given network of canal:-
1. Main Canal.
2. Branch Canal.
3. Major Distributary .
4. Minor Distributary .
5. Water Course .
Classification based on Canal Alignment:-
1. Contour Canal .
2. Watershed Canal (Ridge Canal).
3. Side Slope Canal.
Canal Alignment:-
General consideration for alignment:-
1. It should be aligned in such a way that maximum area is
served with the least length. And its cost including CD- work
is minimum.

2. A shorter length of canal has less loss of head due to friction


and smaller loss of water due to seepage and evaporation, so
that additional area can be brought under cultivation.

3. The alignment should be kept straight as far as possible, it


will result in minimum losses.

4. It should have minimum CD work.


Canal Alignment:-
General consideration for alignment:-
5. It should not passes through the village, town, forest or
costly lands, otherwise heavily compensation shall have to
given.
6. It should be such that heavy cutting and filling (embankment)
are avoided.
7. It should through passes the ridge so that both side of canal
can be irrigated.
8. The alignment should be such that as far as possible a
balanced depth of cutting and filling is achieved.
9. The alignment should not be made in rocky, brackish or
cracked strata.
Balancing Depth:-
A canal section will be economical when earth work
involved at a particular section has an equal amount of
cut and fill. Usually a canal section has a part in cutting
and part in filling as shown in fig.
If the amount of cut is equal to the amount of fill, it
has to be paid for once only.
Definition:-
For a given C/S there is always only one depth of
cutting for which the cutting and filling will be equal. The
depth is known as balancing depth.
Balancing Depth:-
Balancing Depth:-
If :-
h = vertical height of top of bank from the bed of canal.
b = bed width of the channel.
t = top width of the canal bank.
n:1 = side slope of bank in filling.
z:1 = side slope of canal in cutting.
d = full supply depth of canal.
y = depth of cutting.
Balancing Depth:-
Area of the cut = by + zy2
= y(b + zy)

Area of fill = 2[(h y)t + n(h-y)2 ]


Equating the area of cut and fill:
y(b + z y) = 2[(h y)t + n(h-y)2 ]
b y+ zy2 = 2th + 2nh2 2nhy 2ty 2nhy + 2ny2
y2 (2n z) (b + 4nh + 2t)y + 2h(t + nh) =0
From this equation the balancing depth of the canal may
be determined.
Balancing Depth:-
A canal is usually constructed with side slope of 1:1 in
cutting and a slope 1.5:1 in filling.
Putting n = 1.5 and z =1 in above equation.
We get;
y2 (b/2 + 3h + t)y + h (t + 3/2 h)=0
Cross-section of canal:-
A canal is generally taken in such a way that its section
is partly in cutting and partly in filling in order to
approach close to balancing depth. Many times however
the canal has to be carried through deep cutting or
filling. A canal structure may, therefore, either :
1. In Cutting
2. In Filling
3. In Partial Cutting and Filling.
Cross-section of canal:-
Cross-section of canal:-
Cross-section of canal:-
Components of canal:-
Side slopes
Berms
Free board
Land width
Dowla or Dowel
Spoil banks
Borrow pit
Components of canal:-
Side slopes:-
The side slope constructed on both sides of the canal for
allowing the water to flow in between them. As the canal is
to be constructed in cutting and embankment or both.
Sr. No. Type Of Soil Slope In Cutting Slope In banking

1 Clayey Soil 1.5 : 1 2:1

2 Sandy Soil 3:1 4:1

3 Loamy Soil 1.5 : 1 2:1

4 Gravel Soil 0.75 : 1 1.25 : 1

5 Hard Rock 0.25 : 1 ----

6 Soft Rock 0.5 : 1 ----


Components of canal:-
Berms:-
This is horizontal distance, which is left at G.L.
between the top edge of cutting & toe of bank.
When water flows in the canal at FSL (Full Supply
Level), silt particles are deposited on the berms and
make the final side slope to 1.5:1
Components of canal:-
Free Board:-
It is the vertical distance between FSL and the top of
bank. It is provided to ensure that water does not
overtop the bank. The magnitude of the free board
in a channel is governed by the consideration of the
channel size and location, rain water inflow wind
action soil characteristics etc.
I.S. 7112- 1973 recommends a minimum freeboard =
0.5m
Components of canal:-
Land Width:-
The total land required for the construction of
channel is divided into the two parts.
1. Permanent Land
2. Temporary Land
Components of canal:-
Dowel or Dowla:-
A Dowel or Dowla is provided on the side of a service
road between the service road and channel.

The top of the dowel is kept above the FSL in the


channel the Dowel are provided as a measure of
safety for automobile driven on the service road.

They acts as a kerbs on the side of the road way


towards the canal.
Components of canal:-
Spoil Banks:-

When the quantity of earth obtained from


excavation or cutting is deposited near the
cutting in the form of bank known as spoil
bank.
Components of canal:-
Borrow Pit:-

When the earth work in filling exceeds


excavated quantity at particular section
borrow pit are required to make good
requirement of filling.
Canal Lining
It is the treatment given to the canal bed and
banks to make the canal section impervious. The
lineds
Canal lining is the process of
reducing seepage loss of irrigation water by
adding an impermeable layer to the edges of the
trench.
Seepage can result in losses of 30 to 50 percent
of irrigation water from canals, so adding lining
can make irrigation systems more efficient.
Common lining materials include compacted
earth, concrete, and plastic membranes.
Advantages of Lining
Water Conservation:
Lining a canal results in reduction in water losses, as
water losses in unlined irrigation canals can be high.

No seepage of water into adjacent land or roads:


If canal banks are highly permeable, the seepage of
water will cause very wet or waterlogged conditions, or even
standing water on adjacent fields or roads. Lining of such a
canal can solve this problem.
Advantages of Lining
Canal linings improve command:
Lining makes it possible to maintain high
velocity in the canal. Generally lined canals are
designed with normal value of silt factor (f= 1.2) and
maximum permissible velocity (from 1.8 m/sec to
2.5 m/sec).
For these values of f and V steepest
practicable longitudinal slope may be adopted. Even
then this slope will be flatter than the slope of
unlined canal.
Advantages of Lining

Thus this flat slope raises the FSL in general


and brings the high area of land under command
which have not been irrigated before.
Another advantage of maintaining high
velocities can be recognized from the fact that
lined canals require smaller sections to convey
same amount of water as that carried by unlined
canals.
Advantages of Lining
Canal linings increase available head for power
generation.

Canal linings make the canal section stable.

Canal linings prevent bank erosion and breaches.

Canal linings assure economical water


distribution

Canal linings reduce maintenance costs


Types of Canal Lining
Hard Surface Lining Earth Type Lining
Cast Insitu Cement Compacted Earth
Concrete Lining Lining

Shotcrete or Plastic
Soil Cement Lining
Lining

Cement Concrete Tile


Lining or Brick Lining

Asphaltic Concrete
Lining

Boulder Lining
Types of Canal Lining
Exposed and Hard Surface Linings

Earth type canal lining.

Buried Membrane Linings


Types of Canal Lining
Exposed and Hard Surface Linings:-
It includes all linings exposed to wear, erosion and
deterioration effect of the flowing water, operation and
maintenance equipment and other hazards.
Such linings are constructed across of cement concrete
and mortars, asphaltic materials, bricks, stones and exposed
membranes.
Although the initial cost of all these linings is generally
high, the reinforced cement concrete linings are costliest
and are usually recommended for use only where structural
safety is the primary consideration
Types of Canal Lining
Exposed and Hard Surface Linings:-
1. Cast in situ cement concrete lining
2. Shotcrete or plastic lining.
3. Cement concrete tiles lining or Brick
lining.
4. Asphalt concrete lining.
5. Boulder lining.
6. Exposed Membrane Linings.
Types of Canal Lining
Earth type canal lining.
Thick compacted earth lining is durable and can
withstand considerable external hydrostatic pressure.
Bentonite has shown considerable promise for use as
a good lining material.
Bentonite containing large percentage of
montmorillonite, is characterised by high water
absorption accompanied by swelling and
imperviousness. It can be used as 5.0 cm thick
membrane covered by protective blanket or as a
mixed inplace layer of soil bentonite and well
compacted.
Types of Canal Lining
Buried Membrane Linings
Hot-applied asphaltic, prefabricated asphalt
materials, plastic film and a layer of bentonite
or other types of clays protected by earth or
gravel cover are cheap linings. These linings
can be provided immediately after completion
of excavation or even later. Membrane linings
are susceptible to damage by weed root and
permissible water velocity is limited to avoid
erosion. The life of the lining is uncertain.
Cast In-situ Cement Concrete Lining
Shotcrete & Plastic Lining
Canal Lining

CONCRETE LINING
Canal Lining

Concrete tiles canal lining


Canal Lining
Brick canal lining

PREFABRICATED CHANNEL
SECTION
Canal Lining
GEOPOLYMER CANAL LINING

You might also like