ABB Group
July 6, 2017 | Slide 2
132/33KV Substation at Karanja (Lad), Amravati
2007-08
LOA No- MSETCL/CO/TKP-I/ABB/T-0701/6801,02,03 dated
26.06.2007
Supply Value- Rs.114,131,535/-
ABB Group
July 6, 2017 | Slide 3
132/33KV Substation at Karanja (Lad), Amravati
2007-08
Total Amount of work Executed
Supply Value- Rs. 11,72,53,688/-
ABB Group
July 6, 2017 | Slide 4
132/33KV Substation at Rajur, Aurangabd 2007-08
ABB Group
July 6, 2017 | Slide 5
132/33KV Substation at Rajur, Aurangabd 2007-08
ABB Group
July 6, 2017 | Slide 6
132/33KV Substation at Chandwad, Nasik 2007-08
ABB Group
July 6, 2017 | Slide 7
132/33KV Substation at Chandwad,Nasik 2007-08
ABB Group
July 6, 2017 | Slide 8
132/33KV Substation at Lakhandur, Bhandara
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.10,64,25,738/-
Civil Value- Rs. 1,80,46,345/-
Erection Value- Rs. 41,37,967/-
Complision Period-12 Months from date of LOA
Date of Handing over of Site-21/08/2009
Date of Complision of work - (12 Months from LOA)
Present status/progress at Lakhandur s/s
Supply of Material- 90%(132 & 33KV CB,Earting material,Gantry
& equipment structure,station Trafo,Disc Insulators,CI
Pipes,132 & 33KV Isolator, 132KV CT & PT, )
Civil Work- 132KV Gantry Foundation (100%), Control Room
(Plint Level) (80%), 33KV Gantry Structure -(100%), 132 & 33KV
equipment structure (90%)
Erection Work- 33KV gantry structure(100%), 132KV Gantry
structure(80%), 132 & 33KV Equipment Structure (60%)
ABB Group
July 6, 2017 | Slide 9
132/33KV Substation at Lakhandur, Bhandara
2009-10
Delay in Civil Work due to layout changes in SLD,Plan &
Section layout from site.
Delay in Civil drawings due delay in SBC report.
Even though ABB taking over site in Aug-09, progress of s/s
is per schedule but due revision in plan layout approvals
progress of s/s delays.
Payment for s/s work has been made as per activity
schedule of aggrement due to which our bills of supply has
been held up. We request you to make payment of material as
per actual progess of project
Date of Commessioning as per Aggrement- 02/06/2010
Excepated date of Complision of Project- 30/08/2010
ABB Group
July 6, 2017 | Slide 10
220/132/33KV Substation at Balapur, Amravati
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.35,69,51,733/-
Civil Value- Rs.4,73,49,861/-
Erection Value- Rs.1,03,36,452/-
Complision Period-12 Months from date of LOA or MSETCL
Clerance letter i.e.27/08/2009
Date of Handing over of Site-21/12/2009
Date of Complision of work - (12 Months from LOA or MSETCL
clerance letter)
Present status/progress at Balapur s/s
Supply of Material- 85% (220,132 & 33KV CB, 350MT Gantry
& Equipment Structure, CI pipes,220,132 & 33KV
Isolator,220 & 132KV CT & PT,Disc insulator)
Civil Work- 220KV Gantry-60%,132KV gantry-60%, 220KV
Control Room Excavation-50%
Erection Work-Yet to started expected in May-2010
Earthing Of s/s 132KV & 33KV 40%
ABB Group
July 6, 2017 | Slide 11
220/132/33KV Substation at Balapur, Amravati
2009-10
Delay in Work due to three times change in layouts from
division & Circle office also delay in Civil drawings due delay
in SBC report.
Resions for Delay in work for Balapur s/s
SLD,Plan & Section layout changes three times from
02.09.2009.
Delay in SBC reports and Civil Drawings.
ABB Group
July 6, 2017 | Slide 12
132/33KV Substation at Barshi-Takli, Amravati
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.10,29,94,153/-
Civil Value- Rs.2,18,98,377/-
Erection Value- Rs.41,33,423/-
Complision Period-12 Months from date of LOA or MSETCL
Clerance letter (Still awaited). MERC approval is still awaited
from MSETCL due to which site handing over and other
activities are pending.
Date of Handing over of Site- Pending due to MERC approval
Date of Complision of work - (12 Months from LOA or MSETCL
clerance letter)
Present status/progress at Balapur s/s
Supply of Material- Nil
Civil Work- Nil
Erection Work- Nil
ABB Group
July 6, 2017 | Slide 13
220/132/33KV Substation at Bambhori, Jalgaon
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.27,82,47,159/-
Civil Value- Rs. 3,18,14,871/-
Erection Value- Rs. 73,26,355/-
Complision Period-12 Months from date of LOA
Date of Handing over of Site -09/09/2009
Date of Complision of work - (12 Months from LOA)
Present status/progress at Bambhori s/s
Supply of Material- 90%(220KV,132 & 33KV CB, Earting material,
310MT Gantry & equipment structure,station Trafo,Disc
Insulators,CI Pipes,220,132 & 33KV Isolator, 220,132KV CT & PT )
Civil Work- 220KV Gantry foundation- 90%,132KV Gantry
Foundation (100%), Control Room (80%), 33KV Gantry Structure -
(100%), 220,132 & 33KV equipment structure (90%)
Erection Work- 33KV gantry structure(100%), 220KV & 132KV
Gantry structure(80%), 132 & 33KV Equipment Structure (70%)
ABB Group
July 6, 2017 | Slide 14
400KV Switching Substation at Chandrapur,
2009-10
LOA No- C.E/Tran.Proj/TKC-I/T-0804/29/10393,94,95 dated 31.07.2009
Supply Value- Rs.22,02,26,444/-
Civil Value- Rs.11,14,48,891/-
Erection Value- Rs.46,14,719/-
Complision Period-18 Months from date of Handing over of
Site.
Date of Handing over of Site- Pending due to Varieous Issue
Approch road to Site of 0.5KM is not ready
Compound wall & its coordinates points are pending
SLD, Plan & Section layout submitted for approval from
Oct-09 and approved on 08.02.2010.
Due to dealy in layout approval material/equipment
quantity can not freez & its activity schedule can not
complited within time.
ABB already nominated civil & Erection Contractor from
our end
ABB Group
July 6, 2017 | Slide 15
400KV Switching Substation at Chandrapur,
2009-10
Date of Complision of work - (18 Months from date of
handing over of site)
Present status/progress at Chandrapur s/s
Supply of Material- Nil
ABB Group
July 6, 2017 | Slide 16
THANK YOU