Professional Documents
Culture Documents
4
Facts & Problems........
ROAD TRANSPORT FOR THE PAST 50 YEARS
1951 1999
Length (Million Kms) 0.4 3.3 (Eight Fold)
No. of vehicles 0.3 50 (170 fold)
Unbonded Bonded
8.49 Mpa 2.90 MPa
0.6m 0.6m o.6m 1.8m
50mm Ac 100mm AC
72 hrs
from the time the laying is completed
Why Is WT Not Popular in India?
• WT thickness is 180-200mm and is 3 times
the cost of bituminous overlay. ( based on
TMC data).
• Due to high cost difference , WT is not
popular.
• The time for construction is high compared
to bituminous construction leading to
longer traffic disruptions.
Surface Technology’s White Topping
48
Plants for quarry roads for transportation
of limestone into the factory
49
Cement Works – Jharkhand Cement Works.
50
Basic Consideration for the Design of White Topping
52
Support of the existing bituminous pavement
53
Surface Preparation
• Shoving , rutting and potholes need to be
repaired.
• Areas with sub grade failure should be
removed and replaced.
• Depending upon the surface distortion
decide to directly clean and place concrete
or mill and place concrete.
54
White Topping (WT) Design
• AC/DBM bottom strain due to an 8.16 ton single axle
load
• AC/DBM bottom strain due to an 16.2 ton tandem
axle load
• WT corner top stress due to an 8.16 ton single axle
load , kg/cm2
• WT corner top stress due to a 16.2 ton tandem axle
load, kg/cm2
• Additional AC/DBM bottom strain due to
temperature gradient
• Additional WT corner top stress due to temperature
gradient , kg/cm2
• Thermal coefficient of expansion of the PCC
55
WT Design
• Temperature gradient in WT
• Adjusted slab thickness as defined
by the equation.
• Modulus of sub-grade reaction
• Effective radius of relative stiffness
for a fully bonded systems
• Modulus of elasticity of WT PCC
56
Design Considerations of WT
57
Construction Steps for WT
• Core existing surface for bituminous
depth.
• Mill and clean the surface.
• Place, finish and cure the concrete.
• Cut joints early with early entry saw.
• Open to traffic.
58
Why does White Topping (WT) have such short
joints?
The short joints in white topping are
used so that the slabs do not bend
but deflect under wheel load and
come back after the load has passed.
59
What is the typical lifespan of a white topping
pavement?
60
61
Typical Road Improvement Costs With
Conventional Technologies
Road Length and Cost ( TOI:27/09/2005)
3500
3200
3000
2500
2000
Asphalt
1590.34
Concrete
1500
1000
700
500 350.82
0
km Rs./sqm
Surface Technology WT
• Cost Effectiveness can be worked out based on
the site conditions.
Final Mix Proportion
• Final concrete mix proportion arrived
Quantities (kg per cum of concrete)
Cementitious = 530
(cement+mineral)
Water = 180 (w/cementitious ratio = 0.3)
Coarse Agg. = 1000
Fine Agg. = 900
Chemical Adm. = 2.5% by weight of cement (PC based)
65
Test Results Of High Tensile Strength
Pavement Quality Concrete
NEW TECHNOLOGY
GROUTE 240
476
50MM 800
Cost optimization
• Optimizing Design
• Selection of material
• Simple cost effective equipments
• Use of local materials
• Minimum skilled and unskilled labor-semi
skilled worker
• Labor oriented
• Adopting proper technology
Design
• Adjusting spacing of joint
• Selecting proper loadings
• Selection of grade of concrete depending on
stresses
Equipments
• Minimum investment
• Simple –easy to maintain ,least operating cost
• Not targeted for high output
• Weigh batching mixer of 6 to 8 Cubic meter per hour-3.5 lakhs
• Simple good quality screed to get line and level -3.5 lakhs
• Heavy plate compactor- 1.5 lakhs
• Joint cutting- 1.0 Lakhs
• Miscellaneous- 0.50 lakhs
• Total - 10 lakhs
• Output per year 10000 cub meter
• The cost of owning operation, maintenance etc would be about Rs 40 Per
cubic meter
Materials
• Specially designed Semi self compact concrete with fly ash to
• Get proper line and level with minimum efforts
• Vibration not needed making it attractive
• Specially developed sealant
• GSB/WMM of local material
Or
20mm carpet
50mm BBM
500 mm Subgrade
CONCRETE PAVEMENT
Advantages :
• Whole life cycle cost less
• Fuel saving up to 20 %
• Low Recurring maintenance cost
• Improper maintenance of flexible pavement
due to inadequate grant leads to total
deterioration and loss of assets.
Concrete Pavement-Suggested optimum crust
150 to 160 mm M 35 grade concrete
PQC or
M 45 grade concrete
Depending on
design load
Semi self compact
concrete
50mm Voided Voided concrete with
Concrete single size Joint spacing of 2.25
Or 75mm GSB aggregate
with 2 % cement To 2.5 m
GSB as per Month
Spn
500 mm sub grade
Concrete Pavement-role of Joint spacing in
optimization
(i)
Spacing between Contraction Joints:-Temperature stresses proportionate to
joint spacing.
Optimum spacing is 2.25 to 2.5 m.
Reduced joint spacing will reduce joint width and hence improve riding
comfort.
Reduce joint width reduces sealant consumption and hence cost.
Reduce joint width reduces cutting cost as the same can be done in single
operation.
Concrete Pavement
ii) Temperature Stress
It is observed that the temperature stress depends upon the size of the panel, i.e.
the spacing of transverse contraction joint. The temperature stress calculated for
rural road for concrete slab width of 15 cm – 20 cm considering a joint spacing of
2.5 m, 3.75m and 4.5 m for the State of Maharashtra are given as under.
15 24.911 38.758
16 22.609 35.277
17 20.639 32.282
18 18.940 29.685
19 17.461 27.416
20 16.165 25.422
Concrete Pavement
• Therefore the stresses due to wheel load and temperature along
Longitudinal Edge, which is a critical condition for various thicknesses of
slab is given below:
For a Transverse Contraction Joint spacing of 2.5m c/c.
Slab 3.0 t wheel load (Design 5.1 t wheel load (check)
thickness condition)
Stress Stress due Combine Stress due Stress due Combined
due to to stress to wheel to stress
wheel temperature (Kg/cm2) load temperature (Kg/cm2)
load (Kg/cm2) (Kg/cm2) (Kg/cm2)
(Kg/cm2)
Assumptions
• Axle Load 5.1 ton
• Joint spacing 2.25 meter
• Separator with suitable material against joint cutting
• Grade of concrete M 45
• Cost is Rs 560 per square meter which is 21.74 % above
compared to flexible pavement if elements above sub grade
alone are taken. Overall cost would be much less than 15 %
hence within PMGSY norms
Rigid Pavement-Optimum cost
• With reduced axle load
• Assumptions
• Axle load 3.1 ton
• Joint spacing 2.25 m
• Slab thickness 15 Centimeter
• Grade of concrete M 35
• Cost is Rs 535 per square meter which is 16.30 % above
compared to flexible pavement if elements above subgrade
alone taken. Overall cost would be much less than 15 %
hence within PMGSY norms
Is White Topping new?
The first white topping pavement was
reportedly placed in 1918, and has been
used on hundreds of projects. In the 1990’s,
new developments to white topping design
and construction were made, such as the
identification of Ultra-Thin White topping
(UTW) as a pavement type alternative. In the
last 10 years, white topping has been making
a “comeback” as a viable paving alternative.
90
What types of white topping are there?
White topping is commonly classified into three
categories:
1.Conventional White Topping,
2. Thin White Topping, or Ultra-thin White Topping
(UTW). The classes are based on the thickness of the
new concrete layer. Conventional white topping is
the thickest, constructed with 200mm or more of
concrete.
3. Ultra-thin white topping is the thinnest class,
commonly constructed from 50 to 100mm thick.
Thin white topping is the intermediate thickness –
100 to 200 mm – where new opportunities lie to, in
some cases, significantly increase the life of an
existing pavement.
91
What kinds of pavement distresses commonly
occur in white topping?
In thinner white topping, such as UTW,
corner cracking is commonly the
predominate distress type. The thickness,
panel size, and HMA type are dominating
parameters driving the rate of cracking.
Larger panels, used in thicker white topping
sections, typically develop other types of
distress, such as mid-slab cracking and
faulting.
92
When is white topping not an option?
93
Is white topping Limited to Use on Low Traffic Volume Roads?
96
Is special construction equipment required to construct white topping
pavements?