Professional Documents
Culture Documents
PLANNING DEPARTMENT
AN OVERVIEW
A. K. DATTA
REAL PLANNING
1
30/09/2004 JAMNAGAR
PROJECT DEFINITION
Construction Complete
(Except Check List Points)
Project GO Decision
5-10%
4
PROJECT MANAGEMENT -
WORK FLOW DIAGRAM
5
ORIENTATION COURSE IN
PLANNING DEPT. AN OVERVIEW
Type of Projects
Grass root
Expansion
PCO /QYI/VMP Projects
(Some belonging to cost savings / reliability
/ Operability / Yield Improvement /Value
Maximization etc.)
INTERCONNECTED PROJECTS
(Completed projects As an example)
Commissioning of south basin (Phase I/Phase II)
and HBJ pipeline projects,linked with gas based
fertilizer projects. (All projects to run
concurrently) 6
WBS
7
WORK BREAK DOWN STRUCTURE
(SAMPLE)
LEVEL 1 CRUDE QYI PROJECT
LEVEL 3
FRONT END ENGG DETAIL IMPORTED INDIGENOUS Pre-Comm Comm
ENGG & Start Up
SCHEDULING
Scheduling is the preparation of a time table for
implementation for a project.
Fixation of time table for all activities / milestones.
Resource calculation.
Develop schedule progress S Curve.
WTD value calculation for progress measurement.
9
MONITORING & CONTROL
MONITORING:
Monitoring is close follow up of the progress of the job and identifying
critical areas / project trend analysis, Highlighting Deviations from
schedules & corrective action plans on a continuous basis.
Measuring
Reviewing
Reporting
Action
CONTROL:
To take corrective actions so to put back the project progress on
schedule. As required, till completion of the project.
10
ORIENTATION COURSE IN
PLANNING DEPT. AN OVERVIEW
PLANNING, SCHEDULING, MONITORING & CONTROL
YES
Project
Complete 12
TOOLS FOR MONITORING PROJECT
ON TIME ASPECT
EPC Schedule / Construction Schedule / Shutdown
Schedule (Const. Activities) As Applicable to Project
DDS (Engineering Schedule All Disciplines covering
Total Scope)
Schedule Updation / Revision & Rescheduling
Identification of Critical areas & Action Plan
List of Constraints
Project Trend
Fortnightly / Weekly / Daily Progress Report
Development of S Curve / Progress Measurement
13
TOOLS FOR MONITORING PROJECT
ON TIME ASPECT
Monthly / Weekly Constn. Program Vis a Vis Work
Front Availability & Resource Requirements
Preparation of Planning Documents for Project Review
Meetings / PIO Meetings
Generation of various Reports for the Management (As
& when required) on time aspect
Maintenance of Databases
Scheduling :
Activity / Milestone Scheduling
Quantum Scheduling
Micro Level Scheduling & Monitoring 14
PLANNING TERMINOLOGIES
Mechanical Completion
Pre-Commissioning
Commissioning / Start Up
Zero Date, Start Date, Effective Start Date
3 Tier Planning, Scheduling & Monitoring Schedule Levels
Project Trend
Baseline Schedule, Short-term Schedule
Recovery Plan / Catch Up Plan
Project Planning, Construction Planning, Central Planning
Activities List, Milestone List
Resource Planning
Project Work Load
Work Front Availability, Weekly / Monthly Construction
Program 15
PLANNING TERMINOLOGIES
Schedule Updation, Revision, Re-scheduling
Schedule Review
Productivity Data
Project Execution Strategy
Project Performance
Project Implementation (EPC) / Handing Over
Project Termination
Project Key Dates
Project Approval
Pre-Project Activities
Project Data
Project Close Out Report
16
CONSTRUCTION RESOURCE &
INFRASTRUCTURE FACILITIES
DEVELOPMENT OF
RESOURCES INFRASTRUCTURE
FACILITIES
18
ORIENTATION COURSE IN
PLANNING DEPT. AN OVERVIEW
KEY POINTS - PROJECT SCHEDULING, MONITORING &
CONTROL
II. Project Scheduling, Monitoring & Control remains the
same
Irrespective of type of Project
Whether it is for Refinery/Petrochemicals/Infocom.
Projects/Power Projects / Infrastructure Projects / Any
other category Projects.
III. Each and every individual directly responsible for project
implementation should own & monitor / control his
portion of activities (i.e to the extent his involvement out
of total Project) from start to completion .This is the basic
requirement for the Project success.
19
ORIENTATION COURSE IN
PLANNING DEPT. AN OVERVIEW
KEY POINTS - PROJECT SCHEDULING, MONITORING &
CONTROL
DEVELOPMENT OF
LOGISTICS &
WORK BREAKDOWN INFRASTRUCTURE
STRUCTURE (WBS)
NETWORK DIAGRAM
WEEKLY SCHEDULES
-QUANTUM SCHEDULES WITH
PROGRESS EVALUATION
WORK FRONT
BACKUP SLIDE 21
PROJECT COMPLETION
OVERVIEW OF CENTRAL PLANNING
REAL/JAMNAGAR
CONVENTIONAL JOB-PROJECT COMPONENTS
% PROGRESS
PROJECT PROGRESS ( TYPICAL )
I) Process / Basic Engineering - 2%
II ) Detailed Engineering - 10%
III ) Ordering - 2%
IV ) Manufacturing/Delivery - 55%
V) Tendering - 1%
VI ) Construction - 30%
TOTAL = 100%
BACKUP SLIDE 22
OVERVIEW OF CENTRAL PLANNING
REAL/JAMNAGAR
3-Tier Planning & Monitoring System
Level Corporate Management
EPC Schedule
Construction Schedule / S/D Schedule
Level Functional Management
Schedule for Engineering / Procurement / Construction
Level Job Leader
Document / Drawing Schedule (IFC Drawing)
Procurement Schedule (All Bulk as well as Tagged Items)
Construction Schedule(Covering all Construction disciplines jobs
as per Project Scope)
BACKUP SLIDE 23
OVERVIEW OF CENTRAL PLANNING
REAL/JAMNAGAR
PROGRESS REPORT FOR FCO/QYI/VMP PROJECTS
(REAL JAMNAGAR)
Chapter Contents:-
I. Fortnightly / weekly report II. Daily Shutdown progress
1. Executive summary (constn.) Report
2. Construction s curve 1. Brief progress Status
3. Critical Issues 2. System wise Piping
4. Construction Schedule progress
5. Front Analysis & Work Program 3. Milestone progress for
6. List of Piping Materials Constraints internal jobs
7. Piping status (Fabrication / Erection) 4. Milestone progress for
8. Materials Constraints List nozzle jobs
for Tagged Items 5. Other constn jobs as
9. Piping Material (Weldable) control applicable but not covered
sheet above
10. Area of concern/Action Plans
BACKUP SLIDE 24
Project Trend
Typical Project Trend
DATE OF REVIEW
2
( - ) Months ( + )
-1
-2
-3
-4
-5
-6
Month Calender 1 2 3 4 5 6 7 8 9 10 11 12
(+) Advance
0 0 0 0 0.5 1
(-) Delay