You are on page 1of 24

CPM/ PERT

Critical Path Method/ Program


Evaluation and Review Technique

Operation Research II
Prepared By:
Jomari Gingo
BSIE 4-1
CPM/ PERT
Network-based methods design to assist
planning, scheduling and control of time
consuming project.
Provides analytic mean for scheduling the
activities.
Use to know bottlenecks and critical activities
Phases for Project Planning with
CPM/PERT

Define Network
Network Time
Project Scheduling
Calculation
Activities
Defining Project Activities
CPM
Assumes deterministic activity duration.

PERT
Assumes probabilistic duration. The time to
perform each activities appears uncertain and as
such thru time estimate is needed as (optimistic,
pessimistic and most likely) are used,
Defining Project Activities
PERT
Optimistic time- denoted as a, which occurs when
execution goes extremely well.
Most Likely time- denoted as m, which occurs
when execution is done under normal condition.
Pessimistic time- denoted as b, which occurs
when execution goes extremely poorly.
Defining Project Activities
PERT
Expected time
average of the time (optimistic, pessimistic, and most
likely

Expected time=
(a+4m+b)/6
Defining Project Activities
Other Concept
1. Critical Path- consist of the sequence of those events and connected
activities that require maximum time in the completion of the project it
is that path that takes the longest time. It is critical because it control the
completion date of the project.
2. Bottleneck activities-any delay in the completion of one or more of these
activities will cause delay in the completion of the activity.
3. Earlier Start Time (ES)- Beginning of the activity.
4. Earlier Finish Time (EF)- Sum of the earliest start time and estimated
time to perform the concerned activity.
5. Latest Finish Time (LF)- an activity that can finish without delaying the
project beyond its deadline on the assumption that all subsequent
activities are performed as planned.
6. Latest Start Time (LS)- is the difference between the latest finished time
and the estimated time for the activity to be performed.
Network
Legend for making Network:

Event Activity

ES and EF Dummy

LF and LS
Network
Network Representation Rule:
Rule 1: Each activity is represented by one, and only one arc.
Rule 2: Each activity must be identified by two distinct end
nodes.
Rule 3: To maintain the correct precedence relationship, the
following questions must be answered as each activity is
added to network.
1. What activities must immediately precede the current
activity?
2. What activities must follow the current activity?
3. What activities must occur concurrently with the current
activity?
Network
Using Dummy:
2
A C
A
1 2 B
B 1 3

A A B
C 1

1
D
C E
B 2
E
Network
Important note: In case of multiple activity

In ES and EF
Choose the largest value

In LS and LF
Choose the smallest value
Example 1: Activity Project
Activity a b m (a+4m+b)/6
A 1 2 3 2
B 1 2 3 2
C 1 2 3 2
D 1 2 9 3
E 2 3 10 4
F DUMMY 0
G 3 6 15 7
H 2 5 14 6
I 1 4 7 4
J 4 9 20 10
K 1 2 9 3
L 4 4 4 4
Example 1: Network
8 11
2 5 11
7 3 D=3
6 6
2
7
2 11
11

E=4 6 6 I=4
A=2 F=0
5 11
6
5 15 15
0 10
4 15 15
B=2 6 6 G=7
0 15
1 2 4 2 8 9
15
0 L=4
9
0 6 15
2 15
C=2 H=6
K=3
12
2 8
2 12
2 J=10 12
2 2 7
12
12
Example 1: Network Calculation
Activity ES LS EF LF Slack (LS- Critical
ES or LF- Path
EF)
A 0 5 2 7 5
B 0 4 2 6 4
C 0 0 2 2 0 YES
D 2 8 5 11 6
E 2 7 6 11 5
F DUMMY
G 2 8 9 15 6
H 2 6 8 12 4
I 6 11 10 15 5
J 2 2 12 12 0 YES
K 12 12 15 15 0 YES
L 15 15 19 19 0 YES
Example 1: Network Calculation
Note:
LS-ES and LF-EF are always equal and is
called slack

Slack with zero values are the critical


path
Example 2: Problem
A publisher has a contract with an author to
publish a textbook. The simplified activities
associated with the production of the text
book are given below. The author is required
to submit to the publisher a hard copy and a
computer file of the manuscript. Develop the
associated network for the project.
Example 2: Project Activities
Activity Predecessor(s) Duration (weeks)
A: Manuscript proofreading by editor None 3
B: Sample pages preparation None 2
C: Book cover design None 4
D: Artwork preparation None 3
E: Authors approval of edited manuscript A,B 2
and sample pages
F: Book formatting E 4
G: Authors review of formatted pages F 2
H: Authors review of artwork D 1
I: Production of printed plates G,H 2
J: Book production and binding C,I 4
Example 1: Network
7
5 5
3 3 3 7
5 5 7
3 3 3
2 K=0
3 4 6 7
3 E=2 F=2 7
3 3
2
G=2
9
9
A=3
B=2 8
2 5 7 9
8 H=1 9 9
1
0 2 3
0 6 11 15
0
D=2 I=2
0 11 15
J=4
1 C=4
8 9
11 11
7
4 11
0
Example 2: Network Calculation
Activity ES LS EF LF Slack (LS- Critical
ES or LF- Path
EF)
A 0 0 3 3 0 YES
B 0 1 2 3 1
C 0 7 4 11 7
D 0 7 2 8 6
E 3 3 5 5 0 YES
F 5 5 7 7 0 YES
G 7 7 9 9 0 YES
H 2 8 3 9 6
I 9 9 11 11 0 YES
J 11 11 15 15 0 YES
DUMMY K 0 0 0 0 0 YES
ADDITIONAL TOPIC:
BASIC TIME SCHEDULING
(CONSTRUCTING TIME SCHEDULE)
Time Scheduling
Constructing Time Schedule Table
1.The critical activities (shown by solid lines) must
be stacked one right after the another to ensure
that the project is completed within its maximum
duration. (In problem 2, its 15 days)
2. The non critical activities (shown by dashed lines)
have time spans that are larger than their
respective durations, thus allowing slack ( or
leeway) in scheduling them with in their
allotted time intervals.
Example 3: Network

Findings: The critical path is A, D and H. The maximum time is 25


Time Scheduling

Note: Consider time duration and activity predecessor(s).


THANK YOU!

You might also like