Professional Documents
Culture Documents
Handbook
ABB Group - 1 -
Sep 16, 2017
ABB Group - 2 -
Sep 16, 2017
Line protection
Line protection
Electrical faults in the power system
100%
ABB Group - 3 -
Sep 16, 2017
Line protection
Fault types
Transient faults
are common on transmission lines, approximately 80-85%
lightnings are the most common reason
can also be caused by birds, falling trees, swinging lines etc.
will disappear after a short dead interval
Persistent faults
can be caused by a broken conductor fallen down
can be a tree falling on a line
must be located and repaired before normal service
ABB Group - 4 -
Sep 16, 2017
Line protection
Fault types on double circuit lines
Simultaneous and Interline faults
L3 L1
On parallel line applications a problem
can occur with simultaneous faults. L1 L2
A full scheme relay is superior when the
L2 L3
protection is measuring two different fault
types at the same time.
Z<
~ L1- ~
N
ABB Group - 5 -
L2-
Sep 16, 2017
N
ABB Group - 6 -
Sep 16, 2017
Line protection
Line protection
MAIN REQUIREMENTS ON LINE
PROTECTION ARE:
SPEED
SENSITIVITY
SELECTIVITY
DEPENDABILITY
SECURITY
ABB Group - 7 -
Sep 16, 2017
ABB Group - 8 -
Sep 16, 2017
Line protection
Line protection
Measuring principles
Overcurrent protection
Differential protection
Phase comparison
Distance protection
Directional- wave protection
ABB Group - 9 -
Sep 16, 2017
Line protection
Overcurrent protection
Are normaly used in radial networks with system
voltage below 70 kV where relatively long
operating time is acceptable.
On transmission lines directional or undirectional
overcurrent relays are used as back-up
protections.
I>
CHARACTERISTICS OF
DEPENDENT TIME OVERCURRENT RELAYS
100.0
Operate Time [s]
1.0
Extremely Inverse Very Inverse
0.1
1 10 100
Current (multiple of setting)
ABB Group - 11 -
Sep 16, 2017
Line protection
Two or Three Phase Overcurrent Relays
Reverse
operation
0.6 x3I0D
Upol
3I0D Forward -3U0
operation
3I0 >
= the characteristic angle of zero
ABB Group - 14 -
sequence source
impedance
Sep 16, 2017
Line protection
Directional Residual Overcurrent Relays
DL1
DL1
Digital communication with
DL2
optical fibres or by DL2
multiplexed channels
DL3 DL3
ABB Group - 17 -
Sep 16, 2017
Line protection
Phase comparison
load Phase comparison relays
I I compare the angle
1 2 difference between the two
> >
currents at both ends of
the line.
I I The measured time for
1 2
zero crossing is
transmitted to the other
e end.
1
e Normally a start criteria is
2 I added to the phase angle
2
e e func requirement.
ABB Group - 18 -
I
1- 2 -tion 1
Sep 16, 2017
I
2
Line protection
The principle of distance protection
ZK=Uk/
Ik
Uk Uk=0
metallic fault
Zk B
A
Ik
Z<
ABB Group - 19 -
Sep 16, 2017
Line protection
Fault resistance
L3 L1
multi-phase faults
L1 L2
consist only of arc resistance
L2 L3
earth faults
consist of arc and tower
footing resistance
Warringtons
formula
L= length of arc in
28707 x L meters
Rarc = 1.4
I Footing resistance
ABB Group - 20 -
A
Line protection
The principle of distance protection
Power lines have impedances of size 0,3- 0,4 ohm/
km and normal angles of 80 - 85 degrees in a 50Hz
systems.
A B
ZL=R+jX
Z< Z<
VTprim CT sec
Sep 16, 2017
Line protection
The principle of distance protection
Reach setting of zones
R/ X Relation
GFC (General Fault Criterion)
GFC
ZL ZL
Zb
ABB Group - 22 -
Sep 16, 2017
Line protection
The principle of distance protection
t
t3
t2
t1
l
A B C
f f f
1 2 3
l
Sep 16, 2017
Line protection
Requirements on Distance relay Zones
Zone-1
Must not overreach
Zone-2
Must overreach
Must co-ordinate with next section
Provides back-up for the next busbar
Provides back-up for the first part of next line
Zone-3
Can provide back-up for next line
Can provide back-up for next busbar
In feed of fault current at the remote busbar affects the effective
reach of the overreaching zones
ABB Group - 24 -
Sep 16, 2017
Line protection
Measuring loop for three- phase faults
Zs RL XL
IL1
UL1 IL
UL2 2
IL3
UL3
location
Sep 16, 2017
Line protection
Measuring loop for two- phase faults
The distance protection relays are always set based on
the phase impedance to the fault
Zs RL XL
IL1
UL1-L2 IL2
location
Sep 16, 2017
Line protection
Measuring loop for earth faults
The distance protection relays are always set based on
the phase impedance to the fault
Zs RL XL
IL1
UL1
IN RN XN
RF
XF R
ABB Group - 30 -
Sep 16, 2017
Line protection
Distance protection on short lines
jX
Distance protection with mho
characteristic can not see
average fault resistance
Cross polarization has no
significant effect
RF
XF R
ABB Group - 31 -
Sep 16, 2017
Line protection
Distance protection on short lines
jX
Quadrilateral characteristic
improves sensitivity for higher RF/XF
ratio
It still has some limitations:
the value of set RF/XF ratio is
limited to 5
RF
XF R
ABB Group - 32 -
Sep 16, 2017
Line protection
Distance protection on short lines
jX Overreaching permissive
schemes increase the
sensitivity
Weak infeed logic for very
high fault resistance
Independent underreaching
zone 1 gives additional
advantage
RF
XF R
ABB Group - 33 -
Sep 16, 2017
Line protection
jX Distance protection on long lines
Load impedance limits the reach
in resistive direction
High value of RF/XF ratio is
generally not necessary
Circular (mho) characteristic
Has no strictly defined reach
in resistive direction
Needs limitations in resistive
direction (blinder)
R
ABB Group - 34 -
Sep 16, 2017
Line protection
Communication equipment
Power line carrier (PLC) equipment is based on a
capacitive connection of signals with frequency in
range 50- 500 kHz on the power line.
Radio link is a good and reliable communication
equiment, but is rarely used due to the high cost.
Optical fibres have the advantage to be insensitive
to noise and can transmit a huge amount of
information.
ABB Group - 35 -
Sep 16, 2017
Line protection
Permissive communication schemes
Communication signal carrier send (CS) is sent to remote end when
the fault is detected in forward direction. Tripping is achieved when
the commmunication signal carrier receive (CR) is received and the
local relay has detected a forward fault.
In a permissive underreaching scheme the communication signal is
sent from a zone that underreaches the remote end.
In a permissive overreaching scheme the communication signal is
sent from a zone that overreaches the remote end.
A B
Z< Z<
overreach
Sep 16, 2017
A B
Z< Z<
A B If
ZL If
1 2
If If=If1+If2+If
Um ZF
3 3
Z<
ABB Group - 41 -
I1 I Load
I2
U1 U2
UF RF
UF = RF ( I1 + I2 )
RF ( I1 + I2 )
RF1=
I1
ABB Group - 42 -
Sep 16, 2017
Line protection
Measuring error at high resistive earth fault on
a line with double end infeed
X
Rf Load import
ZL
Rf Load export
R
ABB Group - 43 -
Sep 16, 2017
Line protection
Zero- sequence mutual coupling on parallel
lines
ZL
~ ZOM ~
ZL
~ ~
ABB Group - 44 -
overreaching underreaching
Line protection
Parallel line out of service and earthed at
both ends
= - 0.23 ZL
ABB Group - 45 -
Sep 16, 2017
Line protection
Parallel line in Service
D
KOM
ZL
Z = 1 + KO
= 0.38 ZL
ABB Group - 46 -
Sep 16, 2017
Line protection
Distance relay settings for parallel lines
Power swing
locus
t = 40 ms
ABB Group - 49 -
Sep 16, 2017
Line protection
Stub protection function It is not possible for the
distance protection relay to
Bus A measure impedance when the
+ >Z
line disconnector is open. Not
to risk incorrect operation the
distance protection must be
blocked and a Stub protection
is released.
The Stub protection is a simple
current relay.
25ms
line disc
open & trip
CR CS
Z< (echo) Z<
t3 CS CR
t2
t1
CS = ZM2 l
CS (echo)=CR x low voltage x no start forward or
ABB Group - 53 -
reverse
Sep 16, 2017
100% F1
gape flashed
B
Consideration for line
A
distance protections
R
Correct direction
discrim-ination at voltage
70% gape not flashed reversal (negative fault
reactance)
variation in resulted line
ABB Group - 54 -
impedance
Sep 16, 2017
Line protection
Directional wave protection
The basic principle of directional wave protection is to observe the
polarities of the instantaneous change in voltage and current. Here by
one can determine the direction of a fault with respect to the location
of the measurement.
Tripping is achieved when both protections detects a fault in forward
direction.
I U Trip
A B + + 0
~ ~ - - 0
F
- + 1
+ - 1
ABB Group - 55 -
Sep 16, 2017
CBIP manual on
Protection of Line Protection
Generators, generator
transformers and 220kV
and 400 kV networks
ABB Group - 56 -
Sep 16, 2017
Line protection
1.1
1.1 400
400kV
kVLines
Lines
If Main-I and Main-II are both distance protection schemes, then they
should be preferably of different types. They need not necessarily of
different make. Both should be suitable for single and three phase tripping
ABB Group - 57 -
Sep 16, 2017
Line protection
In addition to above, following shall also be provided
ii) Auto reclose relay suitable for 1 ph / 3 ph (with deadline charging and
synchro check facility) reclosure.
Main protection should be suitable for single and three phase tripping.
(i) If found necessary, at certain locations, out of step tripping relays shall be
provided for islanding the system during disturbances.
(ii) For short line application distance relays should have shaped characteristics
for ground faults and be used in permissive over reach mode with weak end
infeed logic. Further, if it is a double circuit line, current reversal should
also be available.
(iii) O/V relay for 400 kV lines shall be connected to trip concerned line breaker,
start LBB, block auto reclosure and send direct trip command.
ABB Group - 60 -
Sep 16, 2017
Line protection
(iv) The directional earth fault relay recommended along with the distance relay
should be seen as a supplement to it and not as a back up. It helps to detect
very high resistance fault which distance relay cannot.
(v) HVDC Systems connected to AC networks with low short circuit levels can
influence AC line protections in its vicinity. This aspect needs to be looked
into on case to case basis.
ABB Group - 61 -
Sep 16, 2017
Line protection
3.0
3.0 SETTING
SETTINGCRITERIA
CRITERIA
3.1
3.1 Reach
Reachsettings
settingsofofdistance
distanceprotection
protection
3.3.1
Low set voltage may be set at 110% with a typical time delay of 5
seconds.
3.3.2
High set stage may be set at 150% with a time delay of 100 m second.
ABB Group - 65 -
Sep 16, 2017
Line protection
3.4
3.4 Power
PowerSwing
SwingBlocking
BlockingFunction
FunctionAssociated
Associatedwith
withDistance
DistanceRelays
Relays
Decisions pertaining to allowing which Zone to trip and which to block
should be taken based on system studies on case to case basis.
ABB Group - 66 -
Sep 16, 2017
CBIP manual on Reliable
fault Clearance and Back- Lines and Cables
UP Protection for EHV and
UHV Transmission
Network
ABB Group - 67 -
Sep 16, 2017
Line protection
Lines and Cables
Transmission line protection is the most
complex of all the protections in terms of
the challenges it poses. In the above
paragraphs many of these aspects
connected with line and cable protection
and some recommendations have been
brought out and these should be
considered. Few of these are brought out
below.
ABB Group - 68 -
Sep 16, 2017
Line protection
Lines and Cables
Section 5.5 gives details of main attributes
and limitations of various main protections.
When applying any of the main protections
these should be fully examined and
understood.
The decision to provide Main-2 protection
and effective back-up protection should not
be merely based on voltage level but on
how important the circuit is .The costs of
reduced supply capacity or total loss of
supply must be considered in relation to the
ABB Group - 69 -
system
Line protection
Lines and Cables
Directional ground protection should be applied
as main protection for high resistance faults
wherever it is felt that Main protections
applied do not cover the high resistance
faults adequately.
When unit protections are used, Phase-
segregated unit protection based on current
measurement is the best option, when it is
economically and technically feasible
Cables do not withstand fault currents for
long periods of time. Unit protection should
be used as main protection and distance
ABB Group - 70 -
local back-up
Sep 16, 2017
Line protection
Lines and Cables
In case a line differential/phase
comparison/directional comparison
protection is used they do not have inherent
features to provide back-up protection.
Therefore it is recommended that they
should preferably be provided with
additional elements that can provide back-
up protection. Usually these features are
achieved by supplementing the unit
protections with additional impedance
elements.
ABB Group - 78 -
Sep 16, 2017
Line protection
Lines and Cables
It is felt that for transmission overhead line
a non segregated type phase comparison
protection may not provide the correct
practical solution to protection problem
due to several technical reasons. Though
segregated type phase comparison
protection overcomes these limitations,
the overall cost may be too high
ABB Group - 79 -
Sep 16, 2017
CBIP manual on Reliable
fault Clearance and Back- Communication
UP Protection for EHV and Systems
UHV Transmission
Network
ABB Group - 80 -
Sep 16, 2017
Line protection
Physical Links
current Present
Sep 16, 2017
multi-terminal circuits.
Sep 16, 2017
Line protection
Zone-2 in multi-terminal lines
ABB Group - 96 -
Sep 16, 2017
Line protection
Zone-2
Load encroachment
One problem with mho impedance elements is
that the fault resistance coverage varies with
the forward reach setting. When applying Zone-
1 elements to short lines, fault resistance
coverage may be insufficient. It can also be
disadvantage for Zone2 elements to be set
with unusually high forward reach setting in
relation to the minimum load impedance. It
may be possible for the minimum load
impedance to encroach upon the Zone-2
operating region.
ABB Group - 97 -
Sep 16, 2017
Line protection
Zone-2 load encroachment
ABB Group - 98 -
Sep 16, 2017
Line protection
Zone-3 Remote back-up
General
Usually set to provide remote back-up
protection for adjacent sections of a
transmission circuit.
May have independently adjustable forward
and reverse reach setting
Usually forward reach provides remote back-
up protection.
With duplicate main protection, there may be
a case for not applying Zone-3 remote back-up
protection at all.
In case of long 400kV lines it may be desirable
either to reduce the reach or to block 3 rd zone
ABB Group - 99 -
Sep 16, 2017
Line protection
Zone-3 remote back-up
Time setting
Must be set to co-ordinate with clearance of faults by
adjacent circuit-local back-up protection. Zone-2 distance
protection or time delayed over current protection
The following formula would be the basis for determining
the minimum acceptable Zone-3 time setting:
t z 3 t MA tCB t z 3reset t s
Where:
tZ3 = Required Zone-3 time delay
tMA = Operating time of slowest adjacent circuit local
back-up protection
tCB = Associated adjacent circuit breaker clearance
time
tZ3reset = Resetting time of Zone-3 impedance element
with load current present
ABB Group - 101 -
Sep 16, 2017
Line protection
Zone-3 remote back-up
Zone-3 load impedance encroachment
Encroachment due to the minimum load impedance under
expected modes of system operation and the minimum
impedance that might be sustained for seconds or minutes
during abnormal or emergency system situations.
Use of blinders in case of Mho type of elements or by use
of polygon type impedance elements.
In case of long 400kV transmission lines it may be
desirable to limit the reach of Zone-3 for reasons of
security. In such cases, if the adjacent station has bus bar
protection and breaker failure protection, Zone-3 can be
dispensed with.
Line protection
Effect of in feeds on Zone-3
ABB Group - 105 -
Sep 16, 2017
Line protection
Zone-3 load encroachment
ABB Group - 106 -
Sep 16, 2017
Line protection
Zone-3 coordination
ABB Group - 107 -
Sep 16, 2017
Line protection
Zone- 4 substation local back-up
An additional zone of reverse-looking
protection (e.g. Zone-4) to offer substation-
local back-up protection.
The Zone-4 reverse reach must adequately
cover expected levels of apparent bus bar
fault resistance, when allowing for multiple
in feeds from other circuits.
Sometimes when separate reverse looking
element is not available the above is
achieved by offset reach of Zone-3 of
ABB Group - 108 -
distance relay.
Sep 16, 2017
ABB Group - 109 -
Sep 16, 2017
Line protection