You are on page 1of 25

Industrial Training

Tnb Distribution
9TH March 2015 31 may 2015

MOHAMAD SYAFIQ BIN ABDULLAH


EE089872
MAY 2015
CONTENT

Self introduction

Industrial training objectives

Company profile

Training activity
SELF INTRODUCTION

Name : Mohamad Syafiq Bin Abdullah


Date of birth : 17 November 1993
ID number : EE089872
Age : 21
Hometown : Kepala Batas, Pulau Pinang
Institution : Universiti Tenaga Nasional (UNITEN)
Course : Bachelor of Electrical and Electronics Engineering (Hons.)
INDUSTRIAL TRAINING OBJECTIVE

To provide the students to the world of work so that they can relate theoretical
knowledge with application in industry
To build and increase creative and positive thinking when overcoming engineering
problems.
To improve my soft skills such as communication, management and team-work.
Enhancing the potential of the student to with the situation that they encounter.
Company profile

The TNB a public listed company with responsibilities:


To generate, transmit, distribute and sell energy to customer throughout Peninsular Malaysia.
To plan, install, operate and maintain electricity installation for the generation, transmission and
distribution of electricity.

To achieve the above objectives, the company owns and operates power plants and the National Grid and
installed for this purpose, customer service center, call management center, substations and administrative
offices throughout Peninsular Malaysia. TNB`s core activities are in generation, transmission and
distribution of electricity which are being handled by its subsidiaries:

TNB Generation Sdn Bhd


TNB Transmission Network Sdn Bhd
TNB Distribution Sdn Bhd

TNB Vision: To be among the leading corporation in energy and related business globally.

TNB Mission: We are committed to excellence in our product and service.


INDUSTRIAL TRAINING SCHEDULE
9 MARCH 2015 UNTIL 31 MAY 2015

DATE DEPARTMENT AMOUNT MAIN ACTIVITY REPORT


OF DAY

PROJECT PLANNING
09/03/2015
- PLANNING 28 CABLE EN NORAZMI BIN ARIFFIN
05/04/2015 &
CONSTRUCTION SUBSTATION

OVER HEAD

06/04/2015 METER
- METERING 28 EN MOHD FADZLI BIN
03/05/2015 SERVICE MOHD TAHIR

04/05/2015 SUBSTATION
-
28/05/2015 OPERATION 28 OVER HEAD EN. AZLI HILMI BIN
& FAUDZI@MD RAWI
MAINTENANCE CABLE

FAULT FINDER
consturction department

In construction department, they responsible to construct substation and overhead pole.


Usually, contractor will do the initial work like dig hole for joining, places the switchgear
or transformer, place the pole and the other work.

Apart from that, TNB also responsible to shut down the substation that involved in the
construction before the contractor start doing their job to avoid accident from happening.

The important work in construction job is joining cable to make sure that the new
substation will get the supply to operate . Furthermore joining cable is done when there is
breakdown which happened because the cable is damaged.
Type of cable

Paper Insulated Lead Cable (PILC) Cross Linked Polyethylene (XLPE)

PILC Amp XLPE Amp

25 90 150 320
70 160 240 400
120 230 500 550
185 290
300 380 Cable
Joining cable

There two types of joining cable that are:


Straight through joint
Termination joint

Termination joint straight through joint


Breakdown of cable
Low Voltage Overhead Lines

Presently all new lines are constructed using aluminum.


Copper conductors are used only for repair of copper lines.

Advantages of Aluminum :
cheaper than copper
lighter and easier to handle
less scraper value, not prone to theft

Disadvantages of Aluminum :
softer than copper and required careful handling
oxidizes easily making connections more difficult
Conductor rating

ABC Amp BARE Amp


1X16+25 80 3/132 120
3X16+25 80 7/122 170
3X95+70 190 7/122 170
3X185+120 300
Poles For LV Overhead Line

Four types of poles are used in the TNB : The standard lengths are:
Wood Poles 10 meter - for HT cable (HV)
Pre-stressed Spun Concrete poles 9 meter - for overhead mains (LV)
Reinforced Concrete Poles

The functions of poles are:


To support conductors and accessories such as fuses
and cable boxes
The safety clearance from the ground, building are
maintained
High Voltage Cable

The 11kV supply that feeds into switchgear comes in the XLPE cable (HV cable).
In one cable, have three cores (R, Y, B) which is connected to the three terminals
of incoming feeder of the switchgear.
From the switchgear, the supply goes to the HV side of the transformer through
XLPE cable

Switchgear Transformer Feeder Pillar


Planning department

This department is responsible to estimation the project include in designing,


planning in all new project requested by users and modified system available
depends on situation.

This department also responsible to calculate maximum demand, cable size,


calculate load, and determine suitable transformer size and switchgear for
consumer
Estimating the project

Estimation of substation project involves working out the cost of the following
Land
Salaries
Materials
Contract
Transport
Overhead
SITE VISIT

Site visits are essential before planning starts. The following can be obtained from site visits.
a) Sources of supply
b) Types of loads
c) Site information on:
Trees
Ground conditions and terrain
Other services on site such as telephone lines and water mains.
Drains, stream, ponds etc
MAKING A Site visit
Metering unit

Type Of Metering Used To Consumer :


a) Ordinary power consumer meter (OPC meter) Metering

b) Large Power consumer meter (LPC meter)

Ordinary Power Consumer (OPC) Large Power Consumer (LPC)

1. Electromechanical single 1. Electromechanical three


phase phase (LV)
2. Electronic single phase 2. Electronic three phase (LV)
3. Electromechanical three 3. Electromechanical three
phase phase (HT)
4. Electronic three phase 4. Electronic three phase (HT)
Type of metering

There are three types of metering


1. Single phases metering (OPC meter).
The current value uses in fuse about 10-50 A.
Use two wire connected from supply to meter board consumer
Having one cut out and one neutral link
2. Three phase metering (OPC meter)
The current value uses in fuse about 10-60 A.
Used four wire connected from supply to meter board consumer
Having one neutral link and three cut out
3. Large power consumer meter (LPC meter).
Use digital electronic meter
Use current transformer
Component of meter

a) The devices at meter board are

Cut out Neutral link Meter


Thank you

You might also like