PROBLEM
IDENTIFICATION
EARTHS WATER
75% Water
25%
30%
Remaining
70% Fresh
Locked in Water
Polar Ice
Cap
ONLY 3% OF OUR EARTHS WATER IS FRESH70% IS LOCKED IN POLAR ICE CAPS; 30% IS IN
LAKES, RIVERS AND UNDERGROUND, OF WHICH 75% IS POLLUTED.
shortage. In a study conducted by water.Org they found that "42% of the population has
access to a clean water supply" and only "11% of that number has access to adequate
services". In rural areas of the country, these figures drop even lower, resulting in health
problems in the villagers. In ethiopia most of the areas have the relative humidity is quite high
(around 70-80%). So, the air in those places can be used to meet the water needs of people by
AWG that is able to produce 10-20 litres of water daily in various climate
conditions, and can deliver water in conditions below 30% relative humidity
This reduce humidity levels in climates where high humidity levels create uncomfortable conditions in homes
or buildings.
This water extractor purifies water for drinking. These units produce distilled water that is perfectly safe to
drink.
EXPERIMENTAL SITE
The proposed project meant for debre tabor university and other
ASSESMENT
DESIGN
TASK
DEVELOPMENT
TESTING
OPIMIZATION
COST ESTIMATION
S. Items Unit Quantit Unit Total
No. y price price
(Birr) (Birr)
I Stationery
1 Laser jet printer cartridge No. 1 900 900
2 Re-writable CD Pack 15 30 450
3 USB Flash Drive(32 GB) No. 1 720 720
4 Paper (A4 size) Packet 5 100 500
5 Fixer Pencil Packet 4 150 600
6 Fixer lid Packet 2 20 40
7 Note book (Big) No. 4 50 200
8 Marker Packet 1 50 50
9 Pen (Lexi 5) Packet 2 100 200
Sub Total 3660
S. No. Task Items Unit/members Quantity/no of Unit price Total price
days (Birr) (Birr)
II On project
1 Assessment Transportation 3 8 100 2400
Accommodation 3 5 300 4500
2 Design ---------------- ------ ------ ---- ------
3 Development 1/8 Compressor 1 1 2000
Condenser 1 1 2000
Heating coil(400 watts) 1 1 2500