Professional Documents
Culture Documents
STRUCTURES
Under The Guidance of:
Prof. K.JAYARAM
Prof. & Head
Department of Civil Engineering
BY,
MANJUNATH.S
IST SEM MTECH(STRUCTURES)
BANGALORE INSTITUTE OF TECHNOLOGY.
BANGALORE.
CONTENTS
Introduction
Advantages
Eugene freyssinet(1879-1962)
Eugene Freyssinet (1879-1962) devoted much of his life to
the research development and construction of prestressed
concrete structures and is rightly named the father of
prestressed concrete. It is through his dedicated research
that many of the techniques and practices used today to
build spectacular and aesthetic structures are possible.
The Freyssinet achieved the first success with prestressed
concrete in marine construction, having secured the tender
beginning to correct the threatened foundations of the LeHarve
marine terminal using prestress techniques.
La grande arch in Paris was
constructed using massive
70m span post tensioned I
beams to carry the upper
decks of three floors.
Precast pretensioned
hollow formed slabs
Prestressed concrete is used today for large
building works in many civil engineering fields
such as ..
Roads
Buildings
Bridges
Today Water
Energy
Public facilities etc..
INTRODUCTION
contd
PRE-TENSIONING METHOD .
POST-TENSIONING METHOD.
PRE-TENSIONING
Pre tensioning is one method of applying prestress,thus
Tendons either pass through a single mould or a line of moulds for multiple
members arranged end to end and can be attached at one end to fixed
anchorage.
The tendons are then tensioned from the fixed anchorage between an
external independent anchorage to give the required tensile force in the
tendon.
The tendons are then held in place while the concrete is poured.
When the concrete has hardened sufficiently the ends of the tendons are
slowly released from the anchorages.The tendons are restrained from gaining
their original length by the development of bond stresses between the
concrete and the tendon, and it is these bond stresses that transfer the
compressive stress to the concrete.
The tendons are then finally trimmed off as shown below.
POST-TENSIONING
Post-Tensioning is another method of applying prestress to a concrete member, thus-
The tendon is placed in the correct position in the formwork with the dead-
end anchorage and live end anchorage, through which the tendon passes.
The concrete is then poured and left to harden.
When the concrete has gained sufficient strength a jack is attached to the live
end anchorage and the tendon stressed to the required force. The operation is
to be carefully done as any error could impair the structural integrity of the
member.
The tension force in the tendon is transferred to the concrete as a
compressive force by the reactions at the anchorages.The jack is then
removed.
Dead-end
anchorage
BONDED
UNBONDED
The photograph
shows the tendon
layout for a post-
tensioned flat slab.
The tendons are placed in position before the concrete is poured.When the
concrete has gained sufficient strength, the tendons are jacked to a
predetermined prestress force.
When concrete has gained sufficient strength the tendon is stressed and then the
sleeve is filled with grout under pressure through tubes placed at intervals along the
sleeve.
The grout bonds the tendons to the sleeve thus enabling the transfer of stress from
the tendons to the concrete.
How Prestressed concrete is made
One anchorage simply holds the end of the tendon in position , while the other is
used with the jack to stress the tendon. Each anchorage is attached to the end of the
tendon before the concrete is poured .The type of anchorage used depends on the
number of tendons and whether they are strands or wires.
A prestressing jack is attached
to the outside plate of the
anchorage through which the
ends of the tendons project.
Once the jack has been
connected to the tendons,
stressing can begin. The
predetermined stressing force
can be applied to each tendon
individually. The force is
applied according to the design
engineers specifications.
Special trucks bring
the concrete to the
casting bed where
the pouring begins.
Once the
pouring is
complete, a
tarp is placed
over the form
and applied to
cure the
cement
The prestressing strands
are cut and the concrete
form is removed from the
casting bed.
The ends are
cleaned and the
prestressing
strands are sealed
with a protective
coating
The end-product
is shipped to a
building site.
Bond Stresses
The prestress force in a bonded tendon is transferred to the
concrete by bond stresses.
There are two stages at which bond stresses are considered in the
design of prestressed concrete elements.
Stiffer
Tensile Strength
Stiffness
Shear
Cracking & deflection
Serviceability
Economy
Safety
Prestressed concrete in construction
industry
It is well established fact that the basic economy of
prestressed concrete lies in its high strength to weight
and strength to cost ratios , its resistance to fire &
corrosion, & its versatility and adaptability.
How to deal with the low tensile strength of concrete by prestressing the
member.
The mechanics of the prestressing system using a row of books as example.
How the prestressing force is applied to a member at site.
A brief history of the development of prestressing from its inventor Eugene
Freyssinet up to the modern day.
The methods of prestressing-
Pre tensioned prestressing,
Post tensioned Prestressing,
Bonded and unbonded tendons,
Anchorages,
Bond stresses.
THANK YOU