Applying Systems Engineering

SYSE 511

Module 9: Systems Engineering


Management Plan
AA
Objectives
 Understand the concept, function, and
contents of a SEMP
 Learn how to develop a SEMP
 Review different suggested and tried
SEMPS

2
Applying SE SYSE 511
Where are We in the
AA
SE Process?

Systems
Engineering
Planning
Mission Analysis / Baseline
Mission Analysis
Requirements Analysis Management

Objectives: System Verification Functional Analysis

 Plan the engineering effort on a


project System
Integration
Alternatives Analysis /
System Synthesis
Tradeoff
Studies

 Integrate with project


management activities

3
Applying SE SYSE 511
AA
Key Terminology
 SEMP
 Integrated Product Teams
 Cross Product Teams
 Illities
 System Products
 System Processes

4
Applying SE SYSE 511
AA
Origin of this material

• This lecture material was taken from the


SEMP Lecture given in SYSE 510
• Still good.

5
Applying SE SYSE 511
AA
Recent Development
 http://dod5000.dau.mil/
 DAU = Defense Acquisition System
 Since SE is all about controlling acquisition,
this is effectively the evolution of 499B and
related Mil-STDs
 View Slides from http://dod5000.dau.mil/
there are 46 slides so we will rush through

6
Applying SE SYSE 511
Program Management Plan
AA
(also Project Management
Plan)
 Function - Plan the management of a
program
 Scope - Cost, Schedule, Scope, and
Organization
 Contents - All over the place - different
schools of thought

7
Applying SE SYSE 511
AA
PMP Contents - Ideal
 Organization
 Top-level Cost, Scope, and Schedule
 Source of funding, means of funds controls
 Responsibility Assignment Matrix
 Reporting and Communication
 Contracts, Conflict of Interest, QA, Audit

8
Applying SE SYSE 511
PMP Checklist
AA from http://www.projectconnections.com/

1. Business case: the product or service description; the project


charter
2. Project justification, deliverables and objectives i.e., scope
3. Name of the project manager
4. Organizational and management strategy - what is the life-cycle,
what major activities, reviews, tests, life-cycle phases, etc.
5. Roster of required team members and their functional expertise
6. Work Breakdown Structure.
7. Cost estimates, start dates, and responsibility assignments of the
work breakdown.
8. Performance level baselines for schedule and cost.
9. Major milestone descriptions and dates
10. Key risks, constraints, assumptions and planned responses
11. Plans for managing product requirements, schedule management,
and project issue management
12. Open issues and pending decisions; a punch list
9
Applying SE SYSE 511
AA
Kerzner’s PMP
 Kerzner is the main Project Management
Text
 Objective
 Strategy
 Schedule
 Budget
 Organization
 Policy (guides for decision making and individual
actions)
 Procedures (for carrying out Policy)
 Standards
 WBS.
10
Applying SE SYSE 511
Kerzner Alternative
AA

 A Program Mgt Plan could consist of Scope and


Organizational Description plus individual plans for:
 Budgeting
 Configuration management
 Facilities
 Logistics Support
 Management
 Manufacturing
 Procurement
 Quality Assurance
 R&D
 Scheduling
 Tooling
 Training
 Transportation

11
Applying SE SYSE 511
So what can a SEMP
AA
provide?
 In project management courses and
guidelines, one rarely finds requirements
management, functional analysis, synthesis,
interface control, integration, cyclic
processes, model-based design, integrated
modeling and design, integrated issues-
risk-decision, systems analysis, document
hierarchy, and measures of effectiveness.
 Also, note above that Human factors, safety,
reliability, maintainability, operability are not
mentioned.

12
Applying SE SYSE 511
System Engineering
AA
Management Plan
 Function - Plan the engineering of a product
 Scope - Cost, Schedule, Scope, and
Organization of engineering and product
 Contents - different schools of thought

13
Applying SE SYSE 511
AA
SEMP Contents
 INCOSE Handbook
 DSMC
 IEEE
 EIA
 Textbook
 Martin Marietta
 BWIP
 MWFA
 P-9
14
Applying SE SYSE 511
SEMP, from INCOSE Handbook
“A comprehensive document that describes how the fully integrated
AA engineering effort will be managed and conducted. “

 Cover
 Title Page
 Table of Contents
 Scope
 Applicable Documents
 Systems Engineering Process
 Transitioning Critical Technologies
 Integration of the Systems Engineering Effort
 Additional Systems Engineering Activities
 Notes
 Appendices
15
Applying SE SYSE 511
AA
INCOSE Details
 Processes
 Systems Engineering Process Planning
 Requirements Analysis
 Functional Analysis/Allocation
 Synthesis
 Systems Analysis and Control

16
Applying SE SYSE 511
AA
INCOSE SEMP
 Process inputs
 Decision database (deliverables and results)
 Technical objectives
 Contract work breakdown structure (WBS)
 Training
 Standards and procedures
 Resource allocation
 Constraints
 Work authorization
 Verification planning
17
Applying SE SYSE 511
AA
INCOSE SEMP

 The SEMP should list what technical reviews will be


conducted, consider
 TIM Technical Interchange Meeting
 SRR System Requirements Review
 SDR System Design Review
 SFR System Functional Review
 IPDR Internal Preliminary Design Review
 PDR Preliminary Design Review
 CDR Critical Design Review
 SWDR Software Design Reviews
 QPRQuarterly Progress Review
 FCA Functional Configuration Audit
 PCA Physical Configuration Audit

18
Applying SE SYSE 511
AA
DSMC Ch. 16

 An introduction that states the purpose of the engineering


effort and a description of the system being developed,
 A technical strategy description that ties the engineering
effort to the higher-level management planning,
 A description of how the systems engineering process will
be tailored and structured to complete the objectives stated
in the strategy,
 An organization plan that describes the organizational
structure that will achieve the engineering objectives,
 A resource plan that identifies the estimated funding and
schedule necessary to achieve the strategy.
 Plus Details for each of these.

19
Applying SE SYSE 511
AA
IEEE
 Functional Orientation
 Identify the SE Functions and define how
they will be done

20
Applying SE SYSE 511
AA
EIA
 Similar to IEEE

21
Applying SE SYSE 511
AA
Textbook
 Strangely Silent
 Chapter 7 and 8 and 13 address it but never
suggest that a SEMP exists.

22
Applying SE SYSE 511
AA
From Andrew Sage

See following page

23
Applying SE SYSE 511
From Andrew Sage – SEMP Outline
5.5. Configuration Management Plan
Title Page
Preface 55.1. CM Objectives and Overview
AA
Table of Contents
List of Figures 5.52. CM Organization, Charter, Members, Duties
List of Tables
5.53. CM Methods
1. Executive summary
2. Introduction 5.5.3.1. Baselines
2.1. Program Objectives
2.2. Program Description 5.5.3.2. Configuration Identification
2.3. Program Scope
5.5.3.3. Configuration Control
2.4. Program Overview
2.5. Program Organization and Responsibilities 5.5.3.4. Configuration Auditing
2.6. Program Deliverables
2.7. The Systems Engineering Management Plan 5.5.3.5. Configuration Status Accounting
Components
2.8. Program Milestones
5.5.4. CM Implementation Plan
3. Program Management Approach 5.5.4.1. Procedures
3.1. Systems Management Assumptions, Needs, Constraints
3.2. Systems Management Objectives 5.5.4.2. Personnel
3.3. Program Risk Management
3.4. Program Staffing
5.5.4.3. Budget
3.5. Program Monitoring and Control 5.4.4.4. Implementation milestones
3.6. Program Integration Approach
4. Program Technology 5.6. System Security Plan
4.1. Technical Description of System Development Projects
6. Budget and Resource Management Plan
4.2. Project Methods, Tools, and Techniques
4.3. Project Procedures and Support Functions 6.1. Work Breakdown Structure
5. Program Quality Assurance
5.1. Quality Assurance Plan 6.2. Cost Breakdown Structure
5.2. Maintenance Plan 6.3. Resource Requirements
5.3. Documentation Plan
5.4. Operational Deployment Plan
6.4. Budget and Resource Allocation
6.5. Program Performance Schedule
Additional Contents 24
Applying SE SYSE 511 Reference Materials
Chapter 6, B.S. Blanchard, Systems
AA Engineering Management

1. Introduction 14. Specifications and Standards


Listing (6.2.4)
2. Scope (6.2.1)
15. Technical Performance Management
3. Roles and Responsibilities (6.2.5)
4. Systems Engineering Process 16. Schedule Management (6.2.6)
(6.2.2 is task oriented, or discuss
as below) 17. Reporting (6.2.9)
5. Mission Definition and Analysis 18. Specialty Plans and Program
Interfaces (6.3 and 6.4)
6. Functional Analysis and
Requirements Allocation 19. Technical Management Tools and
Methods (6.5)
7. Alternative Analysis and
Selection 20. Risk Management (6.6)
8. Validation and Verification 21. Performance Measurement Factors
(6.7)
9. Technical Management
22. Specialty Disciplines Integration
10. Work Integration and Control (3.3)
(6.23 – 6.29)
23. Additional Systems Engineering
11. The Work Breakdown Structure Activities (catch all)
(6.2.3)
24. Acronyms/Glossary
12. Cost Management (6.2.7)
25. References
13. Design Management (6.2.8)
26. Appendices
25
Applying SE SYSE 511
AA
Martin Marietta
 Wiring Diagram
 Emphasis on Flow of Information
 Organizational Interfaces

26
Applying SE SYSE 511
BWIP
AA
High Level Waste Repository Project circa 1985

 Issues Driven Program


 Issues – How to get a License
 Demonstrate issue resolution with computer model
 Identify parameters required to run models
 Collect Data
 Verify and validate models
 Resolve cost estimate with detailed conceptual design. Test
and verify crucial components of design with Prototype
repository
 Emphasis on Document Hierarchy
 Also included Technical Scope and SE
Processes.
27
Applying SE SYSE 511
AA
MWFA
 Identify SE Functions: Requirements,
Functions, Synthesis, Analysis, Integration
and Test
 Define Program specific documents to
accomplish those functions
 MWFA was at the development phase, but
the problem was to tie problems to
requirements to development programs,
and to define the program product.

28
Applying SE SYSE 511
AA
P9
 IPT oriented
 Plus a bit of Text Book
 Plus plus some IEEE
 Primary thrust was to establish IPT.

29
Applying SE SYSE 511
AA
SEMP Errors
 One size fits all – Just write a SEMP and put
it on the shelf – The Rick Harwell/INEEL
SEMP
 Generic, not Project specific – The 1992
ER/Bechtel SEMP
 We need one of those too – The old DOE-
Order 4700 Guidelines – Told how to
engineer, how to plan, specified a Risk Mgt
Plan, IPT, Review cycle and process, WBS,
and a SEMP; or the old EG&G approach
where the SEMP was Chapter 13 of the PMP.
30
Applying SE SYSE 511
AA
Class work shop
 Select a general approach for MRS
 Develop an outline for MRS SEMP

31