Professional Documents
Culture Documents
Corporate Finance
F305
Capital Budgeting
Professor:
Burcu Esmer
Firm Objective
Maximize Value
2
Capital Budgeting
Decision
Invest in projects that add
value to the firm
3
Capital Budgeting
• FCF is a general concept that can be applied to different
scopes of valuations
• First application: Making capital investment decisions
• Decision as to which real assets should the firm acquire?
• Firms have a finite capacity to purchase productive assets
• Is an investment issue, different from how a project is
financed
• What is the implication?
• Major project evaluation methods
• NPV, IRR, and Payback
4
5
To Start: What is an investment/project?
6
Typical Project
Initial cost
Cfi‘s : cash flows
or “outlay”
net of additional costs.
Terminal CF
C0 CF1 CF2 CF3 + CFN
r=?
0 1 2 3 N
B C
Terminal CF
+
C0 CF1 CF2 CF3
CF4
A r=?
0 1 2 3 N
8
Example I
As CFO of Amtrak you are deciding whether to build an
airline division. You estimate the new airline will cost
$6.92 billion to start and produce free cash flow to the
firm of $1.2 billion every year for 25 years. At the end of
the project’s life the terminal value will be 0. You
calculated the appropriate discount rate for the airline is
10.3%. Should you build the airline?
0 1 2 3 25
r = 10.3% 9
Solution to Example I
Do the benefits outweigh the costs? Bring all relevant cash flows to
the present to make cash flows time consistent. Sum the PV of all
cash flow. If costs outweigh the benefits then NPV<0 and if benefits
outweigh costs then NPV>0.
r = 10.3%
0 1 2 3 25
10
NPV Rule
Using appropriate discount rate bring all cash flows to the
present and sum up. If costs outweigh the benefit then
NPV<0. If benefits outweigh the costs NPV>0
N N
CFt CFt
NPV t or t Cost 0
t 0 (1 r ) t 1 (1 r )
If discount rate is less than the IRR then project “hurdles” discount
rate, otherwise we should reject the project.
Example II:
IRR = ?
0 1 2 3 25
12
Solution to Example II
-6.92 1.2 1.2 1.2 1.2+0
IRR = ?
0 1 2 3 25
13
IRR Rule
Find the discount rate that makes a
project’s NPV = 0. If that rate hurdles the
project’s WACC then accept, else reject
the project.
N N
CFt CFt
0 t or t Cost 0
t 0 (1 IRR ) t 1 (1 IRR )
14
Estimating Project Cash Flows
15
Include all Indirect Effects
Side Effects
• A project can have positive or negative side effects
• An important negative side effect is erosion
• Erosion is the cash flow transferred to a new project from customers and
sales of other products of the firm
• It should be treated as a cost to the new project
• e.g. a hybrid sedan cannibalizing sales of existing sedans
18
Opportunity Costs
If the new project uses existing assets, the costs of these assets
should be included even if no money changes hands
By taking the new project, the firm forgoes opportunities for
using the assets
19
Opportunity Costs
• Examples
• If you have a job offer from JP Morgan, and the other
offers you have are from Bank of America and from
Bloomington Credit Union. What is your opportunity cost
of accepting JP Morgan’s offer?
20
Investments in Working Capital
Net Working Capital (simplified version)
21
Financing costs
22
Additional Considerations
23
Detailed Project Analysis
• Involves the following steps
• where,
25
Example : Calculating Salvage Value
26
Solution to Example
27
Hidden Valley Case
• Case introduction
• Step 1. Building pro forma income statements
• Project revenues, costs, and depreciation
• Step 2. Estimate changes in NWC and capital expenditure
• Depreciation = (Cost – BV of Salvage)* Depreciation Rate
• Cash from salvage value = MV of Salvage - (MV - BV of Salvage)*Tax Rate
Note: Tax consequences when the project is scrapped at the end of the horizon
Market value = Book value => no taxes
Market value > Book value => Tax on capital gain
Market value < Book value => Tax shield on capital loss
28
Big Example
As CFO of Hidden Valley you are considering building a new salad
dressing factory. The initial cost to build the factory is $1 billion. You
plan to use straight line depreciation and depreciate the factory to a
book value of 0. The factory will last 5 years and have a salvage value
of $250 million. Sales from the factory are expected to be 1.25 billion
each year for the next 5 years and costs (other than depreciation) are
60% of revenues. Additional capital expenditures of $50 million will be
required at the end of each of for the next 5-years (i.e., at t=1,2,3,4 and
5). Inventories and A/P will immediately rise by $20 million and $5
million respectively and remain at these levels until returning back to
original levels at the end of the project (t=5). A/R will rise by $100
million after the 1st year (i.e., at t=1) and remain at that level until falling
back to original levels at the end of the project’s life (t=5). If the cost of
capital (WACC) for the project is 15%, the marginal tax rate is 40%
and the capital gains tax rate is 36%, what are the project’s NPV and
IRR?
29
Time Line
0 1 2 3 4 5
30
Step 1
“The initial cost to build the factory is $1 billion, the factory will last 5 years and
have a salvage value of $250 million. You plan to use straight line depreciation
and depreciate the factory to a book value of 0. ...the capital gains tax rate is
36%?”
0 1 2 3 4 5 31
Step 2a: Operating Cash Flow
Revenues
Costs
- Dep
EBIT
- Tax
EBIT(1-t)
+ DEP
OCF
0 1 2 3 4 5 32
Step 2b: Additional Capital
Expenditures
“Additional capital expenditures of $50 million will be required at the end
of each of for the next 5-years (i.e., at t=1,2,3,4 and 5).”
0 1 2 3 4 5
33
Step 2c: Change in working capital
“Inventories and A/P will immediately rise by $20 million and $5 million
respectively and remain at these levels until returning back to original levels
at the end of the project (t=5). A/R will rise by $100 million after the 1st
year (i.e., at t=1) and remain at that level until falling back to original levels
at the end of the project’s life (t=5).”
D A/R
D Inv.
D A/P
D WC
0 1 2 3 4 5
34
Put it all together
Estimate FCFF
0 1 2 3 4 5
Revenue - 1,250,000 1,250,000 1,250,000 1,250,000 1,250,000
- Costs - 750,000 750,000 750,000 750,000 750,000
- Dep - 200,000 200,000 200,000 200,000 200,000
EBIT - 300,000 300,000 300,000 300,000 300,000
-Tax - 120,000 120,000 120,000 120,000 120,000
EBIT(1-t) - 180,000 180,000 180,000 180,000 180,000
+ Dep - 200,000 200,000 200,000 200,000 200,000
- CapExp - 50,000 50,000 50,000 50,000 50,000
- DWC 15,000 100,000 - - - (115,000)
FCFF (15,000) 230,000 330,000 330,000 330,000 445,000
35
Find NPV
(numbers are $mills not 000s – time line space considerations)
0 1 2 3 4 5
$140.978 million
36
Additional Considerations
• Sunk Costs
• Opportunity costs (of assets in place)
• Externalities
• Inflation?
37
Sunk Costs
38
Opportunity Costs
Hidden Valley plans to use a building it owns for its new
factory. It could rent the building instead for $15,000 per
year (FCFF equivalent). Does this affect our project
decision?
0 1 2 3 4 5
39
Externalities
The new bottled salad dressing will have sales of $1.25 billion, but some
of those sales (equivalent to $10,000 in FCFF) will come from consumers
who switch from buying Hidden Valley's existing dry packet salad
dressing. Does this affect our decision to produce bottled dressing?
0 1 2 3 4 5
40
Add in the relevant CFs
Inital Outlay (1,000,000)
FCFF (15,000) 230,000 330,000 330,000 330,000 445,000
Terminal CF 160,000
Opp. Cost 0 (15,000) (15,000) (15,000) (15,000) (15,000)
Externalities 0 (10,000) (10,000) (10,000) (10,000) (10,000)
FINAL TIME LINE $ (1,015,000) $ 205,000 $ 305,000 $ 305,000 $ 305,000 $ 580,000
NPV $57,174.39
IRR 17.03%
Assumptions
WACC Project 15%
Dep (S-L down to 0) $ 200,000
Marginal Tax Rate 40%
Cap Gains Tax Rate 36%
41
Effects of Inflation
For example what if our prices for the salad dressing will
rise by inflation each year?
42
Project with inflation:
Assume the price of our new bottled salad dressing will rise by 3% each year (inflation).
Estimate FCFF
0 1 2 3 4 5
Revenue - 1,250,000 1,287,500 1,326,125 1,365,909 1,406,886
- Costs - 750,000 772,500 795,675 819,545 844,132
- Dep - 200,000 200,000 200,000 200,000 200,000
EBIT - 300,000 315,000 330,450 346,364 362,754
-Tax - 120,000 126,000 132,180 138,545 145,102
EBIT(1-t) - 180,000 189,000 198,270 207,818 217,653
+ Dep - 200,000 200,000 200,000 200,000 200,000
- CapExp - 50,000 50,000 50,000 50,000 50,000
- DWC 15,000 100,000 - - - (115,000)
FCFF (15,000) 230,000 339,000 348,270 357,818 482,653
43
Where else is inflation missing?
Inital Outlay (1,000,000)
FCFF (15,000) 230,000 339,000 348,270 357,818
482,653
Terminal CF 160,000
Opp. Cost 0 (15,000) (15,450) (15,914) (16,391) (16,883)
Externalities 0 (10,000) (10,300) (10,609) (10,927) (11,255)
FINAL TIME LINE $ (1,015,000) $ 205,000 $ 313,250 $ 321,748 $ 330,500 $ 614,515
NPV $106,164.01
IRR 18.69%
Assumptions
WACC Project 15%
Dep (S-L down to 0) $ 200,000
Marginal Tax Rate 40%
Cap Gains Tax Rate 36%
Infaltion 3%