Professional Documents
Culture Documents
Construction Joints:
They are typically placed at the end of days work but may be
required when concrete placement is stopped for longer than the initial
setting time of concrete .
Concrete floor slabs Section through concrete floor slab & joint detail
But at the same time, they have to transfer flexural stresses produced in
the slab by external loads.
At the same time they must not allow vertical or rotational displacements.
Using the patented Ideal Joint systems will offer long term benefits and
cost savings for every slab-on-grade project.
TRADITIONAL METHODS FOR A CONSTRUCTION JOINT
Often, through the lack of care and placing the steel dowels unevenly
in spacing or at the incorrect angle, joint failure is inevitable causing
long term damage to the joint and slab-on-grade (Figure 5).
Even if the dowel joint is positioned correctly they are usual knocked
out of place and moved during the concrete placement (Figure 4).
The dowel bars that are misplaced or out of line now increase the risk
of cracking the actual concrete (Figure 6).
Shear transfer is provided by shear friction between the old and new
concrete, or dowel action in the reinforcement through the joint.
COLUMNS AND WALLS
Construction joints are provided at the top of floor slabs for columns
continuing to the next floor; column capitals, haunches, drop panels,
and brackets should be placed monolithically with the slab.
SUMMARY
Construction joints are necessary in most reinforced concrete
construction. Due to their critical nature, they should be located by the
designer, and indicated on the design drawings to insure adequate force
transfer and aesthetic acceptability at the joint. If concrete placement is
stopped involuntarily for a time longer than the initial setting time of the
concrete, the joint should be treated as a construction joint, with advance
input from the designer as to any additional requirements needed to
insure the structural integrity of the element being placed.