You are on page 1of 10

[U98 BUILDING WORKS]

Objective:
How To Measure Simply the
Progress Payment of
U98 Master Control Tower Building and
Administration Building
(Concreting - Forms / Rebar’s / Pouring)

Area to Consider:
Focus only on Foundation Level until GF Slabs (see page 3)

Prepared by: PCM Planning Dept.


2017-00-July
General Layout

Master Control Tower and


Administration Building

Foundation Layout
Security Building Section
Foundation Level

MCTB Section
Foundation Level
INITIAL STEPS ARE NEEDED TO BE DONE FIRST 1 1
Note: PCM Planning Team has
1. Calculate Concrete Volume. 2 the Volume computation if
2. Compare and Determine the Difference. PMC request for verification.
3. Decide which Volume to use. PCM Construction
Planning Team Team
Difference bet
Concrete Concrete
Floor Location Item Unit Planning and Remarks
Volume Volume Const. Team
RC Foundation & MF1 m3 1,832.83 1,766.39 66.44
1st RC Slab MF2 m3 719.85 719.85 (0.00)
(until Elev. 105.95) Tie Girder m3 39.39 48.87 (9.48)
Harbour Master's Control
Column (EL 105.95) m3 11.76 14.00 (2.24)
Tower Building
RC Wall (EL 105.95) m3 55.15 60.07 (4.92)
Grade Slab m3 134.62 149.22 (14.60)
Suspended Slab m3 17.08 20.04 (2.96)
Holding Tank Box m3 22.53 21.76 0.77
Sub-total m3 2,833.20 2,800.20 33.00 Normal
MF3 m3 355.54 353.55 1.99
Isolated Footing and FTB m3 231.95 209.44 22.51
Tie Girder m3 42.28 109.57 (67.29)
Maintenance and
Column (EL 105.95) m3 39.53 39.53 (0.00)
Operations Building
RC Wall (EL 105.95) m3 126.89 121.01 5.88
Grade Slab m3 502.97 219.93 283.04
Because revision is
Suspended Slab m3 98.24 50.37 47.87
not yet Finalized
Holding Tank Box m3 17.02 17.52 (0.50)
Sub-total m3 1,414.42 1,120.92 293.50
Isolated Footing and FTB m3 88.98 96.00 (7.03)
Tie Girder m3 29.39 30.80 (1.41)
Security Building
Column (EL 105.95) m3 7.35 7.35 0.00
Grade Slab m3 96.01 94.65 1.36
Holding Tank Box m3 9.95 10.57 (0.62) 3
Sub-total m3 231.68 239.37 (7.69) Normal
Grand Total m3 4,479.30 4,160.49 318.81 We can use PCM Qty
4 5
4. Simplify the MAIN ITEMS needed for progress
measurement by combining associated items into one.
5. Using the Selected and Combined Volume,
determine the Percentage Weight of the concrete.
Determining Percentage Weight

Main Item Volume Percentage


Floor Location Item Unit
Description Considered Weight
This is Important!
RC Foundation & MF1 m3 MF1 1,832.83 40.92%
1st RC Slab MF2 m3 MF2 719.85 16.07%
This Percentage
(until Elev. 105.95) Tie Girder m3 Column
Weight is Different
Harbour Master's Control 51.14 1.14% from Floor to Floor
Column (EL 105.95) m3 (w/ TG)
Tower Building of the Building.
RC Wall (EL 105.95) m3 RC Wall 55.15 1.23%
Grade Slab m3
Slab 151.70 3.39%
Suspended Slab m3
Holding Tank Box m3 Holding Tank 22.53 0.50%
Sub-total m3 2,833.20 63.25%
MF3 m3 MF3 355.54 7.94%
Isolated Footing and FTB m3 Iso. Footing
274.22 6.12%
Tie Girder m3 (w/ FTB)
Maintenance and
Column (EL 105.95) m3 Column 39.53 0.88%
Operations Building
RC Wall (EL 105.95) m3 RC Wall 126.89 2.83%
Grade Slab m3
Slab 601.21 13.42%
Suspended Slab m3
Holding Tank Box m3 Holding Tank Box 17.02 0.38%
Sub-total m3 1,414.42 31.58%
Isolated Footing and FTB m3 Iso. Footing
118.37 2.64%
Tie Girder m3 (w/ FTB, w/ TG)
Security Building
Column (EL 105.95) m3 Column 7.35 0.16%
Grade Slab m3 Slab 96.01 2.14%
Holding Tank Box m3 Holding Tank Box 9.95 0.22%
Sub-total m3 231.68 5.2%
Grand Total m3 4,479.30 100.00%
6. Establish the Final “Quantity of Main Item” and its “Units”.
6
7. This “Quantity” shall be Utilized until Item Completion.
THIS IS IMPORTANT!

Main Item Percentage Quantity of


Floor Location Unit
Considered Weight Main Item

RC Foundation & MF1 40.92% 5 parts


1st RC Slab MF2 16.07% 1 part
(until Elev. 105.95) Column
Harbour Master's Control 1.14% 37 pcs
(w/ TG)
Tower Building
RC Wall 1.23% 14 span

Slab 3.39% 30 bay

Holding Tank 0.50% 1 unit


Sub-total 63.25%
MF3 7.94% 1 part
Iso. Footing
6.12% 37 pcs
(w/ FTB)
Maintenance and
Column 0.88% 37 pcs
Operations Building
RC Wall 2.83% 16 span

Slab 13.42% 39 bay

Holding Tank Box 0.38% 1 unit


Sub-total 31.58%
Iso. Footing
2.64% 16 pcs
(w/ FTB, w/ TG)
Security Building
Column 0.16% 16 pcs
Slab 2.14% 9 bay
Holding Tank Box 0.22% 1 unit
Sub-total 5.2%
Grand Total 100.00%
EXAMPLE OF BACK UP MATERIAL SHEET [1/2]

8. Back Up Material [1/2]: Rebar Installation (MS-2) Progress


8

9. Back Ups for Forms (MS-1) and Pouring (MS-3) are separate. Back Up Material [1/2]
Rebar Installation Progress [MS-2] [Sample Only]
Main Item Percentage Quantity of This
Floor Location Unit Previous %
Considered Weight Main Item Month Cumulative - MF2 Rebar:
RC Foundation & MF1 40.92% 5 parts 0.00%
50% was
1st RC Slab MF2 16.07% 1 part 0.50 0.50 8.04%
considered
(until Elev. 105.95) Column
Installed
Harbour Master's Control 1.14% 37 pcs 10.00 10.00 0.31% (bottom bars /
(w/ TG)
Tower Building
RC Wall 1.23% 14 span 0.00% top bars etc.)
Slab 3.39% 30 bay 0.00%

Holding Tank 0.50% 1 unit 0.00% - Column Rebar:


Sub-total 63.25% 8.34% 10 Nos.
MF3 7.94% 1 part 0.00% Installed
Iso. Footing
6.12% 37 pcs 0.00%
(w/ FTB)
Maintenance and
Column 0.88% 37 pcs 0.00%
Operations Building
RC Wall 2.83% 16 span 0.00%

Slab 13.42% 39 bay

Holding Tank Box 0.38% 1 unit 0.00%


Sub-total 31.58% 0.00%
Iso. Footing
2.64% 16 pcs
(w/ FTB, w/ TG)
Security Building
Column 0.16% 16 pcs 0.00%
Slab 2.14% 9 bay 0.00%
Holding Tank Box 0.22% 1 unit 0.00%
Sub-total 5.2% 0.0%
Grand Total 100.00% 8.34%
EXAMPLE OF BACK UP [Sample]
MATERIAL SHEET [2/2] - MF2 Rebar:
50% was
considered
Installed
(bottom bars /
top bars etc.)

- Column Rebar:
10 Nos.
Quantity of Installed
Item are
indicated in
Marked
Numbers Measured Items
are Highlighted In
Yellow Color

To be signed by all Parties


10. Apply the Progress in Rebar Installation Back Up [1/2]
into the ‘Payment Progress Sheet (MS-2)” Back Up Material [1/2]
Rebar Installation Progress [MS-2]
Main Item Percentage Quantity of This
Floor Location Unit Previous %
Considered Weight Main Item Month Cumulative

RC Foundation & Harbour Master's Control Tower BuildingSub-total 63.25% 8.34%


1st RC Slab Maintenance and Operations Building Sub-total 31.58% 0.00%
Security Building Sub-total 5.2% 0.0%
Grand Total 100.00% 8.34%

THIS IS
IMPORTANT!

9
OTHER EXAMPLES OF BACK UP MATERIAL SHEET [2/2]

By Nos
By Span By Bay

Quantity of Quantity of
Item are Item are
indicated in indicated in
Marked Marked
Numbers Numbers

11. “Back Up Materials [1/2] and [2/2] shall be


utilized in pairs (Tabulation and Layout)

12. This System will applied Commonly in


Concreting Works for All U98 Building.
END. THANK YOU!