Hold Point: Inspection or Test may not proceed without the QA/QC
organization representative in attendance. Or QA/QC organization shall be
notified of the timing of inspection or test in advance. Inspection or test shall not be
carried out without the QA/QC organization representative in attendance.
Witness Point: It defines a point that provides QA/QC organization with the
opportunity to attend the Inspection or Test, at their option. Or QA/QC
organization shall be notified of the timing of Inspection or test in advance.
However, the inspection or test shall be performed as scheduled if the QA/QC
organization representative is not present.
Surveillance: QA/QC organization to monitor work in progress without notice
from Construction Organization
Anoop E Venugopal
Rotating Equipment – Any piece of mechanical
equipment that has a rotating shaft. This
includes but is not limited to centrifugal pumps,
blowers, fans, compressors, vacuum pumps and
extruders.
Field Fit Weld (FFW) – Piping is fabricated with
additional length (approximately 150 mm (6”)
longer) than the dimension shown on the
isometric drawings. This will result in trimming
the pipe and will require a field weld. This is used
to facilitate alignment of piping to equipment
nozzles.
Anoop E Venugopal
Field Weld (FW) – Welds shall be made on the site to facilitate shipping,
assembly and erection of piping.
Anoop E Venugopal
Pre-Commissioning: Testing of system components for
continuity, operability and in the case of the process
plants, their ability to withstand operating pressure prior
to the introduction of feedstock or other final products
into the facility.
Quality Plan: Document specifying which procedures and
associated resources shall be applied by whom and when
to a specific project, product, process or contract. [ISO
9000] a) Document all procedures. b) Describe how the
processes interact. c) Define the scope of the project
quality system. d) Document all Procurement,
Construction, Inspection & Test Plans and Pre-
Commissioning