Professional Documents
Culture Documents
MEPFS CONTRACTOR
Contractor :
26.45%
TOTAL SALES 27,750,808.09 4,162,621.21 2,775,080.81 495,550.14 20,317,555.92
CHANGE ORDERS BILLING SUMMARY
PERCENTAGE OF
BILLING NO. TRADE DATE GROSS AMOUNT RECOUPMENT RETENTION TAX NET AMOUNT PAID
COMPLETION
PERCENTAGE OF
BILLING NO. TRADE DATE GROSS AMOUNT RECOUPMENT RETENTION TAX NET AMOUNT PAID
COMPLETION
10 21
17 22
8 9
7 24
BALANCE
OF WORK
UNIT 16
BALANCE OF WORKS
BALANCE
BALANCE OF WORK
OF WORK UNIT 16
UNIT 9
BALANCE OF WORKS
BALANCE OF WORKS
BALANCE OF WORKS
BALANCE OF WORKS
21st
25th
24th
20th
19th
18th
17th
16th
15th
14th
12th
11th
10th
23rd
22nd
FLOORS
1
UNIT 1
2
UNIT 2
UNIT 3
DONE
UNIT 4
5
UNIT 5
6
UNIT 6
UNIT 7 CORNER
UNIT 7
UNIT 8 CORNER
8
UNIT 8
9
UNIT 9
UNIT 10
UNIT 11
UNIT 12
UNIT 14
UNIT 15
16
16
UNIT 16
BALANCE/FAILED UNIT 17
SANITARY TESTING MONITORING
UNIT 18
19
UNIT 19
20
UNIT 20
UNIT 21
UNIT 22
UNIT 23
UNIT 24 CORNER
UNIT 24
UNIT 25
UNIT 26
WATERLINE
INSTALLATION
MONITORING
4TH FLOOR
INSTALLED PIPING
18TH FLOOR
INSTALLED PIPING
19TH FLOOR
INSTALLED PIPING
FLOOR
9th
8th
7th
6th
5th
4th
21st
25th
24th
20th
19th
18th
17th
16th
15th
14th
12th
11th
10th
23rd
22nd
UNIT 1
UNIT 2
UNIT 3
DONE
UNIT 4
UNIT 5
UNIT 6
UNIT 7
7
UNIT 8
UNIT 9
UNIT 10
UNIT 11
UNIT 12
12
UNIT 14
UNIT 15
UNIT 16
BALANCE/FAILED
UNIT 17
UNIT 18
WATERLINE TESTING MONITORING
UNIT 19
UNIT 20
UNIT 21
21
UNIT 22
22
UNIT 23
23
UNIT 24
24
UNIT 25
UNIT 26
AUTOMATIC FIRE
SPRINKLER SYSTEM
INSTALLATION
MONITORING
2ND FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)
15-Nov-17
24-Nov-17
11
12-Sep-17
19-Sep-17
12-Oct-17
19-Oct-17
6-Nov-17
2-Oct-17
12
14
15
16
17
18
19
20
21 No
22 Unit
23
24
25
26
Legend:
PASSED FAILED ONGOING RECTIFICATION
PREVIOUSLY INSTALLED
5TH FLOOR
PREVIOUSLY INSTALLED
6TH FLOOR
PREVIOUSLY INSTALLED
7TH FLOOR
PREVIOUSLY INSTALLED
8TH FLOOR
PREVIOUSLY INSTALLED
9TH FLOOR
PREVIOUSLY INSTALLED
10TH FLOOR
PREVIOUSLY INSTALLED
11TH FLOOR
PREVIOUSLY INSTALLED
12TH FLOOR
PREVIOUSLY INSTALLED
14TH FLOOR
PREVIOUSLY INSTALLED
15TH FLOOR
PREVIOUSLY INSTALLED
16TH FLOOR
PREVIOUSLY INSTALLED
ELECTRICAL
INSTALLATION
MONITORING
4TH FLOOR
INSTALLED WIRES
CABLE
TRAY
MEGGER TEST
11TH FLOOR
CABLE
TRAY
MEGGER TEST
12TH FLOOR
CABLE
TRAY
MEGGER TEST
14TH FLOOR
CABLE
TRAY
MEGGER TEST
15TH FLOOR
CABLE
TRAY
MEGGER TEST
16TH FLOOR
CABLE
TRAY
MEGGER TEST
17TH FLOOR
CABLE
TRAY
MEGGER TEST
MEGGER TESTING MONITORING
PROJECT: THE LOOP NORTH TOWER
LOCATION: Rosario crescent cor. Limketkai drive, Cagayan de Oro City CONSTRUCTION, INC.
2nd Level, Starmall Annex, Alabang -Zapote Road , Las Piñas City
SUBJECT: RESIDENTIAL UNIT MEGGER TEST MONITORING Tel: 871-0741 to 42 Fax: 871-0743
DATE: 18-Oct-17
FLOOR AREA
Unit No.
GF 2F 3F 4F 5F 6F 7F 8F 9F 10F 11F 12F 14F 15F 16F 17F 18F 19F 20F 21F 22F 23F 24F 25F 26F 25F 26F RD
1
2
3
4
5
6
7
8
9
10
11
12
14
15
16
17
18
19
20
21 No
22 Unit
23
24
25
26
HALLWAY
Legend:
PASSED FAILED ONGOING RECTIFICATION
FLOOR AREA
Unit No.
GF 2F 3F 4F 5F 6F 7F 8F 9F 10F 11F 12F 14F 15F 16F 17F 18F 19F 20F 21F 22F 23F 24F 25F 26F 25F 26F RD
1
2
3
4
5
6
7
8
9
10
11
12
14
15
16
17
18
19
20
21
22
23
24
25
26
HALLWAY
Legend:
PASSED FAILED ONGOING RECTIFICATION
AIR PRESSURIZATION
STAIR 1
STAIR 2
5
10
4
9
3
8
2
7
GF 6
17
17
22
22
16
16
21
21
15
15
20
20
14
14
19
19
12
12
18
18
11
11