THE LOOP- NORTH TOWER

MEPFS CONTRACTOR

PROJECT WEEKLY ACCOMPLISHMENT REPORT


AS OF
DECEMBER 31, 2017

ENGR. LOWENTAN F. LAXAMANA


PROJECT IN CHARGE
PROJECT INFORMATION

Contractor :

Scope of Work :Fire Protection,


Plumbing/Sanitary, Electrical, &
Mechanical Works

Project Total Contract Package : Php 104,900,000.00

Project Duration : 663 calendar Days

Official Day 1 : July 30, 2016


PROJECT TIME TABLE:

PROJECT COMPLETION : MAY 23, 2018

PROJECT PERIOD : 663 CAL. DAYS

DAYS ELAPSED : 519 CAL. DAYS (78.28%)

DAYS TO GO : 143 CAL. DAYS (21.72%)

TOPPING OFF SCHEDULE : DONE ON NOV. 28 2017


OVERALL PROGRESS
A.) PROJECT STATUS

(see separate sheet)


ii. FINANCIAL REPORT
(DEVELOPER’S BILLING)

PROJECT: THE LOOP NORTH TOWER


TCP: 104,902,327.43
DP: 15,735,000.00

SUMMARY OF DEVELOPERS BILLING


PERCENTAGE OF DATE ENDORSED GROSS AMOUNT
BILLING NO. COMPLETION TO DEVELOPER SUBMITTED TO RECOUPMENT RETENTION TAX NET AMOUNT PAID REMARKS
DEVELOPER
1 2.22% 2/15/2017 2,328,780.00 349,317.00 232,878.00 41,585.36 1,704,999.64 with Interim
2 1.26% 3/21/2017 1,321,740.00 198,261.00 132,174.00 23,602.50 967,702.50 with Interim
3 2.63% 5/30/2017 2,758,870.00 413,830.50 275,887.00 49,265.54 2,019,886.96 with Interim
4 2.01% 7/7/2017 2,108,490.00 316,273.50 210,849.00 37,651.61 1,543,715.89 with Interim
5 2.62% 8/8/2017 2,748,380.00 412,257.00 274,838.00 49,078.21 2,012,206.79 with Interim
6 3.79% 9/1/2017 3,975,710.00 596,356.50 397,571.00 70,994.82 2,910,787.68 with Interim
7 4.15% 10/18/2017 4,353,350.00 653,002.50 435,335.00 77,738.39 3,187,274.11 with Interim
8 2.72% 11/7/2017 2,853,280.00 427,992.00 285,328.00 50,951.43 2,089,008.57 with Interim
9 2.48% 12/2/2017 2,601,520.00 390,228.00 260,152.00 46,455.71 1,904,684.29 with Interim
10 2.57% 1/11/2018 2,700,688.09 405,103.21 270,068.81 48,226.57 1,977,289.49 EVALUATED

26.45%
TOTAL SALES 27,750,808.09 4,162,621.21 2,775,080.81 495,550.14 20,317,555.92
CHANGE ORDERS BILLING SUMMARY

PROJECT: THE LOOP NORTH TOWER (CHANGE ORDER NO. 1)


TCP: 3,726,013.99
DP: -

SUMMARY OF BILLING for CHANGE ORDER NO.1 (CABLE TRAY)


PERCENTAGE OF DATE ENDORSED GROSS AMOUNT
BILLING NO. COMPLETION TO DEVELOPER SUBMITTED TO RECOUPMENT RETENTION TAX NET AMOUNT PAID REMARKS
DEVELOPER
1 17.49% 10/3/2017 651,679.85 65,167.98 11,637.14 574,874.72 with Interim
2 34.87% 12/2/2017 1,299,261.08 129,926.11 23,201.09 1,146,133.88 with Interim
- - - -
- - - -
- - - -
- - - -
- - - -

TOTAL SALES 1,950,940.93 - 195,094.09 34,838.23 1,721,008.60


SUBCON BILLING SUMMARY
PROJECT: THE LOOP NORTH TOWER
CONTRACTOR: ADVANCE MATRIX CONSTRUCTION
TCP: 81,000,000.00
DP: 8,100,000.00

SUMMARY OF SUBCON BILLING

PERCENTAGE OF
BILLING NO. TRADE DATE GROSS AMOUNT RECOUPMENT RETENTION TAX NET AMOUNT PAID
COMPLETION

ELECTRICAL 5/12/2017 1,435,314.78 287,062.96 143,531.48 25,630.62 979,089.72


MECHANICAL 5/12/2017 162,756.89 32,551.38 16,275.69 2,906.37 111,023.45
1 4.32%
PLUMBING 5/12/2017 1,199,393.33 239,878.67 119,939.33 21,417.74 818,157.59
FIRE PROTECTION 5/12/2017 705,555.08 141,111.02 70,555.51 12,599.20 481,289.36
ELECTRICAL 7/6/2017 640,655.11 128,131.02 64,065.51 11,440.27 437,018.31
MECHANICAL 7/6/2017 113,470.08 22,694.02 11,347.01 2,026.25 77,402.80
2 3.23%
PLUMBING 7/6/2017 1,259,146.32 251,829.26 125,914.63 22,484.76 858,917.67
FIRE PROTECTION 7/6/2017 600,357.78 120,071.56 60,035.78 10,720.67 409,529.77
ELECTRICAL 8/12/2017 524,876.51 104,975.30 52,487.65 9,372.79 358,040.76
MECHANICAL 8/12/2017 93,323.96 18,664.79 9,332.40 1,666.50 63,660.27
3 1.97%
PLUMBING 8/12/2017 803,406.80 160,681.36 80,340.68 14,346.55 548,038.21
FIRE PROTECTION 8/12/2017 177,898.28 35,579.66 17,789.83 3,176.76 121,352.04
ELECTRICAL 8/12/2017 541,235.91 108,247.18 54,123.59 9,664.93 369,200.21
MECHANICAL 8/12/2017 165,103.48 33,020.70 16,510.35 2,948.28 112,624.16
4 3.33%
PLUMBING 8/12/2017 1,351,699.45 270,339.89 135,169.95 24,137.49 922,052.12
FIRE PROTECTION 8/12/2017 636,577.30 127,315.46 63,657.73 11,367.45 434,236.66
ELECTRICAL 8/12/2017 876,216.17 175,243.23 87,621.62 15,646.72 597,704.60
MECHANICAL 8/12/2017 196,995.38 39,399.08 19,699.54 3,517.77 134,378.99
5 3.67%
PLUMBING 8/12/2017 1,348,663.81 269,732.76 134,866.38 24,083.28 919,981.38
FIRE PROTECTION 8/12/2017 551,095.49 110,219.10 55,109.55 9,840.99 375,925.85
ELECTRICAL 8/12/2017 1,192,250.92 238,450.18 119,225.09 21,290.20 813,285.45
MECHANICAL 8/12/2017 136,557.56 27,311.51 13,655.76 2,438.53 93,151.76
6 3.58%
PLUMBING 8/12/2017 1,057,450.72 211,490.14 105,745.07 18,883.05 721,332.46
FIRE PROTECTION 8/12/2017 510,103.29 102,020.66 51,010.33 9,108.99 347,963.32
ELECTRICAL 1/5/2018 1,115,899.23 223,179.85 111,589.92 19,926.77 761,202.69
MECHANICAL 1/5/2018 236,821.02 47,364.20 23,682.10 4,228.95 161,545.77
7 3.45%
PLUMBING 1/5/2018 972,306.69 194,461.34 97,230.67 17,362.62 663,252.06
FIRE PROTECTION 1/5/2018 469,185.49 93,837.10 46,918.55 8,378.31 320,051.53

TOTAL 19,074,316.82 3,814,863.36 1,907,431.68 340,612.80 13,011,408.98


23.55%
SUBCON BILLING SUMMARY
(CHANGE ORDER NO. 1)
PROJECT: THE LOOP NORTH TOWER
CONTRACTOR: ADVANCE MATRIX CONSTRUCTION
TCP: 3,093,187.20
DP: -

SUMMARY OF SUBCON BILLING (CHANGE ORDER NO. 1)

PERCENTAGE OF
BILLING NO. TRADE DATE GROSS AMOUNT RECOUPMENT RETENTION TAX NET AMOUNT PAID
COMPLETION

1 ELECTRICAL CT 17.18% 5/12/2017 531,447.82 106,289.56 53,144.78 9,490.14 362,523.33


2 ELECTRICAL CT 27.80% 7/6/2017 859,867.99 171,973.60 85,986.80 15,354.79 586,552.81

TOTAL 1,391,315.81 278,263.16 139,131.58 24,844.93 949,076.14


44.98%
SANITARY INSTALLATION
MONITORING
4TH FLOOR

BALCONY DRAIN INSTALLED

INSTALLED PIPING GRAVITY TEST APPROVED ALL UNITS FIXTURES INSTALLED


5TH FLOOR

BALCONY DRAIN INSTALLED

INSTALLED PIPING GRAVITY TEST APPROVED ALL UNITS FIXTURES INSTALLED


6TH FLOOR

BALCONY DRAIN INSTALLED

INSTALLED PIPING GRAVITY TEST APPROVED ALL UNITS


7TH FLOOR

BALCONY DRAIN INSTALLED

INSTALLED PIPING GRAVITY TEST APPROVED ALL UNITS


8TH FLOOR

BALCONY DRAIN INSTALLED

INSTALLED PIPING GRAVITY TEST APPROVED ALL UNITS


9TH FLOOR

BALCONY DRAIN INSTALLED

INSTALLED PIPING GRAVITY TEST APPROVED ALL UNITS


10TH FLOOR

10 21
17 22

INSTALLED PIPING GRAVITY TEST APPROVED


11TH FLOOR

8 9

INSTALLED PIPING GRAVITY TEST APPROVED


12TH FLOOR

7 24

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


14TH FLOOR

BALANCE
OF WORK
UNIT 16

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


15TH FLOOR

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


16TH FLOOR

BALANCE OF WORKS

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


17TH FLOOR

BALANCE
BALANCE OF WORK
OF WORK UNIT 16
UNIT 9

BALANCE OF WORKS

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


18TH FLOOR

BALANCE OF WORKS

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


19TH FLOOR

BALANCE OF WORKS

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


20TH FLOOR

BALANCE OF WORKS

INSTALLED PIPING GRAVITY TEST ON GOING PREPARATION


9th
8th
7th
6th
5th
4th

21st

25th
24th
20th
19th
18th
17th
16th
15th
14th
12th
11th
10th

23rd
22nd
FLOORS

1
UNIT 1

2
UNIT 2

UNIT 3

DONE
UNIT 4

5
UNIT 5

6
UNIT 6

UNIT 7 CORNER

UNIT 7

UNIT 8 CORNER

8
UNIT 8

9
UNIT 9

UNIT 10

UNIT 11

UNIT 12

UNIT 14

UNIT 15
16
16

UNIT 16

BALANCE/FAILED UNIT 17
SANITARY TESTING MONITORING

UNIT 18
19

UNIT 19
20

UNIT 20

UNIT 21

UNIT 22

UNIT 23

UNIT 24 CORNER

UNIT 24

UNIT 25

UNIT 26
WATERLINE
INSTALLATION
MONITORING
4TH FLOOR

INSTALLED PIPING HYDROTEST APPROVED ALL UNIT


5TH FLOOR

INSTALLED PIPING HYDROTEST APPROVED ALL UNIT


6TH FLOOR

INSTALLED PIPING HYDROTEST APPROVED ALL UNIT


7TH FLOOR

INSTALLED PIPING HYDROTEST APPROVED


8TH FLOOR

INSTALLED PIPING HYDROTEST APPROVED ALL UNIT


9TH FLOOR

INSTALLED PIPING HYDROTEST APPROVED


10TH FLOOR

INSTALLED PIPING HYDRO TEST – ON GOING PREPARATION


11TH FLOOR

INSTALLED PIPING HYDRO TEST – ON GOING PREPARATION


12TH FLOOR

INSTALLED PIPING HYDRO TEST – ON GOING PREPARATION


14TH FLOOR

INSTALLED PIPING HYDRO TEST – ON GOING PREPARATION


15TH FLOOR

INSTALLED PIPING HYDRO TEST – ON GOING PREPARATION


16TH FLOOR

INSTALLED PIPING HYDRO TEST – ON GOING PREPARATION


17TH FLOOR

INSTALLED PIPING
18TH FLOOR

INSTALLED PIPING
19TH FLOOR

INSTALLED PIPING
FLOOR

9th
8th
7th
6th
5th
4th

21st

25th
24th
20th
19th
18th
17th
16th
15th
14th
12th
11th
10th

23rd
22nd
UNIT 1

UNIT 2

UNIT 3

DONE
UNIT 4

UNIT 5

UNIT 6

UNIT 7

7
UNIT 8

UNIT 9

UNIT 10

UNIT 11

UNIT 12
12

UNIT 14

UNIT 15

UNIT 16

BALANCE/FAILED
UNIT 17

UNIT 18
WATERLINE TESTING MONITORING

UNIT 19

UNIT 20

UNIT 21
21

UNIT 22
22

UNIT 23
23

UNIT 24
24

UNIT 25

UNIT 26
AUTOMATIC FIRE
SPRINKLER SYSTEM
INSTALLATION
MONITORING
2ND FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


3RD FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


4TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


5TH FLOOR

FIRE HOSE CABINET NOT YET INSTALLED


-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


6TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


7TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


8TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


9TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


10TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


11TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


12TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


14TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


15TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST APPROVED

INSTALLED PIPES AND FITTINGS


16TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

HYDRO TEST – ON GOING PREPARATION

INSTALLED PIPES AND FITTINGS


17TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


18TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


19TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


20TH FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


21st FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


22nd FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS


23rd FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS NOTE: BALANCE PIPING - ON GOING


24th FLOOR
FIRE HOSE CABINET NOT YET INSTALLED
-WAITING FOR MATERIALS(OSM)

INSTALLED PIPES AND FITTINGS NOTE: BALANCE PIPING - ON GOING


AFSS TESTING MONITORING
PROJECT: THE LOOP NORTH TOWER
LOCATION: Rosario crescent cor. Limketkai drive, Cagayan de Oro City
SUBJECT: RESIDENTIAL UNIT AFSS PRESSURE TEST MONITORING
DATE: 24-Nov-17
FLOOR
Unit No.
GF 2F 3F 4F 5F 6F 7F 8F 9F 10F 11F 12F 14F 15F 16F 17F 18F 19F 20F 21F 22F 23F 24F 25F 26F 25F 26F RD
1
2
3
4
5
6
7

READY FOR INSPECTION

READY FOR INSPECTION


8
9
10

15-Nov-17

24-Nov-17
11
12-Sep-17

19-Sep-17

12-Oct-17

19-Oct-17

6-Nov-17
2-Oct-17

12
14
15
16
17
18
19
20
21 No
22 Unit

23
24
25
26
Legend:
PASSED FAILED ONGOING RECTIFICATION

Prepared by: Noted by:

Eduardo de la Rosa Jr Lowentan Laxamana


MEPF Engineer - MGS Project MEPF Head
PVC EXHAUST
INSTALLATION
MONITORING
4TH FLOOR

PREVIOUSLY INSTALLED
5TH FLOOR

PREVIOUSLY INSTALLED
6TH FLOOR

PREVIOUSLY INSTALLED
7TH FLOOR

PREVIOUSLY INSTALLED
8TH FLOOR

PREVIOUSLY INSTALLED
9TH FLOOR

PREVIOUSLY INSTALLED
10TH FLOOR

PREVIOUSLY INSTALLED
11TH FLOOR

PREVIOUSLY INSTALLED
12TH FLOOR

PREVIOUSLY INSTALLED
14TH FLOOR

PREVIOUSLY INSTALLED
15TH FLOOR

PREVIOUSLY INSTALLED
16TH FLOOR

PREVIOUSLY INSTALLED
ELECTRICAL
INSTALLATION
MONITORING
4TH FLOOR

PIPING AND BOX SETTING - COMPLETED

INSTALLED WIRES

MEGGER TEST COMPLETED ALL UNIT


5TH – 9TH FLOOR

PIPING AND BOX SETTING - COMPLETED

INSTALLED POWER OUTLET AND LIGHTNING WIRES

MEGGER TEST COMPLETED ALL UNIT


10TH FLOOR

CABLE
TRAY

PIPING AND BOX SETTING - COMPLETED

INSTALLED POWER OUTLET AND LIGHTNING WIRES

MEGGER TEST
11TH FLOOR

CABLE
TRAY

PIPING AND BOX SETTING - COMPLETED

INSTALLED POWER OUTLET AND LIGHTNING WIRES

MEGGER TEST
12TH FLOOR

CABLE
TRAY

PIPING AND BOX SETTING - COMPLETED

INSTALLED LIGHTNING WIRES

MEGGER TEST
14TH FLOOR

CABLE
TRAY

PIPING AND BOX SETTING - COMPLETED

INSTALLED POWER OUTLET AND LIGHTNING WIRES

MEGGER TEST
15TH FLOOR

CABLE
TRAY

PIPING AND BOX SETTING - COMPLETED

INSTALLED POWER OUTLET AND LIGHTNING WIRES

MEGGER TEST
16TH FLOOR

CABLE
TRAY

PIPING AND BOX SETTING - COMPLETED

INSTALLED POWER OUTLET AND LIGHTNING WIRES

MEGGER TEST
17TH FLOOR

CABLE
TRAY

PIPING AND BOX SETTING - COMPLETED

INSTALLED POWER OUTLET AND LIGHTNING WIRES

MEGGER TEST
MEGGER TESTING MONITORING
PROJECT: THE LOOP NORTH TOWER
LOCATION: Rosario crescent cor. Limketkai drive, Cagayan de Oro City CONSTRUCTION, INC.
2nd Level, Starmall Annex, Alabang -Zapote Road , Las Piñas City
SUBJECT: RESIDENTIAL UNIT MEGGER TEST MONITORING Tel: 871-0741 to 42 Fax: 871-0743
DATE: 18-Oct-17

FLOOR AREA
Unit No.
GF 2F 3F 4F 5F 6F 7F 8F 9F 10F 11F 12F 14F 15F 16F 17F 18F 19F 20F 21F 22F 23F 24F 25F 26F 25F 26F RD
1
2
3
4
5
6
7
8
9
10
11
12
14
15
16
17
18
19
20
21 No
22 Unit
23
24
25
26
HALLWAY
Legend:
PASSED FAILED ONGOING RECTIFICATION

Prepared by: Noted by:

Eduardo de la Rosa Jr Lowentan Laxamana


MEPF Engineer - MGS Project MEPF Head
CABLE TRAY INSTALLATION MONITORING

PROJECT: THE LOOP NORTH TOWER


LOCATION: Rosario crescent cor. Limketkai drive, Cagayan de Oro City CONSTRUCTION, INC.
SUBJECT: RESIDENTIAL UNIT CABLE TRAY MONITORING 2nd Level, Starmall Annex, Alabang -Zapote Road , Las Piñas City
Tel: 871-0741 to 42 Fax: 871-0743
DATE: 18-Oct-17

FLOOR AREA
Unit No.
GF 2F 3F 4F 5F 6F 7F 8F 9F 10F 11F 12F 14F 15F 16F 17F 18F 19F 20F 21F 22F 23F 24F 25F 26F 25F 26F RD
1
2
3
4
5
6
7
8
9
10
11
12
14
15
16
17
18
19
20
21
22
23
24
25
26
HALLWAY
Legend:
PASSED FAILED ONGOING RECTIFICATION

Prepared by: Noted by:

Eduardo de la Rosa Jr Lowentan Laxamana


MEPF Engineer - MGS Project MEPF Head
MECHANICAL WOKS

AIR PRESSURIZATION
STAIR 1
STAIR 2
5
10

4
9

3
8

2
7

GF 6
17
17
22
22
16
16
21
21
15
15
20
20
14
14
19
19
12
12
18
18
11
11

INSTALLED/ SMOKE TEST PASSED ON GOING WORK


MANPOWER LOADING
MEPF HEAD 1
MEPF QA/QC ENGINEER 4
SAFETY OFFICER 1
SITE ENGINEER 5
ELECTRICIAN 40
PLUMBER 8
PURCHASER 1
WELDER/PIPE FITTER 8
DUCTMAN 7
HELPER/CARPENTER/MASON 42
WAREHOUSEMAN 1
TOTAL 117