You are on page 1of 185

SAV

SDC
Swiss-AIT-Vietnam Management Development Programme

Lesson 2:

Course:
Project Organization
& Implementation

Instructor: Dr. Tran Phuong Trinh


Project Management - 2.2

PROJECT INITIATION

1.Overview
 Project conception and
definition
 Project proposal
 Project feasibility study

SAV
SDC
Project Management - 2.3

2.Project costing
 Cost components
 Types of cost estimates
 Costing problems

3.Negotiation and contract strategy


 Contract strategy
 Negotiation

SAV
SDC
Project Management - 2.4

4.Risk management
 Framework
 Risk identification
 Risk classification
 Risk analysis
 Risk response
SAV
SDC
Project Management - 2.5

Required readings
Avraham, Chapter 10
Harvey A. Levine, Project Initiation
Techniques: A Strategic View.

CASE STUDY
Teloxy Engineering

SAV
SDC
Project Management - 2.6

Learning objectives
 After completing this lesson you should be
able to:
 List major issues that firms have to deal with
during project initiation/definition stage
 Discuss the main content of a project
proposal and major issues of the proposal
preparation process

SAV
SDC
Project Management - 2.7

 Discuss the purpose of a project


feasibility study
 List different schemes to classify
project cost components
 Discuss some major techniques
used to estimate project costs

SAV
SDC
Project Management - 2.8

 Explain a cost coding system and its


benefits
 Describe different types of contracts
and identify the major issues that a
contract strategy deals with
 Discuss when negotiation is needed ,
and issues project managers must
consider before starting a contract
negotiation.
SAV
SDC
Project Management - 2.9

List the negotiation principles for win-win


solutions

Compare and contrast risk with uncertainty

Define what is risk management and discuss


basic components in the risk management
framework

SAV
SDC
Project Management - 2.10

1. Overview

1.1 Conception
 Objectives: Collect and present
information to management in order
that a clear decision can be made
on the project concept.

SAV
SDC
Project Management - 2.11

 Usual steps:
 Identify the problems: increased
competition, reduction in profit or
market share
 Identify the opportunities: new
technology - new market - new
idea – new resources.

SAV
SDC
Project Management - 2.12

Identify the conditions/ constraints.


 Time constraint
 Technology constraint
 Personnel constraint
 Cultural constraint
 Money constraint

SAV
SDC
Project Management - 2.13

 Prioritize the needs.


 First grasp of solution approaches

SAV
SDC
Project Management - 2.14

 Development of initial concepts:


Techniques for developing &
generating new ideas.
 Research, survey, interview.
 Brainstorming.
 Concept paper for discussions.

SAV
SDC
Project Management - 2.15

Beyond perceiving the need, project initiation


requires proving that the idea has merit and
can be achieved at practical cost. To cull the
few good ideas, the organization undertakes
a brief initial investigation (preliminary
feasibility). During the initial investigation the
organization tries to clarify the problem and
evaluate the merit of solutions.
SAV
SDC
Project Management - 2.16

1.2 Project Definition

 Objectives: Produce an agreed


statement of what the project is
(Project Definition Report or Project
document) which will be the basis
for all project work.

SAV
SDC
Project Management - 2.17

 Project objectives:
 Identify the long-term goals.
 Identify the set of objectives.
Technical objectives
Timing objectives
Budget objectives
Scope guidelines

SAV
SDC
Project Management - 2.18

 Prioritize the objectives -


Identify the relationship of the
objectives.

SAV
SDC
Project Management - 2.19

 Project priority:
 Used to compare with other
competing project.
Based on many factors, ranging
from top management's preference
to the environmental impacts.
 Factors may change over time.

SAV
SDC
Project Management - 2.20

 Impacts:
 profit, market share, technological
competence, reputation
 Social impacts.

SAV
SDC
Project Management - 2.21

 Managerial aspects:
 Consistency with parent
organization’s goals and
strategies.
Predict potential/ conflicts,
changes.

SAV
SDC
Project Management - 2.22

If, after the initial investigation, the idea


is found to warrant a full-scale, detailed
investigation of the alternative solutions,
approval is given for the next stage,
feasibility

SAV
SDC
Project Management - 2.23

1.3 Project proposal

Written document presenting the


design & plan of the project
submitted for evaluation and
approval.

SAV
SDC
Project Management - 2.24

 Types of proposals:
 Internal proposal for approval
by top management.
External proposal for client to
offer some services/products

SAV
SDC
Project Management - 2.25

External proposals again have 2 kinds:


 Qualification proposal responds to client
request for proposal (in this case, the client
typically choose to bring in a contractor
who will carry the project feasibility study),
providing information on the company's
capability to carry out some work or to
provide some services/products.

SAV
SDC
Project Management - 2.26

 Commercial proposal involves commitment


from the authors (i.e. a contractor) of the
proposal. Examples includes bids for projects.
This kind of proposal - because of the
commitment involved - requires careful review,
planning and approval of top management
before sending out. This normally requires a
feasibility analysis by the bidder.

SAV
SDC
Project Management - 2.27

 Bid/No bid decision for commercial


proposal:
 Is the company capable to
complete the work?
 Is the company willing to do the
work?
 Is there a chance to win the bid?

SAV
SDC
Project Management - 2.28

- The commercial proposal preparation is


itself a project - with cost constraints, a
deadline for submittal, and performance
requirements - and it should be
managed like one.

SAV
SDC
Project Management - 2.29

 Who is responsible for preparing the


proposal?
 Proposal manager (normally project
designer)
Support proposal staff (normally from
marketing department, specially for
external proposals).

SAV
SDC
Project Management - 2.30

 Cooperation with staff/managers


from others functional departments.

SAV
SDC
Project Management - 2.31

 During the proposal preparation, the


contractor should establish a dialogue
with the user (client) to determine which
requirements are dominant among time,
cost and performance, and which
solutions the user prefers.

SAV
SDC
Project Management - 2.32

Even if the RFP is clear, there is need


to confer with the user about details
of scheduling, costing, specification
and so on.

SAV
SDC
Project Management - 2.33

1.4 Project Feasibility Study

 Feasibility study is the process of


investigating a problem and
developing a solution in sufficient
detail to determine if it is technically
feasible and economically viable and
worthy of development.
SAV
SDC
Project Management - 2.34

A feasibility study is documented with


a report showing all the ramifications
of the project

SAV
SDC
Project Management - 2.35

 Technical study:
The technical capability of the
personnel as well as the
capability of the alternative
technologies should be
considered

SAV
SDC
Project Management - 2.36

 Financial Study:
 What are the magnitude of the
capital and operating costs of the
project?
 What are the source of funds and
the draw-down schedule, and are
they sufficient to cover the costs of
activities and implementation?

SAV
SDC
Project Management - 2.37

 What is the projected cash flow of the


project? Do the benefits outweigh the
costs? To what extent is necessary
borrowing scheduled to meet running
deficits at activation?
 How soon do initial revenues come in
to take part or all of operating costs?

SAV
SDC
Project Management - 2.38

 Administrative/Managerial Study:
 What is the appropriate
organization?
 To whom the project manager
will report? What are his links
with existing functional and
project departments?

SAV
SDC
Project Management - 2.39

 What are the authority and


communication lines?
 Is there qualified key management
and technical personnel for the
success of the project? What is the
recruitment and training plan for the
project team?

SAV
SDC
Project Management - 2.40

 What are the external linkages


(funding agencies, clients, regulating
agencies, etc.)?
 What are the master schedules and
plans for the project?
 What are the systems for
monitoring, controlling the project
implementation?
SAV
SDC
Project Management - 2.41

 Does the plan provide for


contingencies?
 What are the standard for project
performance?

SAV
SDC
Project Management - 2.42

 Economic Study
This involves the feasibility of the
proposed project to generate
economic benefits.
 Can the project objectives be
justified in terms of organization's
strategic goals, or of the national
economic needs?
SAV
SDC
Project Management - 2.43

 Who are the main competitors,


and what is the anticipated
fluctuation of the supply and
demand which may influence the
performance and objectives of the
project?

SAV
SDC
Project Management - 2.44

 Environmental Study
 What will be the impact of the
project on the environment?
 What are the relevant regulations?

SAV
SDC
Project Management - 2.45

 Social/Political Study
 What are the project's likely social
and political impacts on the
community?
 What social, political and
institutional factors may hinder or
assist the project in achieving its
objectives?
SAV
SDC
Project Management - 2.46

 Recommendations:
 Modifications to improve the
project design
 Approve/Not approve the
proposed project (justify)

SAV
SDC
Project Management - 2.47

2. Project costing

2.1 Cost components


 Direct costs: costs attributed
directly to the job or piece of project
equipment.

SAV
SDC
Project Management - 2.48

 Indirect costs (overhead costs or


overhead): costs covering the
provision of factory & office
accommodation, general
management & administration,
heating/air conditioning, lighting,
maintenance, etc.

SAV
SDC
Project Management - 2.49

Notes :
Different interpretations by
companies on indirect/direct costs.
Both can be labor, materials or
expenses, it is always difficult to
estimate the indirect costs.

SAV
SDC
Project Management - 2.50

The reasons are the implicit nature


of the costs. Many projects may
also share the overhead, which
may further complicate the
calculation.

SAV
SDC
Project Management - 2.51

 Fixed costs: costs which remain


unchanged & must continue to be
incurred even though the workload
or production level may fluctuate
between zero & maximum capacity.

SAV
SDC
Project Management - 2.52

 Variable costs: costs incurred at rate


depending on the level of work
activity, usually confined to direct
costs.

 Prime cost: sum of all direct costs


needed to complete a particular job
or project.
SAV
SDC
Project Management - 2.53

 Factory cost: total direct plus


indirect costs needed to complete
the job or project

 Below-the-line costs: collective


name for the various allowances (for
cost escalation, exchange rate
fluctuation & other contingencies)
SAV
SDC
Project Management - 2.54

 Life-cycle cost: total cost to the


organization for the ownership and
acquisition of the product over its full
time. Life cycle cost may include :
 R & D: cost of feasibility study,
cost/benefit analysis, design pilot
production and testing,
documentation etc.

SAV
SDC
Project Management - 2.55

 Production/Construction:
manufacturing, assembly, testing,
materials, etc.
 Operating & maintenance, personnel,
spare parts, repairs, quality controls
 Product support, retirement & phase-
out

SAV
SDC
Project Management - 2.56

2.2 Types of cost estimates

 Order-of-magnitude: first rough


estimate based on past
experiences, scale & scope of the
project, or capacity estimates.

SAV
SDC
Project Management - 2.57

Common technique: using expert


opinions and statistics. Accuracy:
35%.
Example: $/m2 estimate for
construction.

SAV
SDC
Project Management - 2.58

 Comparative estimate, based on well-


outlined project design and similar
projects in the past.
Technique: using cost estimating
relationships such as Cost-
Capacity factor. It is expressed by
the following equation

SAV
SDC
Project Management - 2.59

x
 Q2 
C 2  C1  
 Q1 
where C1 = cost of an existing plant C2 =
cost estimate for a similar plant Q1 =
capacity of the existing plant
Q2 = capacity of the new plant, and. -
x = cost-capacity factor

SAV
SDC
Project Management - 2.60

The X are empirically derived


factors based on well-
documented historical records for
different kinds of projects.
Accuracy: 15-20%.

SAV
SDC
Project Management - 2.61

 Feasibility estimate: based on the


detailed project design (building
/construction specification, site
data, provisional layouts,
drawings), quotations for major
project equipment's & subcontracts.

SAV
SDC
Project Management - 2.62

Technique: Work breakdown


structure (WBS) and Cost
breakdown structure (CBS).
Accuracy 10%.

SAV
SDC
Project Management - 2.63

 Definitive estimate : when most


design work has been finished, all
major purchase orders have been
placed at known prices.

Accuracy: 5%.

SAV
SDC
Project Management - 2.64

Notes :
(i) Learning curve:
A principle in cost estimating
based on the fact that skill and
productivity in performing tasks
improve with experience &
practice.

SAV
SDC
Project Management - 2.65

The rule of thumb: Human performance


improves by a fixed percentage each
time production doubles.
Formula: Tn = T0nr
Where:
Tn = time required for the n-th unit T0 =
time requirement for the initial
unit

SAV
SDC
Project Management - 2.66

n =number of units
r = log (fixed percentage) / log 2

Example: In aerospace industry ,


where the production is in batches,
the unit production cost is reduced
by about 20% every batch..

SAV
SDC
A learning curve
Project Management - 2.68

(ii) Work breakdown:


Process of breaking the whole project
successively into smaller units until all
meaningful tasks have been identified
and the cost of each task can be
individually estimated. The work
breakdown structure will be basis for the
cost breakdown structure (cost coding)
and budget.

SAV
SDC
Project Management - 2.69

Cost coding: System assigning to each


task of the work breakdown structure
(WBS) a number which can convey
essential data about the task. A code
may consists of several identifiers:
project identifier, item identifier,
operation identifier, etc.

SAV
SDC
Project Management - 2.70

Benefit of cost coding:


 facilitate analysis, editing and
reporting;
 facilitate the application of
computers in project
management.

SAV
SDC
Project Management - 2.71

An effective coding system must be


 Clear and logical
 Exhaustive
 Consistent
 in company
 in industry

SAV
SDC
Project Management - 2.72

2.3 Costing problems:

 Cost escalation: amount of


expenses over run the budgeted
cost estimate.

SAV
SDC
Project Management - 2.73

Cost escalation of up to 20% are


quite common with most
projects.

Large, complex, high technology


projects have greater potential
for escalation

SAV
SDC
Project Management - 2.74

 Following are the reasons – some


are avoidable, some are not:
Uncertainty and lack of accurate
information
Changes in design or
requirements

SAV
SDC
Project Management - 2.75

 Economic and social variables


in the environment
 Work inefficiency, poor
communication, and lack of
control
 Kind of project contract

SAV
SDC
Project Management - 2.76

3. Contract Strategy and Negotiation


3.1 Contract Strategy
 Contract:
A contract is an agreement between
two parties wherein one party (the
contractor) obligates itself to perform
a service, and the other party (the
client) obligates itself to do something
in return – typically make a payment.

SAV
SDC
Project Management - 2.77

Most project contracts are


written documents
Can contain unilateral or
bilateral agreement

SAV
SDC
Project Management - 2.78

 Different kinds of contract provides


different advantages to the client and
the contractor. Depending on the risk
of the project and the degree of
difficulty in estimating costs, the client
and contractor try to negotiate the
type of contract that best serves their
own interests.
SAV
SDC
Project Management - 2.79

 Two fundamental types of contracts:


Fixed price contract: the price is
agreed upon and remains fixed as
long as there are no changes to the
scope or provisions of the agreement

SAV
SDC
Project Management - 2.80

Cost reimbursable contract: the


contractor is reimbursed for all of the
expenses incurred during the
performance of the contract, so as the
result, the final price is unknown until
the project is completed.

SAV
SDC
Project Management - 2.81

Fixed price contract

Firm fixed price contract


(“Lump sum” agreement)
 The contractor agrees to perform all
work at a fixed price.

SAV
SDC
Project Management - 2.82

 When a project is readily specified in


details, this type of contract is preferred
by both contractor and client.

SAV
SDC
Project Management - 2.83

Client’s viewpoint: less need to


supervise the project
Contractor’s viewpoint: clients are less
likely to request changes or additions to
the contract.

SAV
SDC
Project Management - 2.84

Disadvantages:
 more difficult and costly to prepare
some incentives for the contractor
to use cheaper materials, perform
marginal workmanship, etc.
 the contractor may run the risk of
underestimating

SAV
SDC
Project Management - 2.85

Fixed price with redetermination


 The initial price is negotiated
with the stipulation that it will be
re-determined at intervals so that
the price can be based upon
actual cost data.

SAV
SDC
Project Management - 2.86

 This type of contract is appropriate


where: engineering and design efforts
are difficult to estimate, in long-term
quantity production contracts

SAV
SDC
Project Management - 2.87

Disadvantages:
The only requirement to renegotiate
the price is substantiating cost
data, therefore this type of
contracts tends to induce
inefficiencies.

SAV
SDC
Project Management - 2.88

Fixed price with escalation provisions


Contracts with long lead time
may have escalation provisions.
For example, the price may be
tied to an inflation index so it can
be adjusted in the advent of
inflation.
SAV
SDC
Project Management - 2.89

Fixed price with incentives


 The contractor negotiates to perform
the work for a target price based upon a
target cost plus target profit. A ceiling
price and a ceiling profit are also
negotiated.

SAV
SDC
Project Management - 2.90

 If the total cost ends up being less than


the target cost, the contract make a
higher profit up to the ceiling profit. If
cost overrun, the contractor absorbs
some of the overrun until a profit floor is
reached.

SAV
SDC
Project Management - 2.91

 This type of contracts applies to long


term or large production projects. It is
not applicable to projects where the
target cost is difficult to estimate.

SAV
SDC
Project Management - 2.92

 This type of contract alleviates some of


disadvantages to the client of a fixed
price contract because it stimulates the
contractor to reduce costs and improve
efficiency.

SAV
SDC
Project Management - 2.93

Disadvantages:
It invites contractors to negotiate
unrealistically high target cost so
that extra profits can be made.

SAV
SDC
Project Management - 2.94

Cost reimbursement contracts


Normally applied when requirements
are uncertain, and it is impractical to
expect the contractor to assume the
risks without providing extensive
contingencies. A fee is usually added
contingent on satisfactory
performance.
SAV
SDC
Project Management - 2.95

Cost plus fixed fee (CPFF)

The contractor is reimbursed for


all direct allowable costs plus an
additional fixed amount to cover
overhead and profit.

SAV
SDC
Project Management - 2.96

This type of contracts puts the burden of


risk on the client.

There is little incentives for the


contractor to control costs, finish on
time or do anything beyond minimum
requirements.

SAV
SDC
Project Management - 2.97

Cost plus incentive fee

 This is similar to CPFF in that


costs are reimbursed, but fee is
based on an incentive formula.

SAV
SDC
Project Management - 2.98

 The contract starts with a specified


target cost, and guarantees a maximum
or minimum fee which is the percentage
of the actual cost. Maximum fees
establish the outside limits on a
contractor’s profit.

SAV
SDC
Project Management - 2.99

Time and Materials Contract

 A simple form of agreement that


reimburses the contractor for
labour costs and materials as
incurred.

SAV
SDC
Project Management - 2.100

 It provides for payment of direct labour


hours at an hourly rate which include
the direct labour cost, indirect costs,
and profit.

SAV
SDC
Project Management - 2.101

 Charges for services such as


electricians, carpenters, etc. are usually
based on time and materials.

SAV
SDC
Project Management - 2.102

 Contract Strategy deals with


 division of the project into
separate contracts
 the timing of contract awards

SAV
SDC
Project Management - 2.103

 the type of the contract most


likely to encourage satisfactory
completion while providing
controls and opportunities to the
owners to rectify problems before
they cause serious difficulty to
the project
SAV
SDC
Project Management - 2.104

3.2 Contract Negotiation

 Negotiation is a dynamic process in


which parties with differing objectives
reach an acceptable agreement on a
matter of common interest through a
process of communication and
compromise.
SAV
SDC
Project Management - 2.105

 The purpose of negotiation is to identify


completely to the satisfaction of all the
parties the scope of the work to be
done, to clarify technical or other terms
in the contract and to reach agreement
on time, schedule, and performance
obligations.

SAV
SDC
Project Management - 2.106

 On-going negotiations improves


communication and helps the client and
contractor reach mutual understanding
and expectations about the jobs.

SAV
SDC
Project Management - 2.107

 Final negotiation before a


contractual agreement is reached
is the last opportunity to correct
mis-perceptions which might
have slipped through the RFP
and the proposal process.

SAV
SDC
Project Management - 2.108

When negotiation is needed?

Negotiation is not necessary on


standardized items for which terms are
simple and cost are fairly well known.

SAV
SDC
Project Management - 2.109

Negotiation is commonplace on
complex system which requires
much development work and
involve considerable uncertainty.

SAV
SDC
Project Management - 2.110

Even if there is a free tendering


process, and the selection of the future
contractor is made according to the
established rules, negotiation between
the client and the contractor is still
needed.

SAV
SDC
Project Management - 2.111

The negotiation principles for win-win


solutions

Separate the people from the problem


The conflicting parties are often highly
emotional. To minimize the likelihood that the
conflict will become strictly inter-personal, the
negotiators should:

SAV
SDC
Project Management - 2.112

 Define carefully the substantive


problem
 Put oneself in the other parties’
position to see the situation from their
point of view and to recognize and
understand their emotions.

SAV
SDC
Project Management - 2.113

Focus on interests, not positions


 The goals of the parties usually
can be reasonable reconciled so
that both parties win.

SAV
SDC
Project Management - 2.114

 To accomplish this, the negotiators


should not be committed to specific
positions and defend those position
without examining other ways of
achieving the overriding goals.

SAV
SDC
Project Management - 2.115

 Knowledge of the other party’s


underlying concern allows a negotiator
to suggest solutions that satisfy both
parties’ interests without agreeing with
the other’s position.

SAV
SDC
Project Management - 2.116

Generate creative options prior to


begin negotiation
 As soon as the substantive
problems are spelled out, effort
should be devoted to finding a
wide variety of possible solutions

SAV
SDC
Project Management - 2.117

 Solutions that advance the shared


interests of the conflicting parties can
be presented and the preferences of the
other party can be solicited.

SAV
SDC
Project Management - 2.118

Insist that results be based on some


objective criteria
The best way to resolve the
remaining conflicts is to base the
solution on an objective standard
(industry practice, allocation of risk
based on investment, etc. ) rather
than the will of the parties involved.
SAV
SDC
Project Management - 2.119

Analysis of negotiation situation


To be in the most knowledgeable and
competitive position, the project
manager must
Learn about the client to determine,
for example, if the client

SAV
SDC
Project Management - 2.120

 Is under pressure to make a


particular decision
 Needs a system as soon as
possible
 Has historically shown a
preference for one particular
approach over the others

SAV
SDC
Project Management - 2.121

Learn about the competitors


 Their likely approach, costs,
competitive advantages and
disadvantages Information can be
derived from historical data of past
projects, published materials, etc.

SAV
SDC
Project Management - 2.122

To be able to negotiate trade-offs, the


project manager must be intimately
familiar with the technical details of the
design, related costs and the project
schedule and time-cost tradeoffs.

SAV
SDC
Project Management - 2.123

4. Risk Management
4.1 Risk Management framework
 Definition
Risk management is an organized
means of identifying and measuring
risk and developing, selecting, and
managing options for handling these
risks.

SAV
SDC
Project Management - 2.124

Risk management, in the project


context, is the art and science of
identifying, analyzing, and responding to
risk factors throughout the life of a
project and in the best interest of its
objectives

SAV
SDC
Project Management - 2.125

Risk and uncertainty

 Risk and uncertainty characterize


situations where the actual outcome for
a particular event or activity is likely to
deviate from the estimate or forecast
value.

SAV
SDC
Project Management - 2.126

 Risk arises when it is possible to make a


statistical assessment of the probability
of occurrence of a particular event.

 In decision making under risk, there are


assigned probabilities for each of the
states of nature.

SAV
SDC
Project Management - 2.127

 Under uncertainty meaningful assignment


of probabilities are nonexistent.

 Hence, the difference between risk and


uncertainty is a knowledge of the
probability of occurrence of each state of
nature.

SAV
SDC
Project Management - 2.128

Example:
A company wishing to invest $50 million
to develop a new product. The company
has three design options: A, B, and C.
The company decides that the states of
nature will be either: a strong market
demand, an average market demand or
a low market demand.
SAV
SDC
Project Management - 2.129

The company has determine the


following the payoff table for this
development project.

SAV
SDC
Project Management - 2.130

Payoff table (Profit in millions)


Design States of Nature (Probability of
strategy occurrence)
Strong Average Low (50%)
(25%) (25%)
A $50 $40 $90
B $50 $50 $60
C $100 $80 $-50

SAV
SDC
The best choice of strategy is design A.
( Id e n t if y s o u r c e & t y p e
R is k Id e n tific a tio n
o f r is k )

(T y p e o f r is k a n d its
R is k C la s s ific a tio n
e ffe c ts )

(E v a lu a te c o n s e q u e n c e
R is k A n a ly s is & im p a c t o f r is k )

R is k A ttitu d e

(A ttitu d e o f p e o p le
in v o lv e d )

R is k R e s p o n s e (H o w r is k s h o u ld b e
h a n d le d )

R is k M a n a g e m e n t
Project Management - 2.132

4.2 Risk Identification and Classification

 The first step in risk management is to


identify and assess all potential risk areas.
The thoroughness with which this
identification is accomplished determine the
effectiveness of risk management.

SAV
SDC
Project Management - 2.133

 Not all risks are high-level risks that will


have a critical impact on a project.
However, the cumulative effect of
combining low-level risks could have a
severe impact.
 It is useful to work closely with the project
team and to consider explicitly these areas

SAV
SDC
Project Management - 2.134

 Risks internal to the project


 Non technical: labor stoppages,
safety issues, cash flow problem
 Technical: change in technology,
design issues, operation/maintenance
issues (unproven technologies,
inadequate logistic support, etc.)

SAV
SDC
Project Management - 2.135

 Legal: subcontractor performance,


patent rights, licenses, etc.
 Risks external to the project
 Government regulations, natural
hazards, etc.
 Borrowing rates, raw material
availability

SAV
SDC
Project Management - 2.136

Principle sources of risks

Physical
Loss or damage by fire,
earthquake, flood, accident, land
slip

SAV
SDC
Project Management - 2.137

Environmental
Ecological damage, pollution,
waste treatment
Public enquiry

SAV
SDC
Project Management - 2.138

Design
New technology, innovative
applications, reliability, safety
Detail precision and
appropriateness of specifications
Design risk arising from surveys,
investigations
SAV
SDC
Project Management - 2.139

Likelihood of change
Interaction of design with method
of construction

SAV
SDC
Project Management - 2.140

Logistical
Loss or damage in the transportation of
materials and equipment
Availability of specialized resources -
expertise, designers, contrattors,
suppliers, plant, scarce construction
skills, materials

SAV
SDC
Project Management - 2.141

Access and communications


Organizational interfaces

SAV
SDC
Project Management - 2.142

Financial
Availability of funds, adequacy of insurance
Adequate provision of cash flow
Losses due to default of contractors,
suppliers
Exchange rate fluctuations, inflation
Taxation

SAV
SDC
Project Management - 2.143

Legal
Liabilities for acts of others, direct
liabilities.
Local law, legal differences between
home country and home countries of
suppliers, contractors, designers

SAV
SDC
Project Management - 2.144

Political
Political risks in countries of owner
and suppliers, contractors - war,
revolution,
changes in law

SAV
SDC
Project Management - 2.145

Constructional
Feasibility of construction methods, safety
Industrial relations
Extent of change
Climate
Quality and availability of management
and supervision

SAV
SDC
Project Management - 2.146

Operational
Fluctuations in market demand or
product or service
Maintenance needs
Fitness for purpose
Safety of operation

SAV
SDC
R is k C la s s ific a tio n

C o n s e q u e n c e o f r is k T y p e o f r is k Im p a c t o f r is k

P u r e ris k S p e c u la tiv e r is k com pany M a rk e t/


( s p e c if ic r is k ) (m a r k e t ris k ) In d u s t r y
- N o p o t e n tia l g a in - P o s s ib ility lo s t E n v iro n m e n t P ro je c t/
o r g a in In d iv id u a l

F r e q u e n c y S e v e r it y / P r e d ic ta b ilit y A s s e t re la te d o r C a p ita l r e la te d
Im p a c t b u s in e s s r is k o r f in a n c ia l r is k
Project Management - 2.148

 Any sources of information that allows


recognition of a potential problem can
be used for risk identification. These
include
 System engineering documentation
 Life cycle cost analysis
 Work breakdown structure

SAV
SDC
Project Management - 2.149

 Brainstorming
 Past projects Lessons

SAV
SDC
Project Management - 2.150

4.3 Risk analysis

 Attempt to capture all feasible options


and to analyze the various outcomes of
any decision.

SAV
SDC
Project Management - 2.151

 The impact of a risk can be quantified


as follows

Impact of a risk = Probability of risk


x Consequence of risk

SAV
SDC
Project Management - 2.152

 Describing and quantifying a specific risk


and the magnitude of that risk usually
require some modeling. Typical methods
for use in risk analysis are:

Decision Analysis
Probability Matrix
Decision Tree

SAV
SDC
Project Management - 2.153

Sensitivity Analysis
Sensitivity table
Spider diagram

SAV
SDC
Project Management - 2.154

Simulation (Monte Carlo)


Scenario Analysis

SAV
SDC
Project Management - 2.155

Risk Attitude:

Risk loving: prefer to accept risk


even when the expected
(monetary) benefit is negative

SAV
SDC
Project Management - 2.156

Risk averse: is unwilling to accept


risk even when the expected
benefits is positive
Risk neutral: base the decision on
the expected benefit

SAV
SDC
Project Management - 2.157

Note: Risk attitude differs from one


person to another person. Even for a
person, the risk attitude may vary
depending on the nature and magnitude
of the risks and benefits involved as
well as other internal and external
factors.

SAV
SDC
Project Management - 2.158

4.4 Risk Response

 The techniques for handling risk fall into


the following categories
 Avoidance
 Reduction (or Mitigation)
 Retention
 Transfer

SAV
SDC
Project Management - 2.159

 Fundamental considerations which


govern the allocation of risk

 Who can best control the source


of the risk
 Who can best manage the risk if
is occurs

SAV
SDC
Project Management - 2.160

 Is it preferable to retain an
involvement in the management of
risk
 Who should carry the risk if it is
not controlled
 Whether the risk premium is
reasonable and acceptable

SAV
SDC
Project Management - 2.161

 Is the transferee likely to be able


to sustain the consequence of risk
 If the risk is transferred, whether it
leads to the possibility of risks of
different nature being transferred
back

SAV
SDC
Project Management - 2.162

Risk transfer:

 Project manager transfers all or part of


a risk(s) to another party by some form
of contract.

SAV
SDC
Project Management - 2.163

 Insurance
The type of contract (will determine
how the risk is shared between the
customer and the contractor)

SAV
SDC
Project Management - 2.164

Remark: Risk transfer does not


reduce the criticality of the source
of risk. In some cases, risk transfer
even increases the risk (e.g. when
the receiving party is not aware of
the risk, or is not capable of
absorbing the risk).

SAV
SDC
Project Management - 2.165

Risk Retention:

Acknowledgement of the existence


of risk but decide to accept the
consequences if failure occurs.
Usually accompanied by some
contingency budget

SAV
SDC
Project Management - 2.166

Risk Reduction
By redesign the project
By training and education
By a process of continually sensing
the condition of a project and
developing options to permit
alternative lower-risk solutions.

SAV
SDC
Project Management - 2.167

Example of risk control options:


process of developing alternative
sources for production, parallel
development for a critical research
and design component, getting
priority for critical materials, etc.

SAV
SDC
Project Management - 2.168

Risk avoidance:
Avoid to accept the option which
have the potentially unfavorable
results.
Usually achieved by use of
exemption clauses in the contrac

SAV
SDC
Event-Likelihood of damage to adjoining
buildings as a result of pile driving

Improbable Rare Possible Probable Very likely


Severity
Negligible Retain Retain Retain Retain Retain
Small Retain Retain Partial Partial Partial
Insurance Insurance Insurance
Moderate Retain Partial Insure Insure Insure
Insurance
Large Insure Insure Insure Insure Insure
Disastrous Insure Insure Cease Cease Cease
activity activity activity
Project Management - 2.170

Potential for systematic Risk Management

 Identification: develop checklist based


on experience :
* Some are common to all
* Some are unique to some projects

SAV
SDC
Project Management - 2.171

 Classification:
* Risks for which past data are available
* Risks that would be accepted by insurance
companies
* Risks where expert-based judgments are
possible
* Warning: A risk is not irrelevant simply
because there are no data regarding its
extent !

SAV
SDC
Project Management - 2.172

 Risk analysis: For each type of risk


factors !
 Response:
* Avoidance: Stop the tender or
proceed with only a part of the
project

SAV
SDC
Project Management - 2.173

* Retention: Make some financial or


other contingency for the risks
(quantitative methods may be used !)

SAV
SDC
Project Management - 2.174

5. Project Financing

 Definition:
Way of financing a project where
the lenders look mainly to
Earnings of the project as source
of fund for loan repayment
Assets of the project as collateral

SAV
SDC
Project Management - 2.175

 Why opting for project finance


New financing opportunities
Off-balance sheet borrowing:
arranging loan for a project without
affecting the sponsor’s credit
standing or balance sheet

SAV
SDC
Project Management - 2.176

Risk sharing: where debts is wholly


or partially non-recourse to the
sponsor all or some of the risks will
be borne by the lenders if the
project fails to produce sufficient
cash flow.

SAV
SDC
Project Management - 2.177

 Types of capital and debt

 Equity risk capital in the project,


with last priority in payment

SAV
SDC
Project Management - 2.178

 Lenders usually require equity investment


 to reduce the debt burden on the
project cash flow
 to ensure that project sponsors have
enough at stake and hence they are
motivated to see the project through a
successful completion

SAV
SDC
Project Management - 2.179

 Quasi equity: subordinated loans


Senior to equity but still have lower
priority in repayment than other
debts

SAV
SDC
Project Management - 2.180

 Senior debt: Debt which is not subordinated


to any other liability
 Unsecured loans: backed only by the
general credit of the borrower and is not
secured by any asset
 Secured loans: where assets securing
the debt have value as collateral
(marketable and readily converted to
cash)

SAV
SDC
Project Management - 2.181

 Example of common types of project


financing
Build-Operate-Transfer (BOT)
Most popular form for funding infrastructure
projects
A private group invests in, construct, and
operate a facility for a concession period.
The investment is repaid during this period

SAV
SDC
Project Management - 2.182

At the end of the concession period,


the facility is transferred free of
charge to the host country
government

SAV
SDC
Project Management - 2.183

Major advantages:
- Reduce public spending
- Increase efficiency (through
privatization)

SAV
SDC
Project Management - 2.184

Major disadvantage:
Financing structure is highly
complex, resulting in a very long
and expensive negotiation phase

SAV
SDC
Project Management - 2.185

 Build-Own-Operate
The ownership of the facility is
retained in perpetuity by the private
developer.

SAV
SDC

You might also like