- All the end of the works you shall send us a list of the remaining free-
issue materials. And the remaining pressure parts materials shall have
punched at least the heat number, the grade of material and the
diameter and thickness.
Progress and current status in percentage
Factor Weighted factor
ENGINEERING (Design drawing) 5%
ENGINEERING (Workshop drawing) 5%
MATERIAL (ORDERED & RECEIPT) 15%
MATERIAL (Free-Issue) 5%
PRODUCTION 55%
TEST & INSPECTION 10%
CARGO READINESS & EX-WORK 5%
OVERALL 100%
Project management

- Management is the technique of understanding the


problems, needs and controlling the use of Resources,
Cost, Scope and Quality.
Project management
• Resource
1. Manpower: Make mobilize manpower schedule for the project with
clear classification and number of them.
2. Equipment & Tool: Make File Control Sheet of all equipment & tool
for this project and make sure that they can proceed without delay:
maintenance, calibration, …
Note: All welding equipment, including wire feeder or powder feed
units, shall calibrated prior to use. Contractor shall check the
calibration on a regular basis during production.
Project management
• Time
1. Work Plan: Make overall project schedule and S-cure for overall and
S-cure for fabrication schedule.
Project management
• Quality
Make sure that quality assurance procedure according to Project
procedure.
Welding Note
• Low hydrogen, non-vacuum packed SMAW consumables shall dried
and stored in ovens prior to issue to ensure that they are capable of
meeting a maximum hydrogen level of 10ml H2/100g weld metal
prior to commencing welding.
• FCAW wires shall be stored in accordance with the consumable
manufacturer’s recommendation to ensure that they are capable of
meeting a maximum hydrogen level of 10ml H2/100g weld metal
prior to commencing welding
• SAW fluxes is capable of meeting a maximum hydrogen level of 10 ml
H2/ 100g weld metal prior to commencing welding.
Welding Note
• The warehouse shall be dry, air temperature inside warehouse shall
be 15 độ minimum and relative humidity 60% maximum.
• FCAW wires shall be stored in accordance with the consumable
manufacturer’s recommendation to ensure that they are capable of
meeting a maximum hydrogen level of 10ml H2/100g weld metal
prior to commencing welding
• SAW fluxes is capable of meeting a maximum hydrogen level of 10 ml
H2/ 100g weld metal prior to commencing welding.
• Arc Air operator shall be properly trained and have current
experience.