GROUP 2
DAPHNE TAN 0329055
ERIC WEE 0329601
FOO VAN JEAN 0330017
FOO ZHI FUNG 0320226
At present, you are working in a quantity surveying consulting firm and assigned
to be in-charge of a 20 storey condominium project in Penang. The project owner wishes
to understand about Employer’s, Architect’s and Consultant Quantity Surveyor’s
obligations in the contract provisions under PAM Form of Contract 2006 (with
Quantities) and seeks your professional advice for the following scenario for the project.
You are to make references to the relevant clauses (if any) under the PAM Form of
Contract 2006 (with Quantities)
(Part A & B)
Variation
(Part C)
Prime Cost Sum
A) Advice the Employer on the Architect’s authority in issuing an Architect’s Instruction (AI) that would
constitute variations as provided in PAM Form of Contract 2006 (with Quantities).
Clause 2.2 – All instructions issued by the Architect shall be in writing expressly entitled
“Architect’s Instruction” (AI). All other forms of written instructions including drawings issued by
the Architect shall be an AI.
Example:
The contractor is given the work of excavating in soft soil. While excavating they
come across hard rock.
Submit a variation of excavating the hard rock as the original work order mentioned
only soft soil.
Varies in….
Yes Yes No
Yes No No
Clause 11.6(b)
The rates in the Contract Bills shall be the basis of valuation, with inclusion of a fair
adjustment in the rates to take into account some cost differences.
B) Variation with Quantities
Clause 11.5 sets out the rules for valuation of Variations and of work executed under
provisional sum by the Contractor.
(i) The changes should be quantified by measuring the “omissions” and the “additions” from
the drawings.
(ii) Where changes are very substantial with total remeasurement of the works, the Q.S and
the Contractor should agree on the set of drawings to be used.
Q.S’ duty :
(a) Q.S’ name, company, time of arrival and
• Recording of site information and Site departure in the site visitor’s book.
measurement assisted by the Contractor.
• I.e: To verify the ground to be excavated, and (b) Ensure that all measurements taken are
properly recorded with date of the
examine the plant/equipment used are measurement.
appropriate for the site condition.
(c) Contractor’s initial.
B) The Contractor has submitted a list of work with time sheets which he alleges were done on day work basis.
Describe with examples of how the evaluation of the above variations would be carried out.
Daywork Contractor
+
Specifically instructed work
A mark up for
on the basis of the cost of
overheads and profit.
labour, materials and plant.
Address of site
B) Daywork
Lift Installation
• As a lump sum.
• a percentage addition,
• Included within profit and overheads allowance.
General attendance Special Attendance
A wide range of services and facilities provided by the Any item or services requested by the sub-contractor
main contractor on the construction site to all sub- or supplier to be provided by the main contractor in
contractors and or suppliers. However, charges for the order to complete his work.
use of such services or facilities are being deducted
from the main contractor’s payment to the
beneficiaries
For examples of general attendance are: hoisting For example a main contractor obtains a quotation
plant, mobile scaffolding, provision of storage space, from a sub-contractor to install external ‘signage’ to a
welfare facilities among others. building, however the quotation excludes cradles and
mobile cranes which are required for the installation
and completion of the work. In this case, ‘the cradle’
and the mobile crane’ constitute the main contractor’s
special attendance
thank you.