Proposal for ZTE

Smart Partnership
UM New Site Project

Prepared by: Isarlizam Bin Ramli


Date: 26 July 2017
• Objective
• Resources Planning( UM Forecast PO Q4 2017 & Q1
2018 _ PO5:30 Sites & PO6:35 Sites)
• N Wave Organization Structure
• Forecast Project Timeline For East Coast (65 Sites)
• Project Timeline Dependencies & Risk
• Summary Of Existing Business
Objectives

• ES for TSS , TSSR , LOS Survey & LOS Report for ( 65 Sites and Hops )
OKV (East Coast)
• ES For TI eNode B & Mw for ( 65 Sites and Hops )
OKV (East Coast)
• ES for SSV & SSO ( 65 Sites )
OKV (East Coast)
Resources Planning (for 65 Sites)
• 1 Project Manager
• 1 Implementation Manager
• 1 Project Coordinator
• 2 Site Engineer
• 2 Site Surveyor
• 2 Frequency Scanning Team
• 4 Installation Team ( 4 Person each )
• 1 RF Manager
• 1 DTA & 1 DTE Coordinator
• 2 DTA – Generating reports
• 4 DTE – For drive test
• 4 Drivers for DTE
• 2 Documentation Controller
N Wave Organization Structure
Country Manager

Sales Manager

Operation Director

Project Manager
Project Coordinator RF Manager
Documentation
Controller A

Documentation Implementation
DTA Coordinator DTE Coordinator
Controller B Manager

DTA A DTA B DTE A


Site Surveyor Site Engineer A Site Engineer B
A
DTE B
Site Surveyor
B TI Team A.1 TI Team A.2 TI Team B.1 TI Team B.2
DTE C
FS Team A
DTE D

FS Team B
Forecast Project
Timeline For East
Coast Region (65 Sites)

PO U Mobile 2017 Q4 Forecast


UM PO5 Issuance Plan : End Aug 2017
UM PO6 Issuance Propose : End Sept 2017
Forecast PO5 EQ Arrival Forecast PO6 EQ Arrival
( Week 43 ) ( Week 49 )
Project Timeline Dependencies

• All the project timeline depends on:-


 Site CME readiness
 Site Access
 TSSR & LOS Report Approval
 RF Parameters & Script readiness
 Equipment & Material Readiness For Delivery
 Weather
 ZTE Back end support ( RAN , Mw , Transmission )
 Backbone Transmission Network Capacity Readiness

• All the plan and schedule subject to change from time to time depends on the project activities or
based on key milestone completion.
Thank you so much for your cooperation and consideration.
Proposal for ZTE
Smart Partnership
UM New Site East Coast
Project

Prepared by: Isarlizam Bin Ramli


Date: 26 July 2017