Professional Documents
Culture Documents
Port Facilities
By:
Susantha Abeysiriwardana
M.Sc.(Marine Technology), C.Eng., B.Sc.(Hongs), MIE(SL)
Project Director (Colombo Port Expansion Project) /
Chief Engineer (Planning and Development)
Sri Lanka Ports Authority
1 susantha@slpa.lk
Out Line
1. Introduction
2. Port Planning
3. Design and Development
4. Layout / Port Operation
5. Construction Breakwater, Quay Wall and Jetties
6. Dredging and Handling Dredging Material
7. Other Projects
2
1. Introduction
Port
A port is a location on a coast or shore containing one or
more harbors where ships can dock and transfer people or cargo to
or from land. Port locations are selected to optimize access to land
and navigable water, for commercial demand, and for shelter from
wind and waves.
3
SLPA
LOGO
Ports
Port of Kanakasanthurei
Port of Trincomalee
Port of Oluvil
Port of Colombo
M.T. ('000)
6,000
50,000
5,000 40,000
30,000
4,000
NO. OF SHIPS
20,000
3,000 10,000
0
2,000 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
M.T('000) 34,52 39,42 43,50 47,96 46,37 58,76 62,01 61,70 63,48 70,79 73,71
1,000 YEAR
0
200
5
200
6
200
7
200
8
200
9
201
0
201
1
201
2
201
3
201
4
201
5
Total Tonnage
NO. OF
3,92 4,22 4,32 4,42 4,11 3,91 4,12 3,87 3,66 3,74 4,19
YEAR CONTAINER THROUGHPUT (TEUs '000) - PORT OF
SHIPS
COLOMBO
6,000
3,000
2,000
1,000
0
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
TEUs('000) 2,455 3,079 3,381 3,687 3,464 4,137 4,263 4,187 4,306 4,908 5,185
YEAR
Container Throughput
Unconstrained Colombo Forecast (TEU )
• Currently more
than 12% of all
containers
handled at ISC
ports
(IND+BGD+PAK)
are transhipped
at Colombo.
• Strong
economic
growth in the
ISC region is
projected to
support future
growth in
Colombo
transhipment
7
Container handling forecast of Port of Colombo in each terminal
Development of East Container Terminal
• Total capacity at Colombo is currently projected to reach 7.1 million TEU in 2016
• Utilisation levels above 100% are forecast beyond 2017
9
National Port Master plan
National Policy
Vision of the sector
Strategy of Sri Lankan Port
Direction of SLPA restructuring among others,
Future cargo estimation of the nation
target market
Trade facilitation
WCT Extension
3
4
WCT
ECT JCT I & II Deepening
JCT IV extension 35
7.1Million
14
11 MillionTEU
TEU
5 YEAR PLAN
15 YEAR PLAN
Maritime Centre
30 YEAR PLAN
Port of Galle Short Term Plan
Ship Repair
Workshop
Yacht
Marina
Phase - 1
Yacht
Marina
Phase - 2
Yacht Marina
Phase - 3
Port
Development
Project
Hotel Project
New Business
Dockyard,
Ship repair facility
Cargo increase – Coal – for
Norochcholai and clinker
4.Port of Oluvil
Coastal erosion
Northern side of Port
approx. 2.5 km coastal length.
Sand siltation
southern side of port.
port entrance channel.
Discussions to Handover Fishery
harbour to Fishery Habour
Coorperation.
5 LOGO
Hambantota Port Development Project
To be Acquired and
To be Acquired
Compensate Rs 2b
Colombo Kataragama
Future
Plan
New Road
Tank Farm
Phase-II
Current Snapshot of Hambantota Port
Phase-I
Dockyard
and Ship
Building
85 ha
Industrial Container
Zone (CT) Terminal Tank Farm
Expansion 61 ha
Industrial
Zone Multipurpo
se Berth
Conventional Cargo
Operation
30 ha
5 YEAR PLAN
15 YEAR PLAN
Ro-Ro Operation
25 ha
Artificial Island
42 ha
6. Port of Kankasanthurai
Total
Ships 34
KKS PORT CURRENT STATUS
Arrived 32 -5.9
20
3. Design and Development
Definitions
Breakwaters
Breakwaters are structures constructed on coasts as part of coastal
defense or to protect an anchorage from the effects of both weather
and long shore drift.
Quay wall
a landing place, especially one of solid masonry, constructed along
the edge of a body of water; wharf.
Jetties
any of a variety of structures used in river, dock,
and maritime works that are generally carried out in pairs from river
banks, or in continuation of river channels at their outlets into deep
water; or out into docks, and outside their entrances; or for
forming basins along the coast for
21 ports in tide less seas.
COLOMBO PORT EXPANSION PROJECT
22
MAJOR CONSTRUCTION WORKS
CPEP Infrastructural Development
– Site Preparation
– Lop Construction
– Break Water Construction
– Quarry Operation
– Dredging & Reclamation
– Armour Unit Construction
– Relocation Of Oil Pipe Line
– Road Network
23
PROJECT FEATURES
Date of Commencement : 11th April 2008
Target Date of Completion : 10th April 2012
Estimated Cost : Rs 36,355,198,496/=
Funded By - ADB & SLPA
Consultant - Scott Wilson Ltd.
Contractor - Hyundai Engineering & Construction ltd.
Break Water Building
MBW length :5.14km Pilot Station/ Port Control Tower : 530 m2
SBW length :1.10km Crew Accommodation Building : 2000 m2
Terminals (3nos) Basin
length :1.2km Depth -18.0 (LWOST)
width :0.480km Area - 260 Ha.
No. of berths :3 nos
Dredging
Access channel
width : 570m Volume – 15.5 million Cu m
Depth : 20.0 m
Internal roads
6 lanes Length : 0.6 km
4 lanes Length : 1.4 km
2 lanes Length : 2.0 km
Width of lane : 3.7 m 24
CONSTRUCTION MILESTONES Colombo port
Expansion Project
Ch 3750 in
Ch. 2000 in 23 43 months
months
Completion
in 48
months
25
4. Layout and Operation of the Port
26
4. Layout and Operation of the Port Conti..
1. Ship berth
2. Quay Crane Operation
3. Load on to Terminal
Tractors
4. To Stacking yard
27
5. Construction Break Water, Quay
Wall and Jetties
+10.30 WAVE
WALL
+8.00
+7.20 2
8 7 1
+5.00
4 +4.50
CORE-LOC 8.5m3 3 +3.50 +3.00 8
10.35 +1.50
1
L.W.O.S.T. 1
1
ROCK 1.3-2.9T 2 6 5 SAND FILL
4 QUARRY RUN
5-500mm
ROCK 8-12T 3
3 4
-8.48 BEDDING LAYER
ROCK 1.8-3.4T
2 5-100mm
1 M3
-11.57 QUARRY RUN 1 CEMENT BOUND MATERIAL
2 4 1
5-500mm GEOTEXTIL FILTER
1 M2 -13.77
SAND FILL
3 M1 QUARRY RUN -15.77 5
2
-17.60 1
4 SAND
Concrete
Surcharge
Quarry
Sand
Remaining
Armour
Wave
Reclamation
Armour
Run&Wall
Rock
Removal
(Core)
RockBlock
Filling
Breakwater Construction
31
WAVE WALL CONSTRUCTION
32
MAIN CHANNEL DREDGING &
DIVERSION OF SUBMARINE PIPELINE
LAGOON
HAMBANTOTA
CITY
33
Break Water Construction
LAGOON
HAMBANTOTA
CITY
MATARA – KATARAGAMA Rd
34
Submarine Pipeline
HAMBANTOTA
CITY
35
Completed Main Breakwater
36
Completed Secondary Breakwater
37
Completed Infrastructural Project
39
TRANSPORTATION OF ROCK MATERIALS
LAGOON
HAMBANTOTA
CITY
Construction Details:-
Date of Commencement : 16th December 2011
Date of Completion : May 2014 (Phase I - 600m Quay)
Nov. 2016 ( Phase II (Entire Terminal)
42
Scope of Work :
1200m long caisson quay wall structure
Dredging the Harbour basin to -18m
Reclaiming the Terminal
Revetments
Container Yard
Buildings
Roads
Utilities
43
SCT Construction Highlights
Quay Wall Structure
44
SCT CONSTRUCTION HIGHLIGHTS
Quay Wall Structure
45
SCT CONSTRUCTION HIGHLIGHTS
Temporary Cofferdam
46
Ground Improvement
47
48
Empty Container Yard
49
Drainage and Service Channel
50
Buildings
51
6. Dredging and Handling
Dredging Material
Dredging for sand fill
52
Dredging Habour Basin
53
7. Other Projects
Proposed CFS Operation and Cargo Value Added Service Area
Background
Expansion of cargo operation and logistics in Port of Colombo have
been confined due to limited land availability.
54
Proposed CFS Operation and Cargo Value Added Service Area
56
Galle Port Development
57
Safety..!!!
Harbour Safety
Our priority is a safe harbour for everyone. At peak times the harbour is a
busy place but with a little thought, understanding and courtesy, everyone
can enjoy the harbour in safety. We strongly encourage harbour users to
undertake appropriate training to enhance their competence, safety and
enjoyment. Please put safety first and always wear a lifejacket when afloat.
safety jacket
safety gloves
safety boot
62
63