Professional Documents
Culture Documents
Issues related to
feasibility studies
Worldwide, hydropower is a crucial power supply
contributing about 16 percent of global electricity.
Hydropower plants (HPPs) are
unique compared to other power
supply options such as thermal.
HPPs are always custom-designed
site-specific projects. HPPs require
substantial capital investment, but
they offer extremely low operating
costs and long operating life spans
of 40–50 years that can often be
extended to 100 years with some
rehabilitation.
The result is extremely competitive
production costs for electricity.
HPPs -custom-designed &
site-specific
This feature of HPPs lends a uniqueness
to them requiring feasibility studies to be
comprehensive and pass the test
against all parameters
Technical
Environmental
Commercial
Strategic
Logistics
Feasibility Studies
Project developers will continue
project preparation only if technically
suitable solutions are possible at a
potential site, if a preliminary financial
assessment reveals adequate returns,
and if regulatory/permitting
frameworks allow a plant to be
constructed and operated for a
reasonable duration. If preconditions
are met, the next step is a pre-
feasibility study
Pre-feasibility study
The pre-feasibility study (PFS) undertakes
further project assessment to answer the
following questions.
1. Is the project financially viable?
2. If so, which technical option/concept is most attractive?
During the PFS the design concept is
elaborated. Technical variants and options
are explored and a preferred technical
concept is selected—one that will maximize
financial return.
The PFS must also evaluate environmental
and social aspects of the project. A
preliminary assessment is undertaken to
identify boundary conditions under which the
project must be developed further, and to
examine potential barriers.
Question 1-Financial Viability
Hydro-power sector operated in a protected
market in the initial years till the ERC Act of 1998
enjoined the CERC to promote competition,
efficiency and economy in the electricity industry.
The recommendations of the K.P. Rao
Committee can be regarded as a landmark in
the history of tariff regulation in India, introducing
the concept of "deemed generation“, the concept
of two-part tariff comprising fixed and variable
charges , limiting both the incentive and
disincentive for recovery of fixed costs and
setting up for the first time operational norms for
power stations.
ABT further improved upon the tariff
determination placing premium on performance
and rationalizing tariff determination.
Implications of tariff
Implications of changing tariff regimes ( in
a market driven economy), high upfront
cost of hydro, falling prices in the power
market coupled with absence of level
playing field and non-compensation for its
positive attributes have led to a serious
question mark on salability of hydropower.
Feasibility studies need to overcome this
most important challenge.
However, increasing global warming
triggered awareness and need for long
term sustainable energy security has
renewed the focus on traditionally
clean power- hydro.
Question 2- which technical
option/concept is most
attractive?
TYPICAL TABLE OF CONTENTS FOR A PFS
1. Introduction
2. Description of project
3. Topography
4. Hydrological analysis and sediment transport
5. Geology
6. Assessment of seismic hazards
7. Preliminary environmental and social impact
assessment
8. Examination and evaluation of layout alternatives
9. Expected power production
10. Civil engineering design
11. Electro-mechanical equipment
12. Grid connection
13. Cost estimation
14. Permitting and licensing process
15. Planning and project implementation
16. Preliminary financial analysis
17. Preliminary risk analysis
18. Conclusion and recommendation
Issues to address
These typical 18 chapters broadly
address the various issues in the
feasibility studies.
Any one of these may render the project
unviable ( mid course corrections may be
possible in some and almost impossible in
others).
Up to this point in the project
development process, financing plays
only a minor role. However, the pre-
feasibility study is often used to present
the project to developers or promoters.
The next phase—the feasibility study—is
used to develop a preliminary design and
accurate investment requirements.
Feasibility Study (or DPR)
The FS structure is similar to that of a
PFS, except FS detail is built up by
collecting and analyzing additional data
such as soil investigations/drillings,
hydrological investigations,
environmental/social research, and
including a detailed elaboration of the
design.
The FS is built on PFS findings, which
examined several potential technical
concepts and selected the most viable.
The selected concept is optimized during
the feasibility study, which includes the
following core elements:
Technical concept:
Specification and description of
the most suitable layout and design for
civil works, mechanical equipment,
hydraulic steel structures, electrical
equipment and grid connection, and
optimization of the main power plant
parameters and so forth.
Despite advancement in knowledge and
innovative solutions available, we have
faced TBM burials ( Parbati-II, Dulhasti
etc), buried channels under dam
foundation ( Malana-II) and reservoirs
silted upto the top ( DTs not being
thought of as future desilting options .)
and many other technical issues.
Hydrology/energy
production
Emissions of greenhouse gases are
expected to lead to significant changes
in climate over the next century. One of
the many potential effects is that river
catchment runoff may be altered. This
could have implications for the design,
operation and viability of hydroelectric
power stations.
In the past, feasibility studies have relied
on historical rainfall and river flow data
for the assessment of hydroelectric
potential at a proposed site. However,
climatic change means that these can
no longer be relied on to indicate future
potential.
Geology: Results of
geological investigations
Geological surprises have quite often been cited
as reasons for time and cost overruns.
Experience tells us that these have rather been
used more as shields to hide the inadequacies
of investigation and lack of support to the
investigating teams . Surprises cant be ruled out
but should not be so regular in manifesting
themselves.
Local
Seismic
Floods
Logistic
Climate
Site-specific
Mitigation options.
Planning and project
implementation
A comprehensive project implementation
schedule, including manpower and
resource planning is vital to achieve
timely completion and within the planned
budget.