Descon-Nordex Presentation
Lahore, Pakistan
Agenda
• History
• Solution Proposed
• Contractual Structure
• Project Scope
• DOR
• BOP
• Value Proposition
History
7. Fencing
Site location
General Layout of Area.
Planned Access Roads
GP site
layout
Beacon Energy Ltd. Windfarm Site
Very loose and inaccessible site terrain
Water level fluctuation
Parameters impacting Civil design
and Construction
1. Accessibility to site.
2. Geotechnical conditions at Site.
3. Tidal variations.
4. Wind speeds and loads.
5. Corrosive Environment.
• The general site terrain described as flat with low changes in elevation.
• The spot elevations of various points across the site generally range
from 1.50m - 2.00m above the Survey of Pakistan (SOP) datum.
Surface
profile at GP
site
Surface
profile at BEL
site
3D Surface
profile at BEL
site
Tidal Study
DEL performed comprehensive evaluation of the following
available tidal data:
LWL = - 1.30 m
Load Data and Design Considerations
42
Recommended scheme for different civil
works
Finished levels (based on tidal evaluation)
• Tower foundation top of concrete = El. +3.80m wrt SOP datum i.e.
1.30m above highest tide level.
• Various sizes were checked through rigorous analysis to arrive upon the
technically most suitable.
• Analysis included:
• Bearing Capacity against Shear Failure.
• Estimate of foundation settlement.
• Pile Capacity Analysis (for compressive, tensile and lateral load
cases)
Tower Foundation
Structural Analysis:
GP site:
• 15 Nos. towers supported on RCC pile foundations; pile dia. 900mm,
pile depth 30-35m; 15-18 piles below each pile cap; pile load test shall
be performed @ 1 test/5 WTGs as per ASTM.
BEL Site:
• All towers supported on RCC pile foundations; pile dia. 900mm, pile
depth 30m; 15 piles below each pile cap.
Schematics of ground improvement below shallow foundations
Crane Pad
Roads
1. Widening of existing road
• Existing road (9.5km long) along the canal will have to be widened to
accommodate the equipment/machinery.
• Widening to be done by borrowed Soil.
• Widening shall be done to maintain safe movement of project
equipment/vehicles (6m max.)
Roads
2. Planned Access Road and Internal
Farm Roads
• These roads shall be built FIT TO PURPOSE.
• Parts of these roads will remain submerged under water. However, the
stone/gravel embankment would ensure the passage of large wheeled
vehicles such as tractors, excavators, rollers, trailers all the time.
• To be located at an area, where the NGL is higher than the average tidal
level.
• Transformers
• 132KV substation
Five (5) bays of 132kV Switchgear 132kV, 40 KA for 1 sec comprising of two
(2) overhead line bays, two(2). transformer bays and one (1) bus section bay.
Eleven (11) bays 24kV , 25 KA for 1 sec. Switchgear comprised of four bays for
collection system, two bays for power transformers, one for shunt compensation and
one spare outgoing bay complete with protection, local control, interlocking system
and interface with substation SCADA.
Main Proposal: Indoor Metal Clad
Alternate Proposal: Indoor GIS
• Auxiliary Supply System
• Telecommunication
Telecommunication equipment including line traps, HF co-axial cables, PLC and PSE
equipment, PABX, 48 V DC battery suitable for transmitting real time on line data of
the Wind Farm for the NPPC.
Five ISDN lines with PABX between control room and substation along with ISDN
line for SCADA server to connect with remote terminal.
• Substation SCADA
Substation Scada at wind farm has been included in DEL’s proposal.
However, RTU for 132kV Substation and modification including additional interface
card and extension of mimic in RPCC will be arranged by the project Company in co-
ordination with the Power Purchaser.
Basis and Assumptions for connectivity with
WAPDA
• The Owner’s Gird studies are based on Suzlon S82, new studies as per
Nordex N82 to be carried out by the Owner
• DEL has proposed distance and over current protections for 132 KV lines.
• The Owner will arrange WAPDA if any other protection will be required.
• DEL has proposed one set of Energy Meters, CTs and PTs for metering
purpose. The Owner shall arrange with Main Metering Panels from
WAPDA.
• DEL has proposed optimal location of 132kV substation for gantry point
interconnection between WAPDA grid and the Wind Farm. The Owner shall
arrange with WAPDA extension of existing WAPDA 132 kV Grid to each
Wind Farm.
Basis and Assumptions for connectivity with
WAPDA
• DEL and NDX has proposed reactive power compensation system to
comply with the draft Grid Code. The Owner to arrange with WAPDA for
their compliance as well to the draft Grid Code.
• Single EPC contract with well defined split of scope between the Contractor
parties with a joint and several cover thus offering transparent control with
double protection to the Owner.
• Contractors committed to the local market, have signed the first EPC contract
• Long term strategy to serve the local market, Descon staff shall be trained on
the commissioning and O&M of the WTGs thus offering long term investment
protection to the Owner
Value Proposition
• Conceptual Design Of Civil Infrastructure, Foundations and Other Civil Related Scope
• Conceptual Electrical System Design and Local Utility Network Requirements knowledge
• Transportation Requirements