You are on page 1of 53

BayCare Health System

Designs
Next Generation Data Center
August 8, 2007

Doug Lauterbach
Data Center Director, Bay Care Health System

Matt Schuster
Principal Consultant, BT INS
In today’s presentation…
• About BayCare
• Challenges that necessitated a new data center
• Planning the new facility
• A look at the new data center
• Your questions
About BayCare
• 9 hospitals in Tampa Bay area
• Largest full service community-based health system in
the region
• 17,000 team members
• 2,707 Beds
• 355,523 ER visits
• 6.3 million lab tests
Challenges that necessitated a new facility
Business needs driving IT
• In the process of a 7 year electronic medical record
project (moving towards paperless)
• Constant growth of digital imaging
• Increasing compliance regulations - JCAHO concerns
about information management and availability
• Increased clinical reliance on IT systems requires high
availability for quality patient care
– Pharmacy
– Lab
– Radiology
– Food and Nutrition
– Bed tracking
– Scheduling
Business Drivers of the new Facility

• Best Practices
• Business Continuity
• Business Expansion
• Capacity Planning or Performance Analysis
• Change in Application Architecture, Providers or Vendors
• Compliance
• Disaster Recovery
• Expense Management
• Increased Capacity
• Operational Optimization
• Regulatory
• Reliability
• Risk Management and Mitigation
• Technology Growth or Consolidation
• Technology Refresh
Existing facility challenge: space
• Short on space
– 8 separate spaces for IT equipment
– 4,700 sq. ft data center split into 4 spaces
• 30% of data center space used for circulation
• Large command center using a large portion of
raised floor space
• Building’s physical resiliency not up to hurricane
standards
• Design aspect to 40 watts/sf
• Shallow cabinets limit the ability to expand and distribute
power and low-voltage cabling
• Structure cabling unable to support:
– Blades
– VoIP
– Anticipated SAN growth
Existing facility challenge: power load
• Design didn’t support heat and power load
• Downtime related to power design and capacity
– circuit capacity lacking
– Distribution: not dual bus all the way to equipment
• Lack of available power threatening to limit new
technology adoption
• No standard power configurations
• No means or method to manage/measure power at the
equipment racks
Existing facility challenge: cooling
• Cooling was inefficient
– Not using hot-aisle/cold-aisle design
– Uneven temperatures through space
– Hot spots creeping up
• Equipment lifespan likely shortened due to heat
• 13-year old design, not optimized for blade configurations
• Not easily expandable
• Low 12” raised floor and under-floor low-voltage cabling
restricting air supply
• No available physical space for additional cooling
• Legacy CRACs were not communicating to efficiently cool
the space.
Existing facility challenge: visibility & control
• Monitoring – currently focuses on circuits that are tripped
(reactive), not designed for proactive data
• Temperature monitoring handled at the return air of the
precision air conditioner (not looking at hotspots)
• Little remote control for servers
• Lights-out management (iLO)
• Existing Liebert SiteScan equipment was not managing
non-Liebert equipment
• No temperature sensors at equipment location or around
the room
• No branch circuit monitoring
• 100% of lighting on 24x7
Existing facility challenge: managing change
• Provisioning is not standardized, automated or managed
• System deployments are based on:
– looking through racks
– personal knowledge
– gut feeling
– where uneducated users want placement
• Not managing capacity of:
– space
– circuits
– power
– weight
– heat loads
– network switch ports
Planning the New Facility
Objectives
• Provision for planned growth – addition of 100 servers per year
• Gain complete visibility and control and improve administration
• Improve system availability through full redundancy of the
power and cooling systems
• Improve fire detection and suppression
• Implement hot-aisle/cold-aisle design for maximum capacity
and energy efficiency
• Improve planning and provisioning
• Improve cable management
• Increased Mechanical and Electrical efficiencies
• Reduced operational costs
• Operate as a nearly lights-out facility
• Remote access into all systems
Building a Team
• Doug Lauterbach
Imaging Services Director (serving as Data Center Project
Director), BayCare Health System
• Chris Jenkins, Director Technology, BayCare Health
System
• Matt Schuster, Principal Consultant, BT INS
• Thomas Gooch, Local Liebert Representative, Emerson
Network Power
• Paul Carastro, Carastro & Assoc, MEP Engineers
• Mike Montecalvo, General Contractor, Solutions, Inc.
• Paul Schnitzlein, Architect, Harvard Jolly
Documenting Existing Equipment
• Document existing devices, power supplies and port
counts per device at the rack level
• Determine/Graph device averages per rack to determine
cabinet profiles
• Each piece of equipment assigned a number and
quantities and loads were considered. Classifications
included:
– Legacy
– Low
– Medium
– High
– Blade
– IBM RISC
– Network
Planning Process: Modeling
• Mapped watts per square foot via CFD several times,
tweaking each time to determine placement of precision
air conditioners
• Room designed for 800-1,000 kW; CFD proves capacity
• 24-inch raised floor, multiple precision air conditioning
units
• White space to grow into: 40 to 50 percent allows for
doubling of capacity
• Rerun CFD every three to six months as changes are
required using actual values collected from thermistors,
branch circuit monitoring and other tools
Existing facility: Servers per Cabinet
Planning Process: Profile Planning
Cabinet Profiles
Best Practice: Technology Infrastructure
• 44U, 45” deep cabinets to allow for distribution of power
and low-voltage cabling
• Metered Power Strips
– Every cabinet has at least two strips, one for each bus
– Some cabinets with additional strip behind a static
transfer switch
– Each strip has colored tape to quickly determine
which bus
• KVM over IP in each cabinet
– Centralized
– Decentralized
• iLO switch in each cabinet ($38/Ethernet port)
Best Practice: Power System Design

New caterpillar
Generator
1000 KW

Liebert 610 UPS Liebert Precision


225 KVA Power Center
480v Input 225 kVA
480v Output 480 Volt Input
BUS A 120/208 Ouptut

Dual Bus
Dual Power
BUS Remote BUS
Supply Servers
A Distribution B
Automatic Cabinet
Transfer
Switch 800 A
#1 Emergency
RSC Distribution
Panel
480v
70 kW A/C

Automatic 70 kW A/C
Transfer
Switch
#2
SPAWAR 70 kW A/C
Liebert 610 UPS Liebert Precision Dual Bus
225 KVA Power Center
70 kW A/C 480v Input 225 kVA
BUS Remote BUS Dual Power
Supply Servers
A Distribution B
480/ Output 480 Volt Input Cabinet
BUS B 120/208 Ouptut
Automatic
Transfer
Switch
#3
Building

Main
Electrical
distribution
panel
Best Practice: Dual-Bus EPO Systems
Best Practice: Fire Suppression
• Very Early Smoke Detection Apparatus (VESDA)
• Clean Agent Suppression system
– People-friendly
– Environmentally friendly
– Lower quantity of agent vs. FM-200
– Over 3,000 pounds of FE-25 agent
• Four zones
• Over 150+ detection points (above and below floor)
• Sprinklers were required, therefore pre-action with
double-interlock was installed
Best Practice: Remote Management
• Integrated Lights Out – allows remote control of servers
from anywhere in the world
• People-free facility benefits:
– Removed NOC Command Center from raised floor
– Minimizes human error disruptions
– Allows managers to monitor and control environment
remotely
Best Practice: Proactive Monitoring
• Followed some of ASHRAE’s TC9.9 recommendations for
monitoring temperature in racks/cabinets
• Temperature and Relative Humidity
• Branch Circuit Monitoring
• SiteScan I/O-32 and additional units
• Leak Detection
• VESDA
• Fire Suppression
• Fire Detection
• Liebert Environmental Control Systems ICOMs Control
Network
Best Practice: Labeling
• Mechanical equipment
• Electrical equipment
• Electrical receptacles
• Grid Coordinate
• Racks and Cabinets
• Structured Cabling
Tools: Rackwise/DCM
• Used tool to document existing inventories
• Tracking relocation from one facility to another
• Manage asset location by rack unit
• Provisioning limitations per cabinet
• Reporting capabilities
– Space and Assets
– Power and Cooling
– Cost and Capacity Planning
– Rack Assembly with Cabling
– Service & Warranty Contracts
– Department & Customer Information
• Long term objective: to integrate a change/configuration
management tool to track and manage assets
Tools: Rackwise/DCM
Tools: Computational Fluid Dynamics
• Allowed modeling the complete room for the initial 6
CRACs and full deployment of 12
Tools: Computational Fluid Dynamics
• Initial assessment indicates potential problems related to
placement of precision cooling units…

Low Pressure Zone

1 2
4 5
3 6

CRACs
Tools: Computational Fluid Dynamics
• CFD Program allows for virtual change - validating
proposed solution prior to installation.

CRAC Moved To New


Location

Low Pressure Zone


Removed
Tools: Computational Fluid Dynamics
• Follow-on Modeling Provides Proof of Operational Success
Assuming Full Load – 735 kW.

Clouds Per Fahrenheit Degree


Tools: Computational Fluid Dynamics
• Modeling allows for proof of design concept at full load –
prior to implementation

Pathlines from CRACs

Temperature (oF) in 1 foot


increments
CRAC Network Communications
New Data Center – Construction
New Data Center – Construction
Current Data Center – Raised Floor
Current Data Center – Raised Floor
Current Data Center – Raised Floor
New Data Center – Raised Floor
Current Data Center – Operations
New Data Center – Operations
Current Data Center – Generator
Current Data Center – Network Rack
Current Data Center – Server Cabinets
Current Data Center – Server Cabinets
Current Data Center – Server Cabinets
Current Data Center – UPS Room
New Data Center – UPS Room
Current Data Center – Yard
New Data Center – Yard Construction
New Data Center – Yard Outside
Critical Success Factors
• Teamwork between BayCare, INS and Emerson Network
Power/Liebert enabled success
• Maximization of modeling tools allowed a solid design,
even before the first nail was hammered
• Have done virtualization study – partially executing
recommendations ahead of time to make move easier
• Can’t convert everything to dual corded, so a Liebert STS
was installed to provide redundancy
• Space for a second generator is provisioned and an ATS
is in place to accommodate expansion
• Move in progress!
Questions and Answers

You might also like