METODE PELAKSANAAN

PEMASANGAN PIERHEAD

PROJECT TOL JAKARTA – CIKAMPEK ELEVATED II


TIPIKAL PIER AREA WINGS

6.1 m

14 m
TIPIKAL PIER AREA MAIN ROAD

18 m

1 2 3

14 m
SUMBER DAYA

TENAGA KERJA MATERIAL ALAT


Project Manager ( 1 org ) Pierhead segment (20 - 25 Crawler Crane 150 (1 unit)
pcs/bln)

Site Manager ( 1 org ) Crawler crane 250 (1 unit)

Supervisor ( 1 org ) Rafter crane 45 (1 unit)

K3 ( 1 org) Hyap crane 5 t (1 unit)

Operator ( 4 org ) Jacking

Rigger (6 org) Genset/penerangan

Pekerja Harian ( 8 org ) Plate

Mekanik ( 2 org) Scafolding set/Akses

Alat bantu
TAHAPAN
PEKERJAAN
 Persiapan (Mobilisasi peraalatan)
 Ijin kerja area
 Pasang scafolding (Akses pekerja)
 Persiapan material & Pekerja
 Marking survey & Top Elevasi
 Persiapan lahan
 Traffict management
 Persiapan alat bantu erection
 Pekerjaan Erection
 Setting alat berat Crawler crane 150 Ton / 250Ton
dan alat bantu
 Posisi alat dengan beban angkat +- 70 ton dengan
radius putar max 10 m, Boom tinggi max 27.4m
 Standby Surveyor untuk elevasi
 Jika semua sarana bantu sudah siap maka
Pekerjaan siap erection Pierhead
SKEMA ERECTION WINGS

SKEMA PERGERAKAN ERECTION PIERHEAD RAMP

RAMPA

Erection Pier Erection Pier Erection Pier Erection Pier Erection Pier Erection Pier

P1a P2a P3a P4a P5a P6a P7a


Moving Moving Moving Moving Moving Moving

4 jam 2 jam 4 jam 2 jam 4 jam 2 jam 4 jam 2 jam 4 jam 2 jam 4 jam 2 jam 4 jam

Target pekerjaan erection dalam 1 hari = 2 segmen pierhead


SKEMA ERECTION MAIN ROAD

SKEMA PERGERAKAN ERECTION PIERHEADMAINROAD

MAINROAD
Crane 150Ton Crane 150Ton Crane 150Ton

Finish Seg1&2 Erection Seg1&2 Erection Seg1&2

P1 Crane 150Ton P2 Erection Seg3 P4 Erection Seg3 P5 Erection Seg3 P6 Erection Seg3

1. Pier 1 Erection Segment 1&2 ( Crane 150 Ton)


2. Moving Crane 150 Ton ke P 2
3. Seting Crane 250 Ton di P1 untuk erection Segment 3
4. Moving Crane 250 Ton ke P 2
5. Continue
TRAFFICT MANAGEMENT
Segment Wings
Pierhead 6.1 meter

Pier
PIERHEAD SEGMENTAL 1&2 (CRAWLER
CRANE 150 TON)
 Pierhead Precast Seg 1

Handling loop
WORKING RANGE
CRAWLER CRANE 150 T

27-30 m

8-10 m
LOAD CHART CAPACITIES
CRAWLER
96.2 Ton (S 1&2)
CRANE 150 T
WORKING RADIUS CRAWLER CRANE
250 T

36,6 m

Radius 8-12 m
Load chart with Counter weight 80.6 T, Car body 20 T

81.7 Ton
Crawler Crane 150 Ton
 Kobelco 7150  Kapasitas beban 150 Ton
 Kapasitas beban  Panjang boom 27 – 30 meter
maksimun 150 ton  Radius erection 8 meter
radius 5 meter
 Berat Pierhead 65 Ton
 Boom maksimum
 Berat Hook 2.5 Ton ( kap 150
73.15 meter
Ton)
 Lebar trek 6.82
 Maksimum kapasitas crane
meter
96.2 Ton
 Panjang trek 8.15
 Faktor keselamatan 1.42
meter
(70.16%)
CRAWLER CRANE 150
TON
 Kobelco 7150
 Kapasitas beban
maksimun 150 ton
 Kapasitas beban 150 Ton
radius 5 meter  Panjang boom 27 – 30 meter
 Boom maksimum  Radius erection 8 meter
 73.15 meter  Berat Pierhead 60 Ton
 Lebar trek 6.82  Berat Hook 2.5 Ton ( kap 150
meter Ton)
 Panjang trek 8.15  Maksimum kapasitas crane
 meter 96.2 Ton
 Faktor keselamatan
1.59(62.8%)
CRAWLER CRANE 150 TON

 Kobelco 7150
 Kapasitas beban 150 Ton
 Kapasitas beban
 Panjang boom 27 – 30 meter
maksimun 150 ton radius
5 meter  Radius erection 8 meter
 Boom maksimum  Berat Pierhead 60 Ton
 73.15 meter  Berat Hook 2.5 Ton ( kap 150
 Lebar trek 6.82
Ton)
meter  Maksimum kapasitas crane
 Panjang trek 8.15 96.2 Ton
 meter  Faktor keselamatan 1.59
(62.8%)
CRAWLER CRANE 250 TON

 Kobelco CKE2500  Kapasitas beban 250 Ton


 Kapasitas beban  Panjang boom 36 meter
maksimun 250 ton  Radius erection 12 meter
radius 4 meter  Berat Pierhead 50 Ton
 Boom maksimum
 Berat Hook 2.5 Ton ( kap
91.4 meter 150 Ton)
 Lebar trek 7.22  Maksimum kapasitas crane
meter 81.7 Ton
 Panjang trek 8.83  Faktor keselamatan 1.63
meter (61.1%)
SCHEDULE