LEAP2-RUT-T1

TASK 1: HF Radar Systems November 2, 2010 –

Engineering Plan February 24, 2011


75days

• Define performance Objectives for Multi-Static


Operation
• Define system requirements for Large Scale
Deployment Architecture
• Define Interfaces and Requirements for Second
Shore Station and at sea bistatic transmitter
• Deliverable “Codar HF Radar Functional
Specification”
U.S. National HF Radar Network

Segment Color Key


Red > 90 km
70 km < Orange < 90 km
70 km > Green

http://ioos.gov/hfradar/
Existing and Proposed HF
Radars for the United States
Nominal Existing Proposed Total
Range Radars Radars Radars
(km)
VeryHigh Resolution(42 MHz) 20 4 12 16
High Resolution (25 MHz) 45 25 36 61
Standard Range (13 MHz) 75 39 120 159
Long Range (5 MHz) 180 44 40 84
Total 112 208 320
Google Earth Map: Existing Sites
Alaska - 3

Puerto Rico - 2

CONUS - 104

Hawaii - 3
Google Earth Map: Proposed Sites Alaska - 17

Puerto Rico - 20
CONUS - 262

Pacific Islands - 21
LEAP2-RUT-T2

TASK 2: Purchase Shore November 2, 2010 –


April 7, 2011
105 days
Station Components
• Purchase SeaSonde SSRS-100 13 MHz
• GPS Synchronization
• Lightning Protection Package
• Bistatic Software Package
• Shore Station Infrastructure (shed,
enclosure, communications, power, UPS)
LEAP2-RUT-T2
LEAP2-RUT-T2

TASK 2: Install Shore March 25, 2011 –


June 17, 2011
Station 60 days

• Specify Shore Location


• Obtain Necessary Approvals and Permits
• Install and Calibrate System
• Initial System Testing in MonoStatic Mode
LEAP2-RUT-T2

Existing Medium
Range Network
LEAP2-RUT-T2

Future Medium
Range Network
LEAP2-RUT-T2

Belmar Fishing Club


LEAP2-RUT-T3

TASK 3: Association March 25, 2011 –


Requirements June 17, 2011
60 days

Analysis
• Define Performance Requirements for
Association Algorithms
• Develop Preliminary Implementation Plan
for Association of Data from Multiple
Shore Stations
Processing Matrix
Threshold (dB)
6 7 8 9 10 11 12 13
16 IIR

32 IIR MED
FFT Points

64 IIR MED
IIR IIR IIR IIR
128 MED MED MED MED
IIR IIR IIR IIR
256 MED MED MED MED
IIR IIR IIR
512 MED MED MED
1024 MED
Processing Time and Velocity
Resolution
FFT Points FFT Length vr (cm/s) vr (knots)
16 8s 144 2.88
32 16 s 72 1.44
64 32 s 36 0.72
128 64 s 18 0.36
256 2 min 8 s 9 0.18
512 4 min 16 s 5 0.09
1024 8 min 32 s 2 0.05
LEAP2-RUT-T4

TASK 4: Develop November 2, 2010 –

Implementation February 24, 2011


75days

Plan
• Assist OPT in defining data structure,
protocol and hardware configuration
required for LEAP Regional Server
Network
Portals, Nodes, Sites
LEAP2-RUT-T5

TASK 5: Design Vessel April 8, 2011 –


Detection Architecture July 1, 2011
60 days

• Optimize threshold levels, background


levels and integration times for vessel
detection
LEAP2-RUT-T6

TASK 6:Multi-Static April 8, 2011 –

Operations August 4, 2011


83 days

• Add second to multi-static processing


• Configure Software and Hardware for
multi-static operation
• Produce data from BRNT, BELM,
• Continue multi-static operation, testing and
optimization
LEAP-R-T4

Radial Current Vectors


Totals from Radials
LEAP-R-T4

Elliptical Current Vectors


Totals from Radials & Ellipticals
LEAP2-RUT-T7

TASK 7:Bistatic Interface November 2, 2010 –

Development April 28, 2011


120 days

• Support OPT with Tx/Buoy interface


• Provide detailed mechanical/ electrical
specifications for shock and vibration,
positional stability criteria
• Support systems integration and testing at
OPT
• Analyze performance of Vessel detection
based on bistatic operation
LEAP2-RUT-T7

Bistatic Transmitter Package


Transmit Antenna
Atop Buoy
LEAP2-RUT-T8
Refinement of
TASK 8:
Multistatic Detection August 5, 2011 –
September 16, 2011
Technologies 30 days

• Develop Improved Detection


Methodologies
• Report on detection improvements
LEAP2-RUT-T9

TASK 9:Real Time August 5, 2011 –

Transition Studies September 16, 2011


30 days

• Update Shore Stations to automate


production of Detection files at the shore
station
• Implement ftp or equivalent to provide
detection files to regional node
• Make real time architecture
recommendations