You are on page 1of 15

Achieving EMS

14001: 2004
certification
Seginiaga Rubber Industries SB.
1st. Kick-off Meeting.
16th DECEMBER 2010
Our Deliverables

•Oberves The Current • Draft The Quality Manual. • Finalize Documentation • Apply for the Quality System
Practice. (Strategic) • Undertake Internal Audit Certification.
• Identifiy current • Draft The Procedures • Fine tuning System • Formal Pre-assessment.
documentation practices (Tactical) • Facilitate the Management • Formal Adequacy / Document
• Set the Policy & Objectives • Draft the Forms / Review Meeting Review.
• Form & Conduct Steering Checksheets. (Opeartional) • Formal Compliance Audit.
Committee meeting • Conduct Training : QMR, • Undertake Corrective Action.
• Establish the Doc. List Steering Committee, • Certification Award &
• Prepare Doc. Outlines Internal Audit. Registration.
• Facilitates Awareness
Campaign

• Stage 1 • Stage 2 • Stage 3 • Stage 4


PLAN •
DO •
CHECK •
ACTION
TIMELINES ON ACHIEVING EMS ISO 14001:2004 CERTIFICATION

Project Planning. Setup Design & Develop the Readiness Review


Steering Team. Kick-off QMS Documentation & Stage 1 – Document
Mtg. Gap Analyis Implementation. Review

December 10 January 11 February 11 March 11 April 11 May 11


Certification Process:
Plan Timeframe. Draft The Carry-out Internal Audit. Fine Stage 2 – Certification
Quality Manual & Policy. Tuning – Corrective Action & Audit
Awareness & Training Management Review
The Implementation Process Flow
INVESTMENT AND QUOTATION FOR SEGINIAGA RUBBER INDUSTRIES SDN. BHD.

S ta tu s
PDC A
S ta g e
Task KEY TASKS No. of Subtotal RM 980
No. Mandays Mandays /Mandays
0 Observes the current position 1.00 980.00
2 Identify current documented practices 0.50 490.00
3 Set the Policy and Objective 1.00 980.00

P LAN
ONE
4 Form & conduct steering group meeting 0.50 490.00

A p p ly
5 Establish the Documentation List 0.50 490.00
6 Prepare the documentation outline 0.50 490.00
7 Conduct the Awareness Campaign 1.00 5 980.00
8 Draft the Quality Manual (Strategic) 0.50 490.00
9 Draft the Quality System Procedures (Tactical) 4.00 3920.00
10 Draft the (Operational) Document and Checksheets T 3.00 2940.00

DO
W 0.50 490.00

o p tio n al
11 Conduct the training for Top Management
O
12 Conduct the training for Middle Management & MR 0.50 490.00
13 Conduct the training for wokers 0.50 490.00
14 Conduct the training for Internal Auditors 1.00 10 980.00
15 Finalize all level documentation T 0.50 490.00

CHE CK

A p p ly
H
16 Undertake audit program (internal)
R
3.00 2940.00
17 Fine tuning System E 1.00 980.00
E
18 Conduct the Management Reviews Meeting 1.00 5.5 980.00

N o t ap p licab e
19 Apply for the Quality System certification 0.00 0.00
20 Formal Pre-assessment 0.00 0.00

A C T IO N
FO UR
21 Formal Adequacy / Documentation Audit 0.00 0.00
22 Formal Compliance Audit 0.00 0.00
23 Undertake corrective action 0.00 0.00
24 Certificate award and registration 0.00 0.00
Total 20.5 20.5 20090.00
Paid
Balance
Mode of payment RM Discounted
Upon Letter acceptance agreed and signed@20% 5022.50 0
Once completion of Stage 3 15067.50
20090.00
*Cheque made payable to:
Rezqi JS Enterprise M utual Agreement Concluded
Rezqi JS Enterprise Agreed By Date& Company Stam p
5 Keys Element of ISO14001
Hierachy of EMS Documentation
Integrated ISO/TS 16949, ISO9001 & IS014001
Level I: Is a Startegic Documents it might
consists ; QMS Management Manual,
Quality Policy, Objectives & Targets.
General Requirements for the Level II: Is a Tactical Documents it might
Management System - clause 4 consists; Quality Procedures, etc.
4.1 Establish and maintain a quality Level III: is a Opeartional Doocuments it
management system: put it into Integrated Manual
might consist; Work Instructions,
action and improve it. Env. Policy & Objectives
Standard Operating Procedures, Work
4.2 Document the quality Method Statements, etc.
management system. System Procedures Level IV: is a record whichever forms
4.2.1 Create documents including a have been fulfilled with data, Customer
quality policy, objectives, manual, Specific Requirements, Standards,
procedures and records Drawings, etc.
4.2.2 Have a quality manual WI SOP WMS
4.2.3 Control documents
4.2.4 Create and maintain
records of the system.
Forms Records Drawings, Std.,CSR
QSHE Steering Committee
Chairman
QSHE / MR

Secretariat
Internal Audit
QSHE / DMR

Legal Requirements & Environment Aspect & Emergency Preparedness Chemical Control & Waste
Pollution Control Impact Team & Response Team Management Team

First Aid Team


Fire Fighting Team
Chemical Spillage & Gas