Promotional Novelties
How many wheels will the
manager need to order??
Number of wheels for the wheel assembly of tractor : 6
Number of wheels for the wheel assembly of tractor : 12
Total Number of wheels for a tractor-trailer : 18

Total Number of toy tractor-trailers needed : 20000

Total Number of wheels for 20000 toys : 20000 * 18=360000

As the ordered wheels comes in sets of 6400, the manager would


order 364800 wheels
When should the manager place the order??
In the beginning of first week of Master Schedule
How many wheels should the manager
expect to have left over?
Total Number of wheels for 20000 toys : 20000 *
18=360000
As the ordered wheels comes in sets of 6400, the
manager would order 364800 wheels
Left over wheels : 4800
DMD Enterprises
Master Schedule
 DMD Enterprise Case
 David “Marty” Dawkins owns the company which produces two models
of bike Arrow and Dart
 We need to forecast the MRP schedule for manufacturing
 The Arrow(15)
 The Dart(10)
 For week 4 through week 8.
Product Structure Tree : Arrow
Arrow
 
 

X M W
  
F
 
Product Structure Tree : Dart
  Dart
 
 

K(2) F
 
 

 
W(2) Q 
MRP Schedule for arrows
Week Beg 1 2 3 4 5 6 7 8
number inv

quantity 0 0 0 15 15 15 15 15
MRP Schedule for darts
Week Beg 1 2 3 4 5 6 7 8
number inv

quantity 0 0 0 10 10 10 10 10
MRP schedule for arrows
MRP schedule for Darts
MRP schedule for X
MRP schedule for M
MRP schedule for Q
MRP schedule for K
MRP schedule for F
MRP schedule for W