Professional Documents
Culture Documents
Given the product structure tree for A and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed Product Structure Tree for Assembly A
Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day Total Unit Demand Day 10 40 A Day 5 40 D (Spares) Day 4 20 F (Spares)
Finally, repeating the process for all components, we have the final materials requirements plan:
Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 1 2 3 4 5 6 7 8 9 50 200 100 55 55 20 200 200 400 300 20 200 400 100 300 10 50
20 20 200
200
B(4) D(2)
Material Requirements Planning (MRP) Driven by dependent demand Used to determine the no. of parts, components & matls needed for a product Gives time scheduling information specifying when each of the mats, parts & components should be ordered or made It is a software system
Inventory transactions
Secondary reports
Primary reports Planned order schedule for inventory and production control Exception reports Planning reports Reports for performance control
The McGraw-Hill Companies, Inc., 2004
Contains complete information regarding Inventory of each item in product structure Upto date info on on-hand quantities, Gross requirements Scheduled receipts, Planned order releases Includes LOT sizes, lead times, Safety stock etc
10
11
MRP Terms
Gross Requirements Scheduled receipts Safety stock, LOT Size etc Net requirements Planned order receipt Planned order release
12
eg : MRP Schedule
In a moped the following product structure diagram represents its bill of materials
MOPED
ENGINE ASSEMBLY
GAS TANK
FRAME
MOTOR
CARBURETOR (2)
HUB ASSEMBLY
TYRE
13
Parent Code
Offtake
Moped
EA GT WA F M C HA T
Engine Assy. Gas Tank Wheel Assy Frame Motor Carburetor Hub Assy. Tyre
1 1 2 1 1 2 1 1
EA
WA
14
Moped EA GT WA F M C HA T
10 10 10 --11 11,12
15
The company is currently planning production for weeks 10 through 16. Based on existing orders and demand forecasts, the master production schedule is as follows: Master Production Schedule: Moped Determine the MRP schedule required to support the master production schedule for the moped in weeks 10-16 WEEK QUANTITY
10 0
11 1000
12 0
13 1300
14 800
15 1200
16 1400
Data from Inventory Status Report On-Hand balance : 500 mopeds OnNo Scheduled Receipts for mopeds Lot-for-lot (LFL) rule is used for ordering mopeds Lot-forSafety stock of 200 mopeds is desired Lead time for mopeds is one week
MRP Schedule for Mopeds ITEM: MOPED LOT SIZE: LFL LT: 1 SS: 200 WEEK
16
I n i t i a l
10 0
11 1000
12 0
13
14
15
16
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 500) (ONNET REQUIREMENTS PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: MOPED LOT SIZE: LFL GROSS REQUIREMENTS F i n a l SCHEDULED RECEIPTS AVAILABLE
WEEK
10 0
11 1000
12 0 0
13
14
15
16
1300 800 1200 1400 1300 800 1200 1400 1300 800 1200 1400
17
18
I N I T I A l
WEEK ITEM: GAS TANK LT: 2 LOT SIZE: LFL SS: 200 10 11 12 13 14 15 16 GROSS REQUIREMENTS 1000 0 1300 800 1200 1400 0 SCHEDULED RECEIPTS 900 AVAILABLE (ON-HAND = 600) (ONNET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES
ITEM: GAS TANK LOT SIZE: LFL GROSS REQUIREMENTS F i n a l SCHEDULED RECEIPTS AVAILABLE
NET REQUIREMENTS
WEEK
11
12
13
14
15
16
1000 800 1200 1400 1000 800 1200 1400 1000 800 1200 1400
19
ITEM: FRAME LOT SIZE: 2000 GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE NET REQUIREMENTS
LT: 3 SS: 0
WEEK
10 1000 2000
11 0
12
13
14
15
16 0
600
20
WEEK
ITEM: FRAME LOT SIZE: 2000 GROSS REQUIREMENTS F i n a l SCHEDULED RECEIPTS AVAILABLE
LT: 3 SS: 0
10 1000 2000
11 0
12
13
14
15
16 0
2600 1600 1600 300 1500 300 900 0 0 0 500 2000 2000 2000 0 1100 2000 0
21
MRP Schedule for Engine Assemblies for Weeks 10 - 16, considering : Gross Requirements come from moped Planned-Order-Releases There is an On-Hand balance of 300 engine assemblies at the end of week 9 There is a Scheduled Receipt for 1000 engine assemblies in week 10 The firm uses a Lot Size (multiple) of 500 for ordering engine assemblies Safety Stock of 100 engine assemblies is desired Lead time for engine assemblies is 1 week ITEM: ENGINE ASSEM. LT: 1 LOT SIZE: 500 SS: 100
WEEK
10 1000 1000
11 0
12
13
14
15
16 0
I N I T I A L
GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE (ON-HAND = 300) (ONNET REQUIREMENTS PLANNED ORDER RECEIPTS PLANNED ORDER RELEASES
22
ITEM: ENGINE ASSEM. LT: 1 LOT SIZE: 500 SS: 100 GROSS REQUIREMENTS SCHEDULED RECEIPTS AVAILABLE F i n a l
WEEK
10 1000 1000
11 0
12
13
14
15
16 0
(ON-HAND = 300) 1200 200 200 400 100 400 (ON1100 400 1100 1000 1500 500 1500 1000 1500 500 1500 1000
23
24
Successor to the MRP, it integrates planning of all aspects (not just production) of a manufacturing firm. MRP II integrates functions such as production planning, scheduling,capacity requirement planning, operations planning etc
25
ERP
a software that organises & manages a companys business processes by sharing information across functional areas.
Useful for global companies and those that share data regularly benefit the most from ERP.
26
Human Resources
27
Financial Accounting
Financial s,controlling, Asset management
Human Resources Payroll & Benefits admn. Applicant data administration Personnel development planning Workforce planning Schedule & shift planning Time management Travel expense accounting Sales and Distribution Customer management Sales order management Distribution Shipping and transportation mgmt
Manufacturing & Logistics Materials management Plant maintenance Quality management Project mgmt system
28
Major vendors
29
ACC, Arvind Mills, Bharat Forge,., Crompton Greaves,, Essar Oil,Essar Steel, Grasim, Haldia Petrochemicals, Ispat Industries, Kalyani Brakes, L & T, Mahindra, MICO,Microland, ONGC, Ranbaxy, Tata Communications, M&M,TELCO,TISCO,UTI
,Siemens,P&G,Colgate,WIDIA,Volvo,Telco,Samsung,ABB