Professional Documents
Culture Documents
A B C D E F G
2 6 5 4 6 9 3
B A,C D B E,F
Act
Dur
Pre
A A D start B F C E G finish B C D E F G
2 6 5 4 6 9 3
B A,C D B E,F
A A 2 C 5 B 6 F 9 D 4 E 6 G 3 finish B C D E F G
2 6 5 4 6 9 3
B A,C D B E,F
start
The critical path is the path of activities that takes the longest amount of time; the path with the activities that cannot be altered time-wise without changing the overall project duration.
Calculating slack
Any activity on the critical path has NO SLACK. Any others are based on when they meet the critical path. EX: Activity A requires two days, but there are 11 days available ( Activity A meets the critical path at start (0) and at D. 11 days have passed on the critical path before getting to D (B+C=11). A 2 start B 6 C 5 F 9 D 4 E 6 G 3 finish
Activity Duration
ES EF LS LF
A 0 2 2 9 11 start B 0 6 6 0 6 C 6 11 5 6 11
D 10 15 4 10 15
E 15 21 6 15 21 G 21 24 3 21 24 finish
F 6 15 9 12 21
A B C D E F G
4 5 2 4 7 5 1
A C C D B start
A 4
C 2
F 5 finish
A| 0 4 4| start
C|4 6 2 |
S=9 B|0 5 5 | 9 14
A B C D E F G
4 5 2 4 7 5 1
A C C D B
F 5 finish