ARNAIZ AVENUE (PASAY ROAD)

MRT STATION (AYALA)

MRT STATION (MAGALLANES)

EDSA

5,000 sqm

PROJECT CONCEPT
Masterplanned by the world-renowned design firm,

ISO 9001 AND ISO 14001 Certified TUV (Germany) Certified Awardee, BD Magazine Top 200 Architectural Firms in the World

PROJECT CONCEPT
A mix-use development in Makati with complete features and amenities offered at affordable prices

MAIN FEATURES
Three residential towers on top of a five-level commercial structure 5-level parking complex 5-level mall and shopping center 5,000 sqm state-of-the art Amenities & Garden Complex

Tower 1 378 units ( 28 floors ) Tower 2 540 units ( 37 floors ) Tower 3 306 units ( 24 floors ) Chino Roces (Pasong Tamo)

Height of Tower 1 96.00m Tower 2 125.00m Tower 3 83.00m * From road line

South Expressway

What are the amenities that can be enjoyed?


health club, swimming pool, outdoor fitness center, garden patio, childrens playground, function areas

> Pool size - 100.00sqm

Amenities & Garden Center

STRUCTURAL MEASUREMENTS
Distance between buildings: 7.50m - 8.50m

Vertical Clearance Ground-4.0m 2nd-5th 3.5m

FLOOR-TO-CEILING HEIGHT
Floor to slab - 2.80m Floor to Beam - 2.40m

slab soffit beam soffit

South Expressway

TOWER 1 378 Units 2 passenger elevators 18 units per floor

TOWER 2 540 Units 3 passenger elevators

South Expressway

18 units per level

Chino Roces (Pasong Tamo)

Tower 3 306 Units 3 Passenger elevators

18 units per level

What are the different types and average sizes of the units?

Typical 20.40sqm (middle unit)

Typical 21.00sqm (studio unit)

Typical 31.23sqm (corner unit)

UNIT DELIVERY
Ceramic Floor Tiles Unglazed Ceramic floor tiles @ T&B Painted Finish Walls Granite Counter @ Kitchen w/ under counter built-in cabinet Sliding Flush Door @ Bedroom ACU Provision only Aluminum Sliding Window Individual electric meter per unit (located at the electrical room near fire exit) Individual water meter per unit (located along the corridor)

What kind of materials is used for the walls in between rooms and in between units?
CHB between units, Dry wall w/in unit

COMMERCIAL UNITS
TOWER 3

Tower 3 Ground Floor Total Units = 21 ( Pasong Tamo Entrance) Suggested type of store: -fastfood chain, -banks, -convenient store

Tower 3 Second Floor Total Units = 25 Suggested type of store: -fastfood chain, -book store

Tower 3 3rd Floor Total Units = 25 Suggested type of store: -dry goods, -music store, -internet/computer shop

Tower 3 4th Floor Total Units = 25

Suggested type of store: -office space

FREQUENTLY ASKED QUESTIONS

Does a unit comes with air-conditioning units? No, provisions only.

Covered with Ficemboard window type

Is there exhaust for kitchen? Is it ducted?


Yes

Ducted Kitchen exhaust located above the counter

Granite Color type


Kitchen counter

Is there a power backup?


Yes, generator will be utilized as a standby power source. Common areas have 100% power while each residential unit will provide limited power for basic appliances.

Where will be the water tank located?


Located at the roof deck of every building

What are the safety features of the building?


Fire Detection & Alarm System Fire Escape Stairs Fire Rated Residential Floors Sprinkler System at common areas

When is the completion of the project?


Dec 2010-Tower 1 Dec 2013-Tower 2 1st Half 2014-Tower 3

How much is the Reservation Fee?


Parking 10,000 Below 3M 25,000 3M to 6M 40,000

PAYMENT TERMS
TOWER 2
Payment Term - 20% Equity, 80% Balance 20% - payable in 36 months, 0% interest 80% - payable thru Bank / In-House Financing

PAYMENT SCHEMES

TOWER 3
Payment Term - 40% Equity, 60% Balance 40% - payable in 48 months, 0% interest 60% - payable thru Bank / In-House Financing