TANGGUH LNG

Tangguh Overview
David Clarkson
Tangguh Project Performance Unit Leader
TANGGUH LNG

Content

• Introduction
• Tangguh Organisation
• Tangguh Facilities
• Project Progress
• Integrated Social Program
TANGGUH LNG

Introduction
TANGGUH LNG

Tangguh Location

Tangguh
LNG
Project

Jakarta
3000 km
TANGGUH LNG

BINTUNI BAY AREA: VILLAGES

Sorong Manokwari

Papua
I R I A N Province
J AY A

Bintuni

Taroy Biak
Tomu Ekam

Mogotira Arandai
Weriagar Teluk Bintuni
Tangguh LNG Project

Tanah Merah
Saengga

Onar Tofoi
Babo

Otoweri
Kokas

Obadari

Timika
Kaimana

Fak-Fak
TANGGUH LNG

Tangguh Context

• Tangguh LNG is one of BP’s five New Profit


Centres.
• Tangguh LNG is Strategic at BP Group Level and
is positioned to access new markets in China,
US, Japan, Korea, and SE Asia.
• Tangguh LNG is also Strategic for Indonesia.
TANGGUH LNG

LNG Market

SK / K-Power Sempra
1.15mmtpa 3.7mmtpa

Fujian,
2.6mmtpa

LNG Sales Drives Two Train Launch


• Fujian Sales – China new LNG market (2.6 mmtpa)
• Sempra Sales – first long term Asia Pacific sales to North America (3.7 mmtpa)
• SK / K-Power – new Korean LNG Buyers (1.15 mmtpa)
TANGGUH LNG

Tangguh Fields

Papua
IRIANJAYA
Province

MUTURI PSC
Mogoi
Deep-1

MUTURI PSC
WIRIAGAR PSC
W Nam-
D- WD 1 S
1 -8 WD V V V-ak-
W -6 -1 V V -4 V 8 1
D- - V-
W WD - V- - V
7 7 11
WD D- -5 3 V5 -
-3 2 R 6 -2 Vorwata Field
9
Wiriagar Deep Field
WIRIAGARDEEPFIELD W oa-1 VO
V-
RWATAFIELD
D- Roabiba
Ofaw ROABIBAFIELD 10
4
BERAU PSC OfaweriOFA
Field Field
eri-1
WERIFIELD
Wo
LNG Plant
s-1
Wos
WOSFIELField
D
Ubad
ari-1
Ubadari Field
Ubada ARGUNI PSC
ri-2

BABO PSC
0 10 20km

Birds Head Topography & Bathymetry


TANGGUH LNG

Tangguh Organization
TANGGUH LNG

Tangguh Project Performance Unit


BUSINESS UNIT
LEADER
Anne Drinkwater

TANGGUHPROJECT
PUL
David Clarkson

DEPUTY VP PROJECT PROJECT DRILLING& RESERVOIR &


TANGGUH SERVICE DIRECTOR COMPLETION WELLS BU HSE Sr. MANAGER VP ISP
Ngurah MANAGER FACILITIES MANAGER MANAGER MANAGER
OPERATION
Kresnawan Roedhy Mike Wortham Russ Achmadi Kasim Tba Tba
Triasto Hunzeker Fauziyah Mansur

Areas of FOCUS
Train 1 & Train 2: build and operate Trains 1 & 2
Phase II: provide services related to engineering and
exploration
TANGGUH LNG

Construction Workforce Profile (2005 -2009)

6000 Office/Babo
Seismic
5000 Drilling
GPF
4000 Platform Fabrication
LNG
3000

2000

1000

0
May-05

May-07

May-09
May-06

May-08
Sep-06
Sep-05

Sep-07

Sep-08

Sep-09
Jan-05

Jan-07

Jan-08
Jan-06

Jan-09
TANGGUH LNG

Tangguh Facilities
TANGGUH LNG

Major Project Milestones

Description Milestones
FID Jan 2005
LNG Effective Date Feb 2005
GPF Effective Date Mar 2005
Platform 1 installed Mar 2007
Platform 2 installed Apr 2007
1st Gas Mar 2008
Train 1 First Drop Oct 2008
Train 1 Take Over Jan 2009
Train 2 Take Over Jun 2009
Tangguh – World Class Project TANGGUH LNG

LNG Plant

• US$ 5 billion initial development cost


• Two train 3.8 mmtpa capacity each, gas drive, air cooled, C3
precool/mixed refrigerant process
• KJP (Kellog Brown & Root, JGC and Pertafenikki) as appointed
• contractor
$ 200m worth of long lead
equipment orders placed - Airport
Gas Turbines, Refrigerant
compressors, Main Commu
nity
Cryogenic Heat Control
Room
Exchangers, LNG Storage LNG
Trains
Tanks plates. LNG
Storage

• Formal EPC award 1Q 2005 Gas


Production
Facilities
Maintenance
Area

LNG Cargo Dock


Loading
Dock
TANGGUH LNG
Tangguh OFFSHORE – Gas Processing Facilities

Ma
ngr
o ve-
line
dC OSF
oas
tlin
e
Platform 24” CRA (316L Clad)

Sandwaves
Trenched and rock covered

Risks:
• Pipeline buckling
• Mobile seabed
Tinlet = 110° C
P = 120 bar - Two 6 legs NUI platforms & 40 km 24” OD CRA
Capacity = 1.3 bcfd pipelines (316L metallurgically bonded clad)
- Saipem as awarded contractor.
TANGGUH LNG

Babo Base Camp


TANGGUH LNG

Babo Airstrip

Babo April Babo


Babo Base Camp - Jetty
TANGGUH LNG
TANGGUH LNG
Babo Base Camp - Road to Jetty

You might also like