Tangguh Overview
David Clarkson
Tangguh Project Performance Unit Leader
TANGGUH LNG
Content
• Introduction
• Tangguh Organisation
• Tangguh Facilities
• Project Progress
• Integrated Social Program
TANGGUH LNG
Introduction
TANGGUH LNG
Tangguh Location
Tangguh
LNG
Project
Jakarta
3000 km
TANGGUH LNG
Sorong Manokwari
Papua
I R I A N Province
J AY A
Bintuni
Taroy Biak
Tomu Ekam
Mogotira Arandai
Weriagar Teluk Bintuni
Tangguh LNG Project
Tanah Merah
Saengga
Onar Tofoi
Babo
Otoweri
Kokas
Obadari
Timika
Kaimana
Fak-Fak
TANGGUH LNG
Tangguh Context
LNG Market
SK / K-Power Sempra
1.15mmtpa 3.7mmtpa
Fujian,
2.6mmtpa
Tangguh Fields
Papua
IRIANJAYA
Province
MUTURI PSC
Mogoi
Deep-1
MUTURI PSC
WIRIAGAR PSC
W Nam-
D- WD 1 S
1 -8 WD V V V-ak-
W -6 -1 V V -4 V 8 1
D- - V-
W WD - V- - V
7 7 11
WD D- -5 3 V5 -
-3 2 R 6 -2 Vorwata Field
9
Wiriagar Deep Field
WIRIAGARDEEPFIELD W oa-1 VO
V-
RWATAFIELD
D- Roabiba
Ofaw ROABIBAFIELD 10
4
BERAU PSC OfaweriOFA
Field Field
eri-1
WERIFIELD
Wo
LNG Plant
s-1
Wos
WOSFIELField
D
Ubad
ari-1
Ubadari Field
Ubada ARGUNI PSC
ri-2
BABO PSC
0 10 20km
Tangguh Organization
TANGGUH LNG
TANGGUHPROJECT
PUL
David Clarkson
Areas of FOCUS
Train 1 & Train 2: build and operate Trains 1 & 2
Phase II: provide services related to engineering and
exploration
TANGGUH LNG
6000 Office/Babo
Seismic
5000 Drilling
GPF
4000 Platform Fabrication
LNG
3000
2000
1000
0
May-05
May-07
May-09
May-06
May-08
Sep-06
Sep-05
Sep-07
Sep-08
Sep-09
Jan-05
Jan-07
Jan-08
Jan-06
Jan-09
TANGGUH LNG
Tangguh Facilities
TANGGUH LNG
Description Milestones
FID Jan 2005
LNG Effective Date Feb 2005
GPF Effective Date Mar 2005
Platform 1 installed Mar 2007
Platform 2 installed Apr 2007
1st Gas Mar 2008
Train 1 First Drop Oct 2008
Train 1 Take Over Jan 2009
Train 2 Take Over Jun 2009
Tangguh – World Class Project TANGGUH LNG
LNG Plant
Ma
ngr
o ve-
line
dC OSF
oas
tlin
e
Platform 24” CRA (316L Clad)
Sandwaves
Trenched and rock covered
Risks:
• Pipeline buckling
• Mobile seabed
Tinlet = 110° C
P = 120 bar - Two 6 legs NUI platforms & 40 km 24” OD CRA
Capacity = 1.3 bcfd pipelines (316L metallurgically bonded clad)
- Saipem as awarded contractor.
TANGGUH LNG
Babo Airstrip