Vishal Telang
Engineer GIS
TM-1600
Timing tests are done first in the factory during the routine tests and after
They have to be done periodically in order to validate the good working order Timing tests are also a powerful tool for troubleshooting faulty breakers.
Description
This device sends electric signals via cables connected to each contact, in
the case of several contacts in series each signal has its own source to eliminate interference.
The signal has two possible states. The first is when the contact is closed,
the second when the contact is open. All is recorded for consultation and analysis.
Timing CB TM 1600
2. PARKING TERMINALS.
Safety terminals for breaker control wires. Not connected to internal circuits. Also to avoid unintentional breaker operation while working on the breaker, the breaker control circuit must disconnect from TM-1600 outputs.
3. Power ON/OFF.
ON
4. POWER-ON lamp.
OFF
10
10
11
11
12
12
13
13
From these terminals we made connection between CB Main contact & TM-1600.
These channel also known as verification circuit .Each verification circuit includes a voltage source that injects current on contact making; a detection circuit, to detect the current and determine if the contact is closed.
14
14
15
15
2.Contact Mode(Normal position) This mode is generally used as measure operating time of CB.Toggle switch is in normal position. Ex. Main contact of isolated CB,Indicating or control s/w contact of CB.
16
16
17
17
1. 2. 3. 4. 5. 6. 7. 8.
Table of events in channel-number order.Graph of events,compressed time scale. Table of events in channel-number order. Table of events in chronological order.
18
18
18. TRIG.
Input for external start of recording. Recording starts if the READY lamp is on.
19
19
PRECUATION
a) Ensure that SFT/PTW is taken as per norms. b) There should not be any joints in testing cables.
20
20
Procedure of test
1.Check that :The poles or the cubicles are correctly secured to the ground.
The electrical connections between the circuit breaker and control cubicle are made in accordance with the electric circuit diagrams. When the measurements are performed on energised substation, disconnect the alarms or commands can be transmitted to the control. 2. Wire up the time recorder according to FIG. 3.Energise the time recorder after having checked that it is properly connected to earth. 4. Adjust the time delays of the switching operations, no time delay is necessary for the operations C, O and CO. For the switching cycle O-(t)-CO, delay the C with the value (t) specified in the Inspection Results File (contractual cycle). For example : t = 0.3 s (300ms) normally 5.Perform the switching cycle desired. 6.Place the print selector onto program 1. 7.Press the READY button, the red lamp lights up, turn the START knob before the lamp goes out. 8.The report will be automatically issued after the switching operation.
21
21
Time of the auxiliary contacts type a or type b on closure = Time for the Cs a or b switching over on closure - time of appearance of the voltage at the terminals of the making coil.
Time of the auxiliary contacts type a or type b on opening = Time for the Cs a or b switching over on opening - time of appearance of the voltage at the terminals of the tripping coil. Report Form
22
22
Accessory
23
23
Accessory
24
24
Thanking You