Professional Documents
Culture Documents
Quality Management
Quality: Quality refers to the sum of attributes or properties that describe the product.
Quality is the totality of features and characteristics of a
product or services that bear on its ability to satisfy stated or implied needs.
Quality has different meanings for different people. The American Society for Quality (ASQ) glossary defines quality as: A subjective term for which, each person has his or her own definition. In technical usage, quality can have two meanings: 1. The characteristics of a product or service that bear on its ability to satisfy stated or implied needs. 2. A product or service free of deficiencies.
The above definitions bring out certain distinct features of the term quality Fitness for use: The components are said to possess good quality, if they work well in the structure for which they are meant. Grade: Quality is the distinguishing feature or grade of the product in appearance, performance, life, reliability, taste, odour and maintainability etc. These are generally called as quality characteristics. Degree of preference: Quality is the degree to which a specified product is preferred over competing products of equivalent grade. This is based on comparative tests by customers and is normally called customer preference. Degree of excellence: Quality is a measure of the degree of general excellence of the product. Conformity to requirements: Conformity to requirements is concerned with how well a product conforms to design and other specifications.
Quality History
Quality issues have been of great concern throughout the recorded history of humans. During the New Stone Age, several civilizations emerged, and some 40005000 ago, considerable skills in construction were acquired.
The pyramids in Egypt were built approximately 25892566 BC. Hammurabi, the king of Babylonia (17921750) BC codified the
law, according to which, during the Mesopotamian era, builders were responsible for maintaining the quality of buildings and were given the death penalty if any of their construction collapsed and their occupants were killed. The extension of Greek settlements around the Mediterranean after 200 BC left records showing that temples and theaters were built using marble.
Quality History
From the foregoing writings and many others on the history of quality, it is evident that the quality system in its different forms has moved through distinct quality eras such as: Quality inspection Quality control Quality assurance Total quality However, quality actually emerged as a dominant thinking only since World War II, becoming an integral part of overall business system focused on customer satisfaction, and becoming known in recent times as Total Quality Management, with its three constitutive elements: Total: Organization wide Quality: Customer satisfaction Management: Systems of managing
Total Quality Management Policy deployment Involve suppliers and customers Involve all operations Process management Performance measurement Teamwork Employee involvement Continuous improvement, Empowering people Caring for people & Involvement Compliance to specification Allocating blame
Quality assurance Quality systems development Advanced quality planning Comprehensive quality manuals Use of quality costs Involvement of non-production operations Failure mode and effects analysis Statistical process control
Quality control Develop quality manual Process performance data Self-inspection Product testing Basic quality planning Use of basic statistics Paperwork controls
Inspection Salvage Sorting, grading, reblending Corrective actions Identify sources of nonconformance
3. User-based View:- The goods and services that best satisfy individual consumers different wants or needs are regarded as having the highest quality. This view of quality is personal i.e., perceived quality. It is highly subjective and focuses on issues of fitness for use by the individual consumer 4. Manufacturing-based View: - Focus on producers of goods, works and services and identify quality as conformance to requirements. Once designs or specifications have been established, any deviation implies a reduction in quality. 5. Value-based View: - Quality in terms of costs and price. A quality product is one that provides performance or conformance at an acceptable price or cost. An inexpensive product is expected to be of lower quality than a similar and more expensive product.
Conformance
Durability Serviceability Aesthetics
Dimensions of Quality:
Benefits of Quality:
It gives a positive company image It improves competitive ability both nationally and
internationally It increases market share, which translated into improved profits Overall, it reduces costs, which also translates into improved profits It reduces or eliminates product liability problems, avoiding unnecessary costs It creates an atmosphere for high employee morale, which improves productivity
Types of quality:
scholars breaks down quality into four categories to understand its relationship to competition. Indifferent quality :- Quality that the customer does not notice or appreciate. Expected quality :- Quality that customer expects and demands. One-dimensional quality :- Quality that the customer expects, but that does not necessarily result in lots of order or displeased customer, when lacking. Exciting quality:- Quality that exceeds the customers expectations, attracting favourable attention of customers. It is the quality that pleasantly surprises customers, perhaps creating an order winner.
Levels of Quality:
An organization that is committed to quality must examine quality at three levels: Organizational level Quality concerns centre on meeting external customer requirements. An organization must seek customer input on a regular basis. Customer-driven performance standards should be used as the basis for goal setting, problem solving, performance appraisal, incentive compensation, non-financial rewards and resources allocation. Process level Organizational units are classified as functions or departments, such as marketing, design, product development, operations, finance, purchasing, billing and so on. Since most processes are cross-functional, the managers of particular organizations units may try to optimize the activities under their control, which can sub optimize activities for the organization on a whole. Performance / job level Standards for output must be based on quality and customer-service requirements that originate at the organizational and process level. These standards include requirements for accuracy, completeness, innovation, timeliness and cost
Based on the foregoing, the quality of construction projects can be defined as: Construction project quality is the fulfillment of the
owners needs per defined scope of works within a budget and specified schedule to satisfy the owners/users requirements.
quality assurance(QA) programme and related activities. Effective QC reduces the possibility of changes, mistakes and omissions, which in turn result in fewer conflicts and disputes. Quality assurance (QA) is a programme covering activities necessary to provide quality in the work to meet the product/project requirements. QA involves establishing project related policies, procedures, standards, training, guidelines, and system necessary to produce quality.
Many studies have identified the following objectives, benefits and problems of QA implementation. Objectives: Satisfy the customer's needs and expectations. Satisfy the company's needs and interests. Benefits: Reduce wastage. Enhance team spirit, instil discipline in staff. Reduce staff conflict, enhance job satisfaction. Increase efficiency.
Provide confidence to clients, reduce customer complaints, lower rejection rates, lessen reworks. Improve sales. Shorten lead time. Strengthen relation with subcontractors. Lower cost, increase profit. Improve systems and standardize procedures. Improve workmanship, guarantee quality
Obstacles and problems faced by the whole construction industry in adopting QA are: Short term profit. Low priority on quality. Tendering at lowest price. Multi-layered subcontracting. Adversarial relationship in construction industry. Lack of training. Poor site conditions. Complexity and variability of construction process. Necessity and ineffectiveness of policing quality.
Expensive to develop and implement the scheme. Lack of right decision by top management. Lack of Substantial documents and verification. Lack of qualified staff.
management system to direct and control an organization with regard to quality. A construction contractor usually has three quality documents for running a quality management system. The three quality documents are as follows. Quality Manual Quality Procedures Quality Plan
Quality Manual
This is a company-wide document setting out the general quality policies, procedures and practices of the organization. A quality manual usually comprises the following: 1. Company policy statement which includes a statement, a summary of activities undertaken and the firm's policy, objectives towards implementing a quality system in accordance with the requirements of a standard. 2. General statement to amplify the company's commitment to implementing a quality system. 3. Amendment re-issue and distribution. 4. Authority and responsibility included in the firm's organization. 5. Summary of different procedures.
Quality Procedures
These are documents describing the activities involved in conducting business which are essential to the achievement of quality, e.g. instructions for the production of concrete would require a quality procedure. They are in fact method statements which make reference to relevant specification documents. The quality procedures include the following: 1. Scope and purpose of the procedures. 2. Sequence of actions. 3. Persons responsible in the execution of duties and for ensuring that requirements are met. 4. Remedial actions if non-conformance is detected.
Quality Plan
Besides the quality manual and the quality procedures,
which are applicable to the entire company, there is also a quality plan which is applicable only to a particular project (or a construction contract) undertaken by the company Therefore, there can be a number of quality plans for a company, depending on the number of individual projects it is undertaking. A quality plan is the document derived from the quality system setting out the specific quality practices, resources and activities relevant to a particular contract or project.
Quality system
In a manufacturing factory, material and labour are input through a
series of processes out of which a product is obtained. The quality of the output is monitored by inspection and testing at various stages of production ; and any nonconforming product found is either repaired, reworked or scrapped. In construction, the scenario is similar except that if anything goes wrong, the nonconforming work is very difficult and costly (and sometimes even impossible) to rectify Consistency of operation involves three basic functions: say what you do, do what you say, and record what you have done. This can be achieved by establishing a quality system in the organization and maintaining it to be effective.
A quality system is a framework for quality management. It embraces the organizational structure, procedures, processes and resources needed to implement quality management. Purpose of quality system The quality system of an organization clarifies the authorities and responsibilities of the staff and their interrelations. It standardizes the administrative and the work procedures. It regulates the conduct of verification activities. It generates permanent records showing that the prescribed activities of verification have been performed and the required quality has been attained. It regulates the conduct of the different processes and prevents side-stepping.
A quality system has to cover all the activities leading to the finished
product. Depending on the scope of the project of the organization, these activities include planning, design, development, purchasing, production, inspection, storage, delivery and after-sales service. A reference base is required against which the adequacy of a quality system can be judged. Such a reference base is called quality system standard. The International Organization for Standardization (ISO) went one step further by developing a standard which would be internationally accepted.(ISO1900) Note: in the construction industry quality standards are usually referred to as project specifications, which consists of the customers requirements and all of the stated and implied regulatory requirements.
for taking a systematic approach to managing the business process so that organizations turn out products or services conforming to customers satisfaction in the construction sector. The typical ISO quality management system is structured on four levels, usually portrayed as a pyramid.
2.Quality system
A companys quality system is its blue-print for quality management. It is a means of ensuring the quality of the product. The quality system is to be fully documented with documentation usually in three tiers. The first tier document is the quality manual which covers the requirements of the International Standard to which the quality system is to conform. The second tier documents consist of a number of quality procedures which are referred to by the quality manual.
that define how the activities are performed. The quality procedures and work instructions together ensure consistency of operations.
3.Contract review
Contract review is a preventive measure to avoid any
misunderstanding between the parties to a contract. The first review normally takes place at the tender stage. Before submitting the tender, the contractor should ensure that the requirements of the client are well defined in the drawings, specifications, bills of quantities and other documents, and should clear up any ambiguities and omissions with the architect/engineer. During the progress of the contract, any variation order involving substantial changes in the design or specification of the works, either in kind or in quantity, should be reviewed before acceptance.
Monitoring Responsibility Summary Sheet Project: Owner: Contractor: Consultant: _____________________________ _____________________________ _____________________________ _____________________________
Contract Article
Owner Resp
Contractor Resp.
Overlap Resp
4. Design control
Design control is a key element in ISO. The aim of design control is to ensure that the clients
requirements, including applicable regulatory requirements, are faithfully translated into drawings and specifications. The design is to be reviewed, verified and validated before being released for use; and this applies also to subsequent changes to the design.
control. Obviously the quality system documents are controlled documents. Other documents belonging to this group are those which control the processes of tender preparation, requisition and procurement, staff recruitment, etc.(operation manual) Document control does not affect the contents of the documents, but regulates the administrative processes by which a document is created, revised, distributed, retrieved, archived and disposed of. The control mechanism operates through the following: review and approval of new and revised document before issue by an authorized person; distribution of pertinent issues to prescribed personnel and departments; prompt removal of obsolete documents to prevent inadvertent use; marking of obsolete documents to such effect, if not immediately disposed of.
6. Purchasing
In the construction industry, purchasing refers not only to
procurement of supplies but also to provision of labour and other services. Nowadays there is a tendency for contractor to take up a management role, employing a team of subcontractors to carry out the construction activities and the subcontractors in turn may rely on other subcontractors to work for them. As the main contractor is contractually responsible to the client for the subcontracted work, it is to his advantage and protection to verify that any supplier of material or labour is capable of providing the right product or service at the right time. For satisfactory purchasing, there are two prerequisites, i.e. selecting a supplier/subcontractor capable of providing the supply or service of the intended quality; specifying the required supply or service in sufficient details to avoid ambiguity
provide certain materials or products for incorporation into the finished works. Examples of customer (or client) supplied product are materials that the client trades in, products from his own factory, mechanical plants to be installed in the permanent works, and logos or other signs of distinction. On receipt, these items should be verified as to kind and quantity, properly identified and stored to prevent misuse or deterioration.
prefabricated components. These include precast concrete units and semi assembled steelwork. After the units have passed the appropriate inspection and/or testing, they should be made identifiable as to batch or series. Such markings can simply be painted on the units or indicated with stick-on labels.
9. Process control
Construction processes, including erection of temporary works, pre
casting and prefabrication as well as installation of appliances, should be identified, planned and scheduled well ahead of time. This is normally done soon after the project is commissioned. A construction programme for the entire project, together with the equipment and manpower requirements, is developed long before construction commences. The outcomes of construction planning are incorporated in the project quality plan. The construction processes should be carried out by labour with appropriate skill, using suitable and well-maintained equipment, and under regular supervision. With multi-layers of subcontractors working on site, difficulties are often encountered in satisfying this requirement. Provision of documented procedures or work instructions is essential for non-routine and unconventional processes. These documents have to be prepared specifically for the project.
the project quality plan. On a construction site, inspection and testing is carried out at three stages: on receipt of purchased or subcontracted items or service; during a construction process in which an in-process check is conducted before proceeding to the next step; before final delivery or handover of the finished works.
Materials, components and appliances received on site are subject to
receiving inspection and/or testing. The amount and nature of checking required vary with the degree of control exercised at the suppliers premises and the recorded evidence of conformance.
measuring and testing includes surveying instruments, pre stressing jacks, torque wrenches, weigh-bridges, various testing devices, weighing scales and measuring tapes. Such equipment, both self-owned and hired, should be properly maintained and calibrated at regular intervals as recommended by the respective manufacturers. A schedule of calibration is established and the records of calibration maintained. The equipment should be handled, preserved and stored in such a way as to maintain accuracy and fitness for use.
distinguish a product (or semi-product) which is satisfactory from another which is not. Likewise, in construction, anything that will finally become part of the completed structure should have its inspection and test status identified. This includes bought-in materials and components, as well as the contractors own product either on or off site. The identification is maintained throughout the construction process, from receipt of incoming supplies to handover of the finished works or part thereof.
construction. The nonconformities range from minor discrepancies such as sandstreaking of the concrete surface or using a paint of the wrong colour, to major mistakes such as incorrect level of a floor or non-verticality of a wall. With in-process inspection and testing properly and conscientiously performed, it should be able to discover any nonconformity as soon as it exists. The next step is to identify the nonconforming work so as to avoid it being covered over or built upon. The method to do so depends on the kind of work. The nonconforming work should be reviewed as soon as possible after it is detected. Based on the outcome of the review, the disposition of the nonconforming work is worked out, which ranges from qualified acceptance to reconstruction.
client complaint, the cause of the incident and the situation leading to it are usually revealed. A construction activity might have deviated from the contract drawings/specifications or the workmanship might have fallen short of the specified or implied level of standard. Corrective action is necessary to eliminate the cause so as to avoid recurrence of the untoward event. This may involve amending a documented procedure or work instruction, providing additional resources or training the operational staff. In contemplating the appropriate action, account should be taken of the magnitude of the problem and the risks involved. Corrective and preventive action should be implemented by the authorized person(s) following an established procedure.
protection of prefabricated units in transit. From receipt of construction materials through to handover of finished works, the contractor should exercise control to prevent damage and deterioration.
requirements and effective operation of the quality system. Accordingly, these records fall into two categories which are filed separately. Project-specific records: include pertinent records from the subcontractors, provide evidence showing that the required standards of materials and workmanship have been attained. System-related records: indicate that incidents of non-conformance and client complaints diminish in number with maturity of the system.
Stage 3
When the quality management system is completed and fully approved internally, apply the general quality procedures to specific contracts. Staff should be familiar with quality management and understand their roles. Usually, training would be required. Stage 4 For specific contracts, the firm has to prepare quality plans and additional quality procedures. Stage 5 The quality plan is applied to the specific contract and further training may be required. Stage 6 Internal and external audit of the quality system are being implemented. All quality manuals and quality procedures should be reviewed periodically.
Types of audit
Most audits fall into one of three categories: INTERNAL AUDITS These are audits undertaken by an organization to examine its own systems and procedures. They may be performed by people from within the organization or by teams hired from outside. Note that internal auditors must be independent of the people being audited in order that their objectivity will not be compromised. EXTERNAL AUDITS These are audits undertaken by an organization to examine the quality systems of its suppliers. Again, they may be performed by in-house teams or by outside agencies hired by purchasers.
THIRD-PARTY AUDITS
These are audits undertaken by bodies with no existing or intended contractual relationship with either the purchaser or the supplier. They are almost invariably made against a recognized system standard and include audits by accredited certification bodies. Auditor selection and training Quality auditing is a skilled function and, like all other skills, requires : specific personal talents specialized training and broad experience
Audit procedures
A. PREPARATION On receipt of an instruction to carry out an audit, the lead auditors first action should be to make contact with the auditee and establish that there is a common understanding of the background to, and purpose of, the audit. In carrying out preparations, the auditor will seek to achieve the following objectives: 1. To establish whether the auditee has a documented system capable of satisfying the requirements of the audit. 2. To select matters in the documents which require clarification. 3. To identify the functions or departments in the auditees organization which s/he will wish to examine and to draw up a check-list of questions applicable to each.
B. THE AUDIT It is usual to commence the audit with an opening meeting attended by the audit team and the heads of the auditees departments which are to be assessed. The purpose of this meeting is to ensure that all concerned understand the background and purpose of the audit and are aware of the procedure to be followed.
Typical agenda for an opening meeting:
Introduction Background and purpose Confirmation of audit plan Nomination of escort Identification of auditee management representatives Logistics: working hours, office accommodation, lunch, closing meeting, etc. Questions.
C.REPORT AND FOLLOW-UP The audit reporting procedure will depend upon the type and purpose of the audit. Its primary aim will be to provide information to the party which has commissioned the audit. Objective evaluations of quality system activities by competent personnel should include the following activities or areas: organizational structures; administrative, operational and quality system procedures; personnel, equipment and material resources; work areas, operations and processes; products being produced (to establish degree of conformance to standards and specifications); documentation, reports, record-keeping
INTERNAL/EXTERNAL AUDITS
THIRD-PARTY AUDITS
quality management system implementation. The primary purpose of TQM is to achieve excellence in customer satisfaction through continuous improvements of products and processes by the total involvement and dedication of each individual who is a part of that product/ process. The principles of TQM create the foundation for developing an organization's system for planning, controlling, and improving quality .
the whole to achieve excellence . TQM provides the overall concept that fosters continuous improvement in an organization. The TQM philosophy stresses a systematic, integrated, consistent, organization-wide perspective involving everyone and everything. It focuses primarily on total satisfaction for both internal and external customers, within a management environment that seeks continuous improvement of all systems and processes.
importance of measurement, the role of the customer and the commitment and involvement of employees at all levels of an organization in pursuit of such improvement to fully satisfy agreed customer requirements. TQM is now an integrative approach that forms part of the day-to-day business decision process.
Principles of TQM
Five core principles are embodied in TQM
Supporting Elements
The five principles of TQM can be achieved in an organization with the aid of six basic supporting elements: Leadership: Senior Management must lead this effort by example, by applying the tools and language, by requiring the use of data, and by recognizing those who successfully apply the concepts of TQM. Education and Training: Quality is based on the skills of all the employees and their understanding of what is required. Supportive Structure: Senior managers may require support to bring about the change necessary to implement a quality strategy.
may need to be addressed differently in order to communicate to all employees a sincere commitment to change. Reward and Recognition: Teams and individuals who successfully apply the quality process must be recognized and suitably rewarded, so that the rest of the organization will know what is expected. Measurement: The use of data is of paramount importance in installing a quality process. To set the stage for the use of data, external customer satisfaction must be measured to determine the extent to which customers perceive that their needs are being met.
Construction works are carried out in the form of projects. Projects are becoming progressively larger and more complex in
terms of physical size and cost. In the modern world, the execution of a project requires the management of scarce resources: manpower, material, money, and machines to be managed throughout the life of the project, from conception to completion. The projects have five distinctive objectives to be managed: scope, organization, quality, cost and time. Construction work requires different trades and knowledge but the management, scheduling, and control of those projects utilize the same tools and techniques, and are subject to constraints of time, cost, and quality. There are also unique characteristics of projects, which differ from routine operations.
success while others have suffered dismal failures. Many of the failures can be attributed to a misunderstanding of TQM or the way the organization had implemented TQM.
1. Customer Focus
According to the philosophy of TQM, total customer
satisfaction is the goal of the entire system, and a pervasive customer focus is the means to achieve that. The function of the construction industry is to provide customers with facilities that meet their needs. For a company to remain in business, this service must be provided at a competitive cost. TQM is a management philosophy that effectively determines the needs of the customer and provides the framework, environment, and culture for meeting those needs at the lowest possible cost. By ensuring quality at each stage in the construction process, and thereby minimizing costly rework as well as other costs, the quality of the final products should satisfy the final customer.
and customer. These three roles are carried out at every level of the construction process. The designer is a customer of the owner.
2. Process Improvements A process is a way of getting work done. A process consists of the tasks, procedures and policies necessary to satisfy an internal or external customer need. According to the TQM philosophy, if the process is correct, so will be the end result (product). Thus the organization should work to improve the process so as to improve the end product or service.
3. Continual Improvements The goal of continual improvement is common to many managerial theories; but TQM is unique in that it provides a specific step-by-step process to achieve this. This process consists of nine steps: 1. Identify the process. 2. Organize a multi-disciplinary team to study the process and recommend improvements. 3. Define areas where data is needed. 4. Collect data on the process. 5. Analyze the collected data and brainstorm for improvement. 6. Determine recommendations and methods of implementation. 7. Implement the recommendations outlined in step 6. 8. Collect new data on the process after the proposed changes have been implemented to verify their effectiveness. 9. Circle back to step 5 and again analyze the data and brainstorm for further improvement.
aimed at reducing variability. An organization wishing to support and develop such a process needs to use quality management tools and techniques. It is prudent to start with the more simple tools and techniques: check-sheet, check-list, histogram, Pareto analysis, causeand-effect diagram (Fishbone diagram), scatter chart, and flowchart
Benefits of TQM
From the viewpoint of the individual company, the strategic implications of TQM include: Survival in an increasingly competitive world Better service to its customers Enhancement of the organization's "shareholder value" Improvement of the overall quality and safety of its facilities Reduced project duration and costs Better utilization of the talents of its people
1. Establish as top priority by top management Visionary 3. Establish small teams - give Set aggressive goals overall goals oDefine quality "Walk the talk oIdentify what customers want 2. Cultural change oMeasure and change Paradigm change Credibility development Time 4. Execute change and continuous improvement
Implementing a quality system Quality management system (QMS) is defined as all activities of the overall management function that determine the quality policy, objectives and responsibilities, and implement them by means such as: quality planning, quality Control, quality assurance and quality improvement within the quality system
The trial period Motivation
Training
Internal quality audits Management review