1. Collecting Requirements:
Click to edit Master subtitle style
4/20/12
Requirements Documentation:
Requirements documentation describes how individual requirements meet the business need for the project.
Consumers require healthy, tasty with
some form Basically the government needs income through taxes, employees wants their due share, creditors wants the return on money. So, proper functioning of 4/20/12 factory will provide all of them their due
GAP: Current demand for ice cream is around 160 million liters while its production from documented sector is around 60 million liters that means there is a huge market available though their need is satisfied by small producers but with good brand awareness this market can be captured.With these estimates and calculation we get Gap of around 100 million liters in Pakistan and 60 million liters for Punjab.
4/20/12
2.Define Scope:
. Expert Judgement
Click to edit Master subtitle style
4/20/12
Project deliverables
includes the types of ice cream Kulfa (2 lit) Kulfa (1 lit) Kulfa (cup)
4/20/12
3. Create WBS:
Click to edit Master subtitle style
4/20/12
4/20/12
WBS Diagram:
Market Appraisal License for manufacturi ng Land buying
Availability of utilities
Construction of factory
Recruitment
Buying Machinery
Machinery Installation
Packaging
Transport ation
4/20/12
4. Verify Scope:
Click to edit Master subtitle style
Inspection Inspection includes activities such as measuring, examining, and verifying to determine whether work and deliverables meet requirements and product acceptance criteria. 4/20/12
Change Requests
4/20/12
5. Control Scope:
Click to edit Master subtitle style
Variance control to
4/20/12
4/20/12
1. Define Activities
Click to edit Master subtitle style
The tool used is decomposition which involves subdividing the work packages into smaller, manageable components called activities.
4/20/12
Activity List & Activity Attributes: The activities are as follows: Market Appraisal: The following analysis will be done regarding ice cream`s: overview of industry especially local industry market size demand and supply status availability of raw materials trends of consumers segments analysis 4/20/12 License for manufacturing:
Constructing of a Factory structure: It involves the mapping, tender notice, analysis of quotations that is accepting & rejecting quotations.
Recruitment: Giving an add for hiring the engineers, technitian & other official staff.
Buying machinery: Involves the tender process. Basically the following units are required which includes: 4/20/12 freezing units
Install / deploy machinery: Involves the creation of foundation, setting up of units and connection of units Testing phase Major phase which may consume time if there came a problem in machine. Raw Material purchase Will seek in for Lowest possible price with best quality material. Required raw materials are: 1.Milk 2.Butter 3.Sugar 4.Eggs 4/20/12 5.Dry Fruits
Manufacturing Process
Raw material delivery & storage Blending the mixture Pasteurizing Homogenizing Cooling Adding flavor Continuous Freezing Adding extra Fruits and chunks Packaging
4/20/12
Source:
4/20/12
Source:
4/20/12
Milestone List: To get the licence, Avail resources, Buying machinery End product manufacturing.
4/20/12
2. Sequence Activities:
TOOLs & Technique: The tool used for network diagram is Project Diagramming Method (PDM).
4/20/12
OUTPUT
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 Prior Activity None 1 2 3 3 3 3 5 8 9 10 11 12
4/20/12
2 13
11
PDM
10
12
4/20/12
Project deliverables
includes the types of ice cream Kulfa (2 lit) Kulfa (1 lit) Kulfa (cup)
4/20/12
4/20/12
1. Define Activities
Click to edit Master subtitle style
The tool used is decomposition which involves subdividing the work packages into smaller, manageable components called activities.
4/20/12
Activity List & Activity Attributes: The activities are as follows: Market Appraisal: The following analysis will be done regarding ice cream`s: overview of industry especially local industry market size demand and supply status availability of raw materials trends of consumers segments analysis 4/20/12 License for manufacturing:
Constructing of a Factory structure: It involves the mapping, tender notice, analysis of quotations that is accepting & rejecting quotations.
Recruitment: Giving an add for hiring the engineers, technitian & other official staff.
Buying machinery: Involves the tender process. Basically the following units are required which includes: 4/20/12 freezing units
Install / deploy machinery: Involves the creation of foundation, setting up of units and connection of units Testing phase Major phase which may consume time if there came a problem in machine. Raw Material purchase Will seek in for Lowest possible price with best quality material. Required raw materials are: 1.Milk 2.Butter 3.Sugar 4.Eggs 4/20/12 5.Dry Fruits
Manufacturing Process
Raw material delivery & storage Blending the mixture Pasteurizing Homogenizing Cooling Adding flavor Continuous Freezing Adding extra Fruits and chunks Packaging
4/20/12
Source:
4/20/12
Source:
4/20/12
Milestone List: To get the licence, Avail resources, Buying machinery End product manufacturing.
4/20/12
2. Sequence Activities:
TOOLs & Technique: The tool used for network diagram is Project Diagramming Method (PDM).
4/20/12
OUTPUT
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 Prior Activity None 1 2 3 3 3 3 5 8 9 10 11 12
4/20/12
2 13
11
PDM
10
12
4/20/12
3. Estimate Activity Resources Tools & Technique: We will use the tool of Expert judgement and alternative analysis.
4/20/12
Activity Resource Requirements: Manpower Resource requirements can be bifurcated into HR Executive officials Engineers Technical staff Blue colar staff Raw Material s required for initiating production are as follows: Milk Sugar Butter Fruit pulps Dry fruits Project Document Updates: The documents are updated with the information contained in this section. 4/20/12
15% probability of exceeding 1 month & 85 % probability of completion in the 4/20/12 given time.
5. Develop Schedule:
Click to edit Master subtitle style
Tools & Techniques: Gantt chart
4/20/12
4/20/12
6. Control Schedule:
4/20/12
Performance reviews will be done to measure, compare, and analyze schedule performance such as actual start and fi nish dates, percent complete, and remaining duration for work in progress.
Variance Analysis
4/20/12
Organizational process assets that may be updated includes the following: Causes of variances,
4/20/12 Corrective action chosen and the
4/20/12
Quality control
Blending
Mixing units Storage units Freezing units Homogenizer Brine tank Surface cooler Filling and Packaging line 36F (2C) 1,000 gal (3,7851) stainless steel blender Blended for eight to te minutes.
Pasteurizing
To kill the bacteria. Pasteurization machine Thin stainless steel plates. High-pressure piston pumps; Breaks down the fat particles The process of homogenizing will be
Homogenizing
182F (83C) flows on the one side of the plates 180F (82C) water to kill bacteria. Air pressure of 2,000 pounds per square inch (141 kg per sq cm) Mixture: 36F (2 C)
Cooling
Plan quality
Quality assurance
Quality control 300 gal (1,136 1) of mixture 700 gal (2,650 1) per hour. Temp inside refrigerator: -40F (40C), Star wheel in premeasured amounts Premeasured amounts of ice cream at the rate of 70-90 cartons per hour.
Adding flavors
Continuous freezing
Flavorings are then piped into the vats and will be blended thoroughly Liquid ammonia will be using as a freezing agent. Soft-serve ice cream.
Hardening
Fruit feeder: strawberry or cookie chunks are evenly distributed. Automatic filling machines Cardboard cartons Lids Expiration date Production code Plastic shrink wrapping. The cartons move slowly back and forth through the tunnel for two to three hours until the contents are
-10F (-23C).
4/20/12
4/20/12
ESTIMATE COST
(Rs in (000) SNO 1 2 3 4 5 6 7 8 9 10 11 TOTAL FIXED COST INITIAL WORKING CAPITAL TOTAL COST OF PROJECT DESCRIPTION land building machinery local machinery imported inland charges erection & installation charges contingencies furniture & fixture vehicles reproduction expenses interest during construction 329570.398 50628 380198.398 TOTAL COST 175235 57798 570 44719.398 20 200 5000 5000 12500 1000 27528
4/20/12
ESTIMATE BUDGET
DESCRIPTION raw material labor manufacturing overheads depreciation administration & general expenses selling expenses interest amortization of preproduction expenses TOTAL sales value of production Breakeven point VARIABLE COST 572140 37194 37406 0 0 28 0 0 FIXED COST 0 0 171700 8315 3876 0 37534 333 TOTAL COST 572140 37195.2 209106 8315 3876 28 37534 333
221757
868526
0.47
4/20/12
CONTROL COSTS:
Set up time After the cleaning, pipes used for making closed-loop cleaning are disconnected andnozzles are installed back to their place
Holding cost holding one unit of product over a unit of time (one
simply states that inventory level at the end of any given period must be equal to the inventory level atthe end of the previous period plus planned level of production less the forecasted sales during this same given period.
4/20/12
No shortage constraint products should always be available to the
Project HR management
4/20/12
appropriately Food
Project Office
used
Administration Administration
4/20/12
The role and responsibilities of the project coordinator is to be accountable at every phase of development of the ice-cream factory
4/20/12
should effectively negotiate and influence others who are in a position to provide the required human resources for the project hence an experienced person should be hired who has worked on the pervious related project and should work as a leader to carry out the initiative
Environmental factors
I f the human resources are not available due to
constraints, economic factors, or previous assignments to other projects, the project manager or project team may be required to assign alternative resources, perhaps with lower competencies, provided there is no violation 4/20/12 of legal, regulatory, mandatory, or other specific c
effective project teams is one of the primary responsibilities of the project manager
teamwork.
providing challenges and opportunities, by providing timely feedback and support as needed, and by recognizing and rewarding good performance
High team performance can be achieved4/20/12 by using open and
effective
communication,
developing
trust
among
team
management skills for fostering teamwork and integrating the efforts of team members to create highperformance team
4/20/12
Project communication
4/20/12
Program Meetings Program Kick Off Meeting Program Lead Bimonthly meeting ( once in two months) with the Program
4/20/12
Communication
Frequency
Audience
Bi-monthly
Monthly
4/20/12
PROJECT PROCUREMENT
4/20/12
Procurement of machinery
Continuous Freezer Homogenizer (1000lt/hr) Homogenizer (500lt/hr) PHE Chiller (1000 lt/hr) PHE Chiller (500 lt/hr) Cold Room
5 1 1 1 1 2 2
4/20/12
Contd..
Ammonia Compressors (5/5) Pasteurizer (1200Ltr) Ageing Vat
1 1
5 2 1 1 1 1 2
Candy Making Machine Pad Tanks Ice Bank (30000Ltr) Hot water generator
PROJECT MANAGEMENT
RISK
4/20/12
Risk mananagement
.There are a couple of possible hazards,
which could be associated with ice cream. Some of the basic bacteria according to HACCP in ice cream manufacturing are:
4/20/12
4/20/12
4/20/12
4/20/12
4/20/12