UPDATE ON EDI RESTRUCTURING

PRESENTATION TO CITY POWER EXCO

14 MARCH 2008

PRESENTATION OVERVIEW
Update - National EDI Restructuring RED 4 Where are we Our Expectation from City Power Discussions / Q&A

21 May 2012

Slide 2

UPDATE ON EDI RESTRUCTURING


Policy Environment
EDI Reform is a national imperative Mandate remain unchanged from National Government Speed of reform process Resolution of enabling policy framework RED Establishment Legislation Asset Transfer Framework Surcharge Principles Framework National BP&S Strategy Employee Collective Agreements

New approach Deal negotiation at national level EDI Restructuring During the Current Electricity Crisis

21 May 2012

Slide 3

UPDATE ON EDI RESTRUCTURING


Other Focus Areas
Increasing Municipal State of Readiness Accession Agreements MSA Section 78 Process Ringfencing Process Funding Panel of Service Providers Increasing Communication and Public Awareness Campaigns

21 May 2012

Slide 4

RED FOUR WHERE ARE WE


Parties
Eskom Central Region CoJ City Power 24 Local Municipalities

Establishment Approach
Phased approach Critical Mass (Eskom Region, CoJ, Emfuleni, Mogale City)

Operational Project Governance Structures Approved Establishment Project Plan Programme Phakama

21 May 2012

Slide 5

Proposed Critical Path


February 08
12 months KEY IMPLEMENTATION ENABLERS (June 2008)
Agreement on DAY ONE DATE By Sponsors Comm.
Systems solutions (end April 2008) Ring-fencing (end July 2008) MSA Section 78 (end June 2008) Municipal & Eskom Distribution Business ready for transfer to the RED (end November 2008)

March 09

DAY ONE (March 2009)

Parallel Day One Roadmap implementation

License application to NERSA SDA drafted and signed SLAs drafted and signed Three year Business Plan in place

Register RED FOUR Company


Appoint a RED FOUR CEO, Board and Senior Management

Communication, Change Management and Project Management

21 May 2012

Slide 6

RED FOUR Critical Mass Participants


Entity Name Electricity Sales RED % Customer Numbers RED % Co-operative Agreement Section 78 Status Ringfencing %

Eskom Central Region City of Johannesburg (City Power) Emfuleni Mogale City

25.42% 51.10%

48.30% 23.60%

Y Y Y Y

N/A X

100% 100%

9.77% 3.08%

5.50% 4.30%

Y Y

Y -

Y -

X -

20% 15%

X - Currently busy with (i.e. not completed)

21 May 2012

Slide 7

RED FOUR State of Readiness: Summary


ACCESSION AGREEMENTS All municipalities have signed the Accession Agreement LEGISLATIVE COMPLIANCE CoJ and Emfuleni : Started with MSA S78 (3) process

RINGFENCING
Emfuleni (20%) Mogale City (15%) Eskom (100%) CoJ/City Power (100%)
21 May 2012
Slide 8 Slide 8

Project Governance: RED FOUR


#
1

Governance Structure
Sponsors Committee

Status
Established

Key Decisions
The next Sponsors Committee is scheduled for April 14, 2008. REF met yesterday, next one scheduled to take place on July 10, 2008. The next TSC is scheduled for April 02, 2008.
Most re-launced in February 2008

Regional Engagement Forum

Established

Technical Steering Committee

Established

Workgroups

Established

RTLRS

Established

Awaiting direction from National TLRS on way forward.

21 May 2012

Slide 9

OUR EXPECTATIONS FROM CITY POWER


City Power is Proof of Consolidation Concept Leadership
Importance of CoJ

Active Participation in RED Project Governance Structures


Sponsors Committee Technical Steering Committee, REF Working Groups

Involvement and Fast-tracking of the MSA Section 78 Process

Programme Phakama

21 May 2012

Slide 10

THANK YOU