Switchyard: Purpose and main parts Pre- Commissioning Requirement Switchyard Equipment Commissioning process: Circuit Breaker Isolator pantograph and line isolator CT CVT Lightening Arrestor (LA) Earth Switch Integrated checks Conclusion
PMI Revision 00
SWITCHYARD
Purpose : Transmit the electricity generated up to load centre Proper control and protection Communication Exchange of power in emergency Main parts : Control room Relay room EHV yard Compressor room, battery room,
PMI Revision 00
PMI Revision 00
ENSURE THAT THE EQUIPMENT IS PROPERLY ISOLATED FROM SUPPLY AND EARTHED. ALSO, THE BAY NO / CONTROL PANEL NO. IS CORRECTLY IDENTIFIED.
PMI Revision 00
Power supply Skilled / unskilled manpower Testing and commissioning equipments Drawings, schematic diagrams and technical Literature Spares
Cable schedules and proper termination Fuse ratings and Relay setting calculation
PMI Revision 00
Check operating mechanism and alignment Check aux. contacts, coil healthiness and control wiring Check hand valves, drain plugs, pr. Relief valve, pr. Gauge etc Check ac and dc supply, control wiring and relays, timers, indications, Check safety valve operation Contact resistance measurement Other checks to specific type of circuit bkr ( e.g. pressure test for ABCB) Functional checks : Close & open time; anti pumping operation, pole discrepancy , manual and protection trip, interlocks
PMI Revision 00
ISOLATORS
Physical inspection :. Foundation bolts, insulator supporting bolts etc tightened Erection work completed. Cleaning of insulators, corona rings etc. Lubrication of all moving parts. Proper earthing of structure base, operating mech box, Mechanical interlock between isolator and earth switch. IR value bet. current carrying parts and earth (5KV megger) Contact resistance Functional checks : Local and remote operation, indication Thermal Overload : Check after a number of operations Electrical interlock between isolator and circuit breaker. On / Off timing, Limit switches, aux contacts
PMI Revision 00
CURRENT TRANSFORMERS
Physical Inspection : Cleaning &Tightness of terminals, earthing connections, corona rings Check the name plate details Oil level OK, no oil leakage Check external wiring I R value (5KV megger) : Pri - E, Pri - Sec (500 v megger): Sec - Sec of other cores Winding resistance Primary injection Polarity Secondary injection Magnetising characteristics and knee point
PMI Revision 00
PMI Revision 00
10
PMI Revision 00
11
BATTERIES
Battery room : Cleaning, ventilation, fire protection system, distilled and running water, floor and walls to be acid resistant, safety equipments e.g. goggles, aprons, gloves torch etc to be made available. Battery cells : no leakage of electrolyte, vent and caps Ok, polarity correct, inter cell links tightened and greased, electrolyte level and sp gravity ok, Charging and discharging cycle as per manufacturers recommendation. Capacity test
PMI Revision 00
12
CONCLUSION
Original equipment quality + good commissioning = trouble free performance year after year Commissioning results to be interpreted considering Manufacturers specifications Trends Limitations of sampling and measurement External factors like temp. humidity etc