Professional Documents
Culture Documents
Shriram M. Oka
Agenda
Project Scope & Contract Terms Project Schedule Project Cost Project Quality Project Safety Working Capital & Generation of Free Cash Managing People / Client Managing Risk
What is a Project?
A collaborative endeavor to develop and deliver a Unique end-product in given time, managing available resources, executing work within set safety regulations & ensuring Internal /External customer satisfaction. Keywords:
Project Lifecycle
Stakeholders
End user / Client PM Consultant / Design Consultant Contractor Vendors Subcontractors Govt. Bodies / Statutory Authorities Others
Project Management
Project Scope & Contract Terms Time / Schedule Cost Quality of work & Quality of end product Safety of staff / labor Working Capital & Generation of Free Cash People / Client Risk
Project Scope
Payment Terms Advances & Retention Monies Bank Guarantees (ABG , PBG, EMD) Eg Maintenance of facility post commissioning
Types of Contract
Lump-sum Unit Rate (Priced BOQ) Cost Plus Margin BOOT Turnkey EPC (Total scope with 1 party) Design & Build (3rd party F.E.E.D and/or PMC) Supply Contract / Erection Contract
Managing Time
Multiple inter-dependant activities Parallel work fronts Limited available Time Limited Resources
Hence, activity planning is of utmost importance to finish the total scope of work, as per contract, within the given time duration.
TASK-3
TASK-4 TASK-5
5 WEEKS
4 WEEKS 6 WEEKS
TASK-2
_ TASK-4
6
4 6
TASK-6
TASK-7
4 WEEKS
3 WEEKS
TASK-4
TASK-3,5,6
3
3
Gantt Chart
Critical Path
Work with existing Resources & deliver the project with Time delays Increase Resources, use expensive High-end P&M or highly skilled sub-contractors & crash Activity durations. Deliver on time, but at significantly higher cost!
Cost Control A project needs to be executed NOT AT ANY COST, but within a defined BUDGETED COST
Budgeted Cost (ACE) Periodic Monitoring of Cost against ACE (JCR) Variation Analysis
Software used at site to Transact W.Os / P.Os, Record & Monitor Cost incurred - CeMa. Software used at RO /HQ to Transact W.Os / P.Os, Record & Monitor Cost incurred - EIP
Each activity consumes resources pertaining to: L Labor M Supply Materials P Plant & Machinery Sc Sub Contractor & Specialized Agency While preparing ACE, the planning eng allocates a Cost Budget to each activity, that combines all the 4 resource elements L,M,P,Sc.
Monitoring performance
Monitor Cost to date & ETC periodically Analyze variation in Unit Rates
Quality
The lowest project Cost is achieved when every activity is executed at the optimum level of Quality!
Zero Defects Do it right the first time, every time! How to achieve Exceptional Quality? Plan Do Check Act
Excellence of Detail Engg (Team Review of Dwgs) Selection of Vendor (PQ) Selection of Subcontractor (PQ) Stringent Material Inspection & Material Storage Norms Well-defined Work / Erection Procedures Qualitative & Regular Audit of Erection Activity Sharpen the Axe : Regular Training to Staff / Workmen
Safety
Safety encompasses:
Health of workmen / staff Safety of workmen / staff (PPE, scaffolding etc.) Environmental Protection
Cash Flows
Key People
S .No 3 is easiest to achieve, failure to implement this skill leads to uncontrollable situations
Managing Risk
Risk Management is The identification, assessment, and prioritization of risks Minimizing the occurrence and monitoring & controlling the impact of unfortunate events
Risk Assessment
Sr. No. 1 Identified Risk Probability (a) Most Likely Impact (b) Major Risk Rating (a) * (b) Critical
1)
95% will be paid after commissioning of entire SS Incomer is a 220kV UG Cable(Not in L&T Scope) In such a situation, the payment may be held up till UG Cable is laid and charged
2)
3)
Request for amendment in payment terms (Milestone based) Monitor Cost over Invoice Plan Supply such that project cash flow is positive
Possible
Moderate
High
To negotiate with vendor and make specific delivery arrangements Put stringent LD terms on vendor
Probability
Unlikely
Rare Insignificant
Medium
Minor
Moderate
Major
Extreme
Impact / Consequence
Low High Critical Risk Rating
Thank You
25